newrecordconfirmed The state's first public notice (RDCC, April 20, 2026) called it an industrial and power project; no nuclear, no name
2026-04-20 · csite-032 · Resource Development Coordinating Committee, Utah Trust Lands Administration, Carbon County

The Resource Development Coordinating Committee's public project layer (the data behind rdcc.utah.gov) holds project 87203, 'SULA 2095 - Lease Agreement with possible option to purchase', sponsor Trust Lands Administration, created 20 April 2026 with a comment deadline of 18 May 2026, legal description 'T14S, R11E, Sec. 16 N2, SW4', Carbon County, local government contacted 'Y' on 20 April 2026, status 'State Comment Published'. Its abstract says TLA received a lease application 'from a private entity' for 'a large-scale industrial project' including manufacturing, 'power generation infrastructure' and other industrial uses, with a possible purchase option, on 480 acres. It lists impacts as permanent land-use change, landscape change, traffic and 'noise associated with manufacturing and power generation'. It does not name Valar or mention nuclear reactors, fuel or radioactive material. This matches the memo's statement that the proposal ran 30 days on the RDCC dashboard and went to the county (csite-005); the only comment the memo records is from the Division of Water Rights (mine-012). The same layer holds the Guard lease on the section, 'SULA 1321 - Utah National Guard Training Area' (project 588), whose document link is filed under 2001.

In plain termsRDCC is the state's clearinghouse where agencies and local governments can comment on projects on state land. The Wellington lease was posted there from 20 April to 18 May 2026, and Carbon County was formally contacted on 20 April, more than two months before the commissioners signed their letter of support. The posting described a big industrial and power-generation project, which is accurate as far as it goes, but did not say the power would be nuclear or who the company was. A reader of the state dashboard would not have known this was a nuclear campus.
verified 2026-09-29: Holds. Re-queried 2026-09-29: RDCC public layer, projects 87203 (created 2026-04-20 17:14 UTC; comment deadline 2026-05-18; local government contacted Y on 2026-04-20; status 7 = 'State Comment Published') and 588. Abstract quote exact. The 2001 date for SULA 1321 now rests only on the record's document link, as stated.

In tabs: carbon_site, process, government, timeline · file carbon_site