Carbon & Emery
Local happenings: commission and planning agendas, hearings, votes, public comment, local news.
The Carbon County Board of Commissioners' notices on the Utah Public Notice Website show regular meetings on the first and third Wednesdays at 4:30 p.m. (3 and 17 June, 1 and 15 July, 19 August, 2 and 16 September 2026; the 5 August meeting was cancelled), at 751 E 100 N, Price. Wednesday 7 October 2026 is the first Wednesday of October; as of 29 September no notice or agenda for it was posted. The most recent agenda, for 16 September, was posted on 10 September, six days ahead; it had no Valar, nuclear or Section 16 item and listed no public-comment period. The day before, Tuesday 6 October, is the Planning Commission, whose agenda (posted 23 September) has one permit item, the Altigen technology park (no record links it to Valar), and an item 'Updates on Previous Items and Upcoming Projects' (dir-015). No Valar item has been found on any Carbon County agenda posted so far, and no county permit application by Valar was found (csite-012). The county's rules for 'highly contested industries' are at the drafting stage, with a hearing planned for November (csite-013); under Utah Code 17-79-803 an application is judged by the rules in effect when it is complete unless the county formally started changing them first (dir-014), and the Trust Lands memo describes a county conditional use permit with notice and a public hearing as part of the process for the lease (csite-015).
- Carbon County Board of Commissioners: notices (June to Sept 2026) (Utah Public Notice Website) primary government “Commission Meeting”
- Carbon County Commission Meeting, September 16, 2026 (notice and agenda, posted September 10) (Utah Public Notice Website, 2026-09-10) primary government
- Carbon County Planning Commission Regular Meeting, October 6, 2026 (notice and agenda) (Utah Public Notice Website, 2026-09-23) primary government “Updates on Previous Items and Upcoming Projects”
The Carbon County Planning Commission meets 6 October 2026 at 4:30 p.m. in the Commission Chambers, 751 E 100 N, Price (in person only per the notice). Its one permit item is a conditional use permit for 'a phased Technology Park and associated infrastructure located East of Wellington' on parcels 2A-1320-0000 and 2A-1656-0000 for Altigen JS, LLC and Duct Tape, LLC (csite-012). The application's vicinity map ('Project Jurassic Spark', Sept 2026) covers all of Section 36, T14S R11E and all of Section 2, T15S R11E, along U.S. 6. County parcel records list 2A-1320-0000 at 640 acres and 2A-1656-0000 at 600.74 acres, both assessor class 'Commercial' and neither in the state's government-owned parcel layer (privately owned); the county zoning map shows both in the Mining & Grazing zone (dir-013). In May the county agreed to begin holding a BLM gas-pipeline right-of-way for Altigen, whose stated plan is natural-gas power plants on private land east of Wellington (mine-050). The project lies about three miles southeast of Section 28 and about four miles from Section 16, which the state approved leasing to Valar. No record read links this project to Valar.
- Carbon County Planning Commission Regular Meeting, October 6, 2026 (notice and agenda) (Utah Public Notice Website, 2026-09-23) primary government “a phased Technology Park and associated infrastructure located East of Wellington”
- 2026-Altigen Region Map (Project Jurassic Spark CUP application, Exhibit A, vicinity map) (Altigen JS, LLC (via Utah Public Notice Website), 2026-09-28) primary filing
- Carbon County parcels (UGRC LIR): 2A-1320-0000 and 2A-1656-0000 (Utah Geospatial Resource Center / Carbon County Assessor, 2025-11-26) primary government
Mining-claim markers stand in Carbon County. The Notice of Location posted at one of them (fld-002) names Valar Atomics Inc as locator of the RW 453 lode claim in Section 28, Township 14 South, Range 11 East, about 3.4 miles northeast of central Wellington, measured to the section's centre (BLM survey grid, dir-002).
- Field observation (September 2026) (resident, 2026-09) resident fieldwork
The Planning Commission's notices on the Utah Public Notice Website from 5 May to 6 October 2026 (eleven in the website's notice list; the body page itself shows ten) list rezones, subdivisions and routine hearings, and no item for Valar, a reactor, Section 16 or the Wellington trust-land parcel. The June and August 2026 minutes (scanned; read by OCR) do not mention Valar. The agenda for 6 October 2026 (posted 23 September) has one land-use item: possible approval of a conditional use permit for 'a phased Technology Park and associated infrastructure located East of Wellington' on two parcels for Altigen JS, LLC and Duct Tape, LLC, with an attached 'Project Jurassic Spark' region map (added 28 September); Altigen's gas pipeline was before the County Commission in May (mine-050). The October notice says it was sent to a local newspaper, radio stations KOAL and KUSA, ETV Channel 10 and the state website. As of 29 September 2026 no Valar conditional use application, site plan or rezone appears in these records.
- Carbon County Planning Commission: notices (May 5 to Oct 6, 2026) (Utah Public Notice Website) primary government
- Carbon County Planning Commission Regular Meeting, October 6, 2026 (notice, agenda, Altigen region map) (Carbon County Planning Commission (Utah Public Notice Website), 2026-10-06) primary government “a phased Technology Park and associated infrastructure located East of Wellington”
- 2026-08-04 AUG MINUTES-SIGNED (Carbon County Planning Commission; scanned, read by OCR) (Carbon County Planning Commission (Utah Public Notice Website), 2026-08-04) primary government
What the state and counties have offered or given (as of 29 Sept 2026): a REDTIF post-performance refundable tax credit of up to $106,737,499 over 10 years, approved 9 July 2026 and not yet earned (fund-017, csite-024); use of the state-owned San Rafael lab and its shared facilities, terms not public (fund-015, gov-011); Emery County's direct sale of the 112.7-acre lab-side parcel at its appraised $394,500, without competitive bidding (gov-022); that parcel's placement in an Inland Port tax zone, whose status the county and the port authority record differently (gov-018, gov-023); and the Trust Lands 50-year Carbon County lease (480 acres at first, up to 640) with a purchase option, approved 17 Sept 2026 (mine-011, csite-004); no tax incentive for the Carbon campus was found (csite-029). No state or county cash grant to Valar was found in the board, county and legislative records read (state vendor-payment data on Transparent Utah was not searched; open question). What Valar pays or has promised to pay public bodies: $394,500 for the Emery parcel (gov-022); a $400,000 bonus plus rent of $30 an acre a year rising to $625 by year 8 on the Carbon lease, which staff estimated at about $35 million over 50 years (mine-011); a $20,000 outside-district water connection approved for Valar by a local district (loc-015, loc-017); and the proposed $20 million supercritical-CO2 test heater it would fund and hand to the state lab, of which only a $400,000 design phase was approved (gov-014). The known one-time amounts come to about $815,000 ($394,500 + $400,000 + $20,000); first-year rent on 480 acres at $30 an acre would be about $14,400. Utah's Legislature separately spent public money on the lab before Valar came (fund-015). What Valar pays in taxes was not found in public records; the tax credit application projects $213,474,999 of new state revenue over 10 years (fund-017), a projection in the application, not revenue earned.
- GOED Public Board Materials, July 9, 2026: GOED Board Executive Summary, Valar Atomics Inc. (Board of the Governor's Office of Economic Development (Utah Public Notice Website), 2026-07-09) primary government “Incentives are site specific and subject to local incentive participation.”
ETV News describes itself as a free weekly delivered to every home and business in Carbon and Emery counties (circulation 13,800), with a website and cable channels that air government meetings; its contact address is at emerytelcom.com. The two other local papers' sites (Sun Advocate, Emery County Progress) did not answer (sources_not_read). ETV's search feed for 'valar' returned 48 items: 47 from 3 July 2025 to 23 September 2026 and one unrelated 2017 column; 46 of the 47 name Valar in their text and one (a 25 February 2026 Carbon Commission report) refers to the Emery reactor without naming the company. All 47 were checked. Two 2025 items told readers the plan was bigger than one test reactor: the 17 September 2025 state release on the groundbreaking ended with Valar's description of itself as building 'gigasites' of thousands of reactors, and a 10 October 2025 article reported that Valar's 'current plan' was a manufacturing hub in Carbon County after about three years (loc-034); neither named a site. The first report of the Wellington lease is dated 18 September 2026, the day after the vote (mine-041); no earlier item links Valar to Wellington, the Section 16 trust land or a Carbon lease (two earlier items mention trust land in other contexts: 640 acres across the road from the Emery lab, 9 April 2026, and a Farm Bureau speaker on the Trust Lands permit process for solar, 1 May 2026). Six items are press releases printed as articles: from the state lab (23 Jan and 23 Sept 2026), from Valar (24 Feb 2026), from the Office of Energy Development (17 Sept 2025, orig-067), from USU Eastern (26 Mar 2026) and from Southern Utah University (19 Sept 2026). Most of the rest are meeting reports. Residents' concerns appear in them (the June 2025 county hearing on nuclear, the April 2026 land-sale hearing, a resident's data-center presentation in July 2026, a candidate forum where one candidate called nuclear the most expensive source), but no ETV item read quotes an independent expert assessing Valar's reactor or its safety. ETV's post-vote article (18 Sept) reports the lease terms and supporters' remarks and notes that permits are still needed; it reports no opposing comment, which matches the hearing record (mine-014).
- About Us - ETV News (ETV News) news
- ETV News search feed for 'valar' (RSS, pages 1-3, 48 items; re-read 29 Sept 2026) (ETV News) news
- Valar Atomics secures land agreement for Carbon County project (Stephanie Olsen) (ETV News, 2026-09-18) news
- Rapid construction from local contractors at Valar Atomics (USREL press release) (ETV News, 2026-01-23) primary government “will house Valar’s fuel fabrication facility”
- Utah San Rafael Energy Lab gives update on projects (USREL press release) (ETV News, 2026-09-23) primary government
- Valar Atomics welcomes community for reactor facility open house (Valar Atomics press release) (ETV News, 2026-02-24) primary company “it is not a commercial power plant”
- Valar Atomics breaks ground on test reactor at the Utah San Rafael Energy Lab (Utah Office of Energy Development press release) (ETV News, 2025-09-17) primary government “Valar Atomics is building America’s first nuclear gigasites”
- What’s actually happening at the Utah San Rafael Energy Lab? (Susanna Watts) (ETV News, 2025-10-10) news “their current plan is to build a manufacturing hub in Carbon County”
As of 29 September 2026, testing against local records the view that the Carbon site should have been handled in public and that residents did not know. What holds for the company: in Emery County Valar appeared before towns, districts and residents at least 15 times and held open houses (loc-027); Emery's land sale was noticed by name and heard (loc-007); its fuel plant was disclosed in public (loc-016); and in 2025 the local paper printed Valar's 'gigasites' aim and reported a plan for a Carbon County manufacturing hub, without a site (loc-034). What the record shows on the Carbon site: the state's newspaper notice named no applicant or use (loc-032); no report or minutes of Valar's June-September appearances before Carbon bodies, including a Price council work session, name the Wellington site (loc-012); the local paper first reported it the day after the vote (loc-011); a week before the vote the CEO spoke publicly of hundreds of reactors in Carbon and Emery without, as reported, naming a site (loc-001); a commissioner said project NDAs are usually companies' demand (loc-002), and the county's own minutes record it kept a 'strict' NDA on a different factory prospect until August 2026 (loc-036); no NDA with Valar was found. Gaps between words and records: the state lab director, as ETV reported, said firms must show 'no dose' at the fence, while Valar's own analysis gives a small dose (loc-035); Carbon commissioners called the test reactor 'commercial' and the data center waterless (loc-005); a local report of a chamber tour said meltdown risk is gone (loc-006); Valar told Castle Dale its reactor needs about 10 acre-feet of water for industrial use while DOE's review lists only domestic use (loc-025); officials and the state port authority describe the Emery land as sold while Valar said in August it awaited clean title (loc-014); Valar said it 'relocated' from California while most of its openings are there (loc-029); in April Valar said many of its 120 Emery workers did not live in Utah (loc-004). Process gaps: district minutes record a staff report that Valar tied into the sewer 'without prior authorization' (loc-015); the state declined to review the reactor building's fire plans and no record shows who did (loc-018); Emery had no nuclear zoning rules and has now paused new major permit applications (loc-024); Orangeville is drafting a zone for Valar's land with Valar's lawyers reviewing, no hearing yet (loc-013); no water-right application by Valar has been advertised (loc-031). None of this shows intent; it shows where the public was and was not given the facts in time to act, and which records requests would close each gap (open_questions).
- TRUST LANDS OPPORTUNITY (legal notice: Township 14 South, Range 11 East, Section 16, near Wellington) (Utah Trust Lands Administration (legal notice published in ETV News), 2026-07-15) primary government “has received an application on the following property near Wellington”
- Community gets closer look at Valar Atomics during open house (Scottie Kraync) (ETV News, 2026-09-14) news “as we grow here in your backyard, in your community”
- Orangeville City Planning and Zoning Commission minutes, July 16, 2026 (notice text) (Orangeville City Planning and Zoning, 2026-07-16) primary government “Everything needs to go through the attorneys from the City and Valar.”
- CVSSD Regular Meeting Minutes, March 19, 2026 (approved) (Castle Valley Special Service District, 2026-03-19) primary government “Valar tied into the county sewer system without prior authorization”
- Emery County Fire Protection SSD meeting minutes, February 17, 2026 (header misprints the year as 2025) (Emery County Fire Protection Special Service District, 2026-02-17) primary government “State agencies declined to perform plan review and recommended third-party review.”
- Castle Dale City Council Meeting Minutes, March 12, 2026 (approved; scanned, read as page images) (Castle Dale City, 2026-03-12) primary government “The reactor requires minimal water—about 10 acre-feet for industrial use”
- August 13, 2026 City Council Minutes (Orangeville) (Orangeville City, 2026-08-13) primary government “waiting on a clean title to purchase the property”
- Leaders look to coal, nuclear and new industry for growth at local energy summit (Kevin Butler) (ETV News, 2026-08-14) news “typically required by private companies considering an area”
- What’s actually happening at the Utah San Rafael Energy Lab? (Susanna Watts) (ETV News, 2025-10-10) news “their current plan is to build a manufacturing hub in Carbon County”
- Aug 19, 2026 Commission Meeting Minutes (Carbon County Board of Commissioners; scanned, read as page images) (Carbon County Commission, 2026-08-19) primary government “The strict NDA was necessary to protect the company's plans”
- Ward250 Nuclear Safety Design Agreement (Document 100403, Revision 02, marked draft, October 2025) (Valar Atomics, 2025-10) primary company “Preliminary results indicate site boundary doses below 0.5 rem Total Effective Dose Equivalent”
A spatial query of both BLM claim layers against the Census boundary of Carbon County (pulled 2026-09-29) returned 10 open claims and 1 recently closed claim. Nine are lode claims AMBERIA 1-9 (serials UT106330298 to UT106330306), created in BLM's system on 9 and 13 November 2023, status 'Filed', in T14S R8E-R9E, about 23 km west of the Trust Lands parcel approved for leasing to Valar (Sec. 16, T14S R11E, see mine-010). The tenth is the placer claim BLACK RIFLE (UT106782094), created 11 February 2026, status 'Filed', mapped to the SW quarter of the NE quarter of Sec. 12, T15S R11E, about 9.4 km south-east of that parcel. An earlier 160-acre placer claim of the same name (UT106369066, created 13 May 2024) in the NE quarter of the same section is now 'Closed'. Claims created since 1 January 2024: 2 (both BLACK RIFLE). No claim name in the county points to Valar, Ward, Valarin or Numenor, and the layer does not show who staked any of them. Distances are between section centroids from BLM's survey grid and the claims' mapped centroids.
- BLM Natl MLRS Mining Claims - Not Closed (feature layer and query results) (Bureau of Land Management (MLRS)) primary filing
- BLM Natl MLRS Mining Claims - Closed (feature layer and query results) (Bureau of Land Management (MLRS)) primary filing
- BOC National County Boundaries Map Service (Census county boundaries served by BLM) (Bureau of Land Management) primary government
- BLM National PLSS CadNSDI, PLSS Section layer (Bureau of Land Management) primary government
The same query for Emery County returned 1,706 open claims (1,390 lode, 316 placer; 563 'Active', 1,143 'Filed') and 354 claims closed within the last year. Claims created in BLM's system since 1 January 2024: 968 still open and 168 closed, 1,136 in all, in 32 name groups. The largest: 'SS' (341 lode claims, January to April 2024, mostly T23S R15E with some in T23S R14E and T22S R15E); 'GP' (90 placer, August 2025, T22S R8E-R9E); 'GREEN' (83 lode, January 2024, all now closed); 'SAB' (71), 'ECC' (70) and 'SWG' (63), lode claims of May to August 2024 in T22S R15E; 'J' (56 lode), 'GRU' (56 placer, August 2025), 'WB' (54 lode); 'BH' (43 lode, February 2026, T18S R10E-R11E) and 'BIG BODY' (31 lode, February-March 2026, T22S R14E). None of the 1,136 names points to Valar or its product names. The public layer shows neither the claimants nor the mineral sought.
- BLM Natl MLRS Mining Claims - Not Closed (feature layer and query results) (Bureau of Land Management (MLRS)) primary filing
- BLM Natl MLRS Mining Claims - Closed (feature layer and query results) (Bureau of Land Management (MLRS)) primary filing
- BOC National County Boundaries Map Service (Census county boundaries served by BLM) (Bureau of Land Management) primary government
Valar's community page for Carbon and Emery counties, read 29 September 2026, describes Ward 250, open houses ('more than 400 neighbors' at the first), town halls, the Emery County Commission's unanimous backing, local partners and news items. The words Green River, Wellington, Beehive, Raceway, BLM, Bureau of Land Management, trust, lease, acres and Price do not appear on it; 'Carbon' appears only in the page's 'Carbon & Emery County, Utah' headings. The company's document library (valaratomics.com/docs) lists five documents (a Series B announcement, the NOVA criticality release, a pilot-program selection, a roadmap and its NRC lawsuit) and no land, siting or environmental document. The page does say Valar 'is building America's first nuclear gigasites', energy campuses powered by fleets of reactors, without saying where; that text is the same in the Internet Archive's copy of 18 September 2026 and on 29 September.
- Castle Country | Valar Atomics (Valar Atomics) primary company “More than 400 neighbors came to our first open house”
- Library | Valar Atomics (Valar Atomics) primary company
- Castle Country (Internet Archive copy, 18 September 2026) (Internet Archive, 2026-09-18) primary company “building America's first nuclear gigasites”
The Trust Lands memorandum says HALEU, LEU+ or LEU feedstock may be delivered to the Carbon site in certified special-nuclear-material containers under NRC, DOT and DOE rules and made into TRISO fuel there. POWER magazine's 19 June 2026 report on Ward 250 noted Utah hosts the nation's only fully licensed operating conventional uranium mill, but said it would add details on fuel sourcing later. POWER's report on DOE's second round of HALEU allocations (27 August 2025) names Antares, Standard Nuclear and Abilene Christian University/Natura as recipients; it mentions Valar only as a Reactor Pilot Program participant. No record read names the supplier of Ward 250's fuel or of Valar's planned feedstock, and none links it to Utah mines or mills. The claims staking in Emery County (mine-003) and the uranium exploration notices there (mine-029) show no link to Valar.
- 8.20.2026 TLA Board Packet (Discussion Item 9A: SULA 2095 OBA, Board Meeting Discussion Memorandum) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-08-20) primary government “feedstock may be delivered to the site in certified Special Nuclear Material (SNM) containers”
- Valar Atomic's Ward 250 Becomes Second Reactor to Go Critical Under DOE Pilot Program (POWER (Sonal C. Patel), 2026-06-19) news
- DOE Allocates Second Round of HALEU Fuel to Three U.S. Nuclear Companies (POWER (Sonal C. Patel), 2025-08-27) news
The Trust Lands memo relays Valar's statement that no Quaternary-active faults lie within the site and that the nearest are the Pleasant Valley fault zone about 20 miles north-west and faults in the Price River area (mine-016). A query of the Utah Geological Survey's Quaternary fault layer on 29 September 2026 found no mapped Quaternary fault within 10 km of the center of Sec. 16; the nearest is 'Price River Area faults' at about 23 km (age under 2.6 million years, slip under 0.2 mm a year), then strands of the Pleasant Valley fault zone from about 37 km (about 23 miles) and the Joes Valley fault zone at about 45 km, one strand of which is mapped as younger than 15,000 years. The company's 'low-seismicity zone' description was not tested here.
- Utah Quaternary Faults (Hazards/quaternary_faults MapServer, distance queries) (Utah Geological Survey) primary government
- 8.20.2026 TLA Board Packet (Discussion Item 9A: SULA 2095 OBA, Board Meeting Discussion Memorandum) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-08-20) primary government “No Quaternary-active faults exist within the site boundary.”
Built or operating: Ward 250 and its fuel lab at the San Rafael lab, Emery County (plan-002); the company's design, machining and test shops in Hawthorne/Torrance, California (plan-008). Used once: the NOVA test core at the National Criticality Experiments Research Center, Nevada, operated by Los Alamos in November 2025 (orig-008). Being acquired: the 112-acre Emery County parcel beside the lab (gov-022, loc-014). Lease approved: on 17 September 2026 the state trust-lands board approved a lease with purchase option for 480 acres of the section north of Wellington, with the other 160 acres to follow if the National Guard's lease there is moved (mine-011, plan-016); no record read shows the lease signed. Applied for: three Bureau of Land Management cases, all in the Price Field Office, all 'Pending' on 29 September 2026: UTUT106784007 'Green River Gigasite Small Modular Reactor/Data Center' (10,270.61 acres, filed 13 February 2026, which Valar told The Washington Sun it no longer pursues, mine-008), UTUT106801248 'Project Beehive Small Modular Reactor/Data Center' (case date 13 April 2026, no acreage shown), and UTUT106833224, a distribution-line case with no name (entered 23 July 2026). NPR reported on 30 September 2026, citing a Valar proposal to federal regulators that NPR reviewed, that Project Beehive would cover over 9,000 acres of BLM land near Price with data centers, some 456 small reactors of 25 megawatts of electricity each, a fuel facility and nuclear-waste storage, with the first reactors in 2028; BLM's Utah office told NPR it had received an application and was reviewing it for completeness. The proposal itself was not found in public records. No BLM rights-of-way case names Valar outside Utah, and its other public layers show no Valar claims, notices, leases or permits (mine-005, mine-030). Program: NRIC's August 2026 Launch Pad round includes Valar; POWER describes Ward 250 and the Valarin facility (gov-010). Abroad: Ward One in the Philippines, announced March 2025 and still unbuilt and without an approved site as of the last report read (orig-064). Valar says it looked at more than 20 states (ppl-006, loc-001); no site in another state was found in any public record read.
- BLM National MLRS Land Use Authorizations - Rights-of-Way (query: customer name contains 'VALAR', run 2026-09-29) (U.S. Bureau of Land Management, 2026-09-15) primary government “Green River Gigasite Small Modular Reactor/Data Center”
- Castle Country (Valar Atomics, 2026-09) primary company
- Board of Trustees Meeting slides, August 20, 2026 (SULA 2095 Other Business Arrangement) (Utah Trust Lands Administration, via Utah Public Notice Website, 2026-08-20) primary government “Selected by Valar Atomics following multi-state search”
- A startup wants to build a massive nuclear-powered data center on public land in Utah (NPR, 2026-09-30) news “some 456 small nuclear reactors”
HELD: 'First Reactor online by July 4, 2026' (Valar's July 2025 deck to Emery County): DOE announced criticality on 18 June 2026 (orig-010), ahead of Valar's own 30 June target (plan-004). HELD AS A PLAN, UNCHECKED: '30 EFPD in 12 months' (deck) matches Valar's June 2026 draft (orig-035); no run log is public (plan-006, plan-007). CHANGED: 'in a temporary facility' (deck): the approved papers still plan to take Ward 250 down after about a year of running (plan-003), but what was built is a 55-foot modular reactor complex on engineered foundations with more than 4,000 cubic yards of concrete poured, beside a fuel plant (plan-002), on a site Valar now calls home and is expanding (plan-003, ppl-006); '40 employees for about 12 months' (July 2025) became a projection of 275 jobs and $1.3 billion for a state tax credit (loc-004, fund-017). LATE: DOE safety approvals came about two months behind Valar's own schedule, by the only report of their dates (plan-004). NOT DELIVERED: the Philippine reactor announced in March 2025 (orig-064); the gas-fired supercritical-CO2 test heater Valar wanted done by June 2026, approved for design only (plan-018); fuel from Valar's own line: Ward 250's fuel came from a federal site in Nevada (plan-014). DROPPED: the 10,270-acre Green River gigasite, per Valar, though BLM still lists it pending (plan-017, mine-008). NOT YET DUE, NO FILING: 'Commercial Deployment by 2028' (deck), the 30 MW NVIDIA data center (plan-010), 'hundreds of reactors' in Carbon and Emery (loc-001). CONFLICTING: the date of full power (plan-009) and, on paper, the fuel's enrichment (plan-014).
- Valar Atomics + SRERC in Emery County (slide deck, marked confidential, posted on the Utah Public Notice Website) (Valar Atomics, via Utah Public Notice Website, 2025-07-08) primary company “operates for 30EFPD, in 12 months in a temporary facility”
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02, Appendix B, Table 7 (Valar Atomics, 2025-10) primary company “Initial Criticality 06/30/2026”
- Rapid construction from local contractors at Valar Atomics (USREL press release, Energy Corner) (Utah San Rafael Energy Lab and Valar Atomics, via ETV News, 2026-01-23) primary government “more than 4,000 cubic yards of concrete to date for the foundations”
- Utah Energy Research Board Meeting Minutes, February 11, 2026 (Utah Energy Research Board, via Utah Public Notice Website, 2026-02-11) primary government
- BLM National MLRS Land Use Authorizations - Rights-of-Way (query: customer name contains 'VALAR', run 2026-09-29) (U.S. Bureau of Land Management, 2026-09-15) primary government
The NSDA's natural-hazard values are 'preliminary', based on 'regional seismicity and generic site conditions', with final values to follow site-specific studies: peak ground acceleration 0.2 g for its most important equipment, 130 mph design wind, 200 mph tornado wind, -20 to 115 F. DOE's categorical exclusion says no active faults, landslides or geologic hazards exist at or next to the site per Utah Geological Survey mapping, calls the region moderate seismic hazard, and names only the Wasatch Fault Zone, about 150 km (95 miles) northwest. A query of the Utah Geological Survey's Quaternary fault layer on 29 September 2026, from a point on Coal Haul Road beside the lab (39.244 N, 111.094 W; accurate to about 2 km), found no mapped fault closer than about 14.8 km (9 miles); six strands of the Joes Valley fault zone lie within 20 km: the nearest (last movement mapped as less than 2.6 million years ago) at about 14.8 km, and strands mapped as having moved within the last 15,000 years at about 15 to 19 km, all with slip rates under 0.2 mm a year. Allowing for the reference point's uncertainty, the nearest strand is roughly 13 to 17 km from the reactor. Flooding: the NSDA places the site on a mesa about 100 ft above the surrounding terrain, and the CX about 100 ft above Cottonwood Creek and outside FEMA-mapped flood areas; the CX notes the Adobe Wash Regulating Reservoir about 0.4 km southwest, which drains through a separate wash that does not cross the site's drainage. Fire and aircraft: the NSDA screens out wildland and industrial fire on a '10-mile separation distance' and aircraft on 'no nearby airports'; the CX describes the site as pinyon-juniper woodland and 'typical undisturbed rangeland', and the state's airport layer shows Huntington Municipal Airport about 20 km away. Water: the CX puts consumption under 1,000 gallons a day for domestic use, with no process-water discharge; the reactor is cooled by helium, not water. Whether the site-specific seismic study was done, and its result, is in the DSA, which was not found in public records. Our check of the earthquake value: the USGS design-maps service (ASCE 7-22, 29 September 2026) gives a maximum considered peak ground acceleration of about 0.21 g for the site on soft rock (site class BC), 0.23 g for class C and 0.26 g for class D; the paper's 0.2 g is close to the rock value, and the paper gives no soil class.
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (status: Draft; issued for Public Release) (Valar Atomics, 2025-10) primary company “Preliminary seismic parameters based on regional seismicity and generic site conditions”
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (categorical exclusion B5.26) (U.S. Department of Energy, Office of Nuclear Energy (Idaho), 2026-04-22) primary government “The Wasatch Fault Zone is located approximately 150 km (95 miles) northwest of the site.”
- Utah Quaternary Faults (Utah Geological Survey, Hazards/quaternary_faults MapServer, distance queries) (Utah Geological Survey) primary government
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (status: Draft; issued for Public Release) (Valar Atomics, 2025-10) primary company “screened based on 10-mile separation distance and natural barriers”
- AirportLocations (Utah Geospatial Resource Center, FAA airport points, distance query) (Utah Geospatial Resource Center) primary government
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (categorical exclusion B5.26) (U.S. Department of Energy, Office of Nuclear Energy (Idaho), 2026-04-22) primary government “Elevated position approximately 100 feet above Cottonwood Creek eliminates flood risk.”
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (status: Draft; issued for Public Release) (Valar Atomics, 2025-10) primary company “approximately 100 feet above the surrounding terrain”
- U.S. Seismic Design Maps web service, ASCE 7-22, Risk Category IV, site class BC, at the USREL site (39.2395 N, 111.0866 W) (U.S. Geological Survey) primary government “"pgam": 0.21”
Emery County's 17 February 2026 agenda listed an MOU letting Valar do site-suitability testing on parcel 04-0019-0030 (orig-046). Utah's statewide parcel layer (UGRC, Emery County assessor data current as of 17 July 2024) shows that parcel as 112.7 acres, north-west of Orangeville; its centre lies within about 0.5 km of the other parcels in the same 04-0019 block. Valar said on 20 August 2026 that it was buying about 110 acres north of the lab from Emery County (mine-018). The sizes match, but no record read says the purchase is this parcel; the layer carries no owner names or addresses and predates any sale.
- Parcels_Emery_LIR (Utah statewide parcels, land information records) (Utah Geospatial Resource Center (UGRC), 2024-07-17) primary government
- Emery County Commission Meeting (notice, February 17, 2026) (Utah Public Notice Website (Emery County Commission), 2026-02-17) primary government “allowing them to perform site suitability testing on parcel 04-0019-0030”
- 2026-08-20 TLA Board of Trustees Meeting Audio Transcript (auto-generated) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-08-20) primary government “currently purchasing 110 acres north of the lab from Emery County”
Valar's public job board (Greenhouse, read 29 September 2026; postings updated 28 September) lists 92 openings: 71 in Torrance, California and 21 in Orangeville, Utah, and none in Carbon County, Price or Wellington. The Orangeville posts include plant operators, nuclear operations engineer and manager, instrumentation and electrical technicians, a site environmental health and safety specialist, a construction quality inspector, a development and construction finance director, and a Material Control and Accounting Specialist, whose post says the job leads the safeguards program for special nuclear material at Valar's TRISO manufacturing facilities under DOE and NRC requirements. Two fuel posts (a TRISO chemical plant process engineer, posted 16 July, and a TRISO chemical vapor deposition engineer, posted 31 July 2026) describe work to 'install, troubleshoot, and optimize pilot scale uranium processing equipment' in Orangeville; the second calls it a manufacturing 'pilot line' and says the engineer will build on 'completed HAZOPs and existing safety analyses' (a HAZOP is a structured hazard review) as 'the process transitions into production'. Set beside the record: in June 2026 Valar told Orangeville the fuel building would make it the largest US maker of this fuel once completed (loc-016); the job posts describe a pilot stage now; no DOE authorization for the fuel line was found in the public record (safe-031); and the local job figures in loc-004 cannot be matched to a payroll. Job boards change daily; these counts are as of 29 September 2026.
- Valar Atomics job board (Greenhouse public board API: 92 postings with locations and descriptions) (Valar Atomics) primary company “optimize pilot scale uranium processing equipment”
- Material Control and Accounting Specialist (Orangeville, Utah), Valar Atomics job posting (Valar Atomics, 2026-07-22) primary company
- Chemical Vapor Deposition Engineer (TRISO) (Orangeville, Utah), Valar Atomics job posting (Valar Atomics, 2026-07-31) primary company
Valar's public job board (read 29 September 2026; 92 openings, 86 first posted since June 2026) adds detail to loc-019. Torrance-listed roles (71): instrumentation and controls (19), eight 'Power Conversion' turbomachinery roles for a planned 'secondary loop Brayton cycle' (a gas turbine driven by reactor heat) with 'a purpose-built test facility program', manufacturing, machine and weld shops, graphite production, supply chain, licensing and legal. Orangeville roles (21): site operations (a Nuclear Operations Manager, a Nuclear Operations Engineer and Plant Operators who may work at 'the reactor plant or the pilot fuel fabrication facility'), fuels and materials (TRISO process and coating engineers, a nuclear material accountant), controls, QA, EH&S, HR, and a Development and Construction Finance Director whose job is cost tracking 'across active projects' and processes that 'scale across multiple construction sites'. A Project Manager, Commercial Projects (Torrance, 'operate in both Hawthorne and Utah') will 'lead development execution for one of Valar's first commercial projects' from site development to investment decision, asks applicants for experience on projects costing '$1B or more' (the post does not give this project's own cost), and will serve as a senior project representative in Utah with government and community; the post names no site. A Director of Licensing will run 'multiple concurrent licensing campaigns' across DOE and NRC pathways (safe-032). No posting mentions Carbon County, Wellington, Green River or any named future site, and none is located in Carbon County. The Power Conversion post says Valar's HTGR 'power conversion system will be built around' this turbine cycle, in the future tense; Ward 250's July electricity demonstration used a thermoelectric generator, not a turbine (ETV, 1 July; plan-010).
- Valar Atomics job board (public Greenhouse feed, 92 postings) (Valar Atomics (via Greenhouse), 2026-09-28) primary company “secondary loop Brayton cycle”
- Project Manager, Commercial Projects (Torrance, California) (Valar Atomics (via Greenhouse), 2026-05-17) primary company “lead development execution for one of Valar’s first commercial projects”
- Development and Construction Finance Director (Orangeville, Utah) (Valar Atomics (via Greenhouse), 2026-07-14) primary company “scale across multiple construction sites”
- Director of Licensing (Torrance, California) (Valar Atomics (via Greenhouse), 2026-08-11) primary company “multiple concurrent licensing campaigns”
- Director Instrumentation, Control, and Electrical - Power Conversion (Torrance, California) (Valar Atomics (via Greenhouse), 2026-06-30) primary company “paired with development generator sets and a purpose-built test facility program”
- Emery County takes center stage as Valar and Nvidia power historic breakthrough (ETV News (Kevin Butler), 2026-07-01) news “converted into electricity through a thermoelectric generator”
Utah state job requisition 2646 (Department of Natural Resources), opened September 25, 2026 with an application deadline of October 1, 2026, says the Utah Office of Energy Development (OED) is seeking a Safety Manager to lead the environmental, health and safety program at the Utah San Rafael Energy Lab (USREL), 800 N Coal Haul Rd, Orangeville. The role covers work with hazardous chemicals, molten salts, compressed gases, high-temperature systems, electrical and mechanical equipment, radioactive materials and industrial operations; it is to inspect and audit the lab and partner work areas, review new experiments and equipment before authorization, lead incident investigations, run training and emergency drills, coordinate emergency preparedness with local responders and regulators, and coordinate with the lab's Radiation Safety Officer on radiological training, dosimetry, incident response and license conditions, and with UOSH and Utah DEQ. It reports to the Lab Director, with authority to stop work on an imminent hazard. Minimum: ten years of safety experience and a bachelor's degree; radiological safety experience is listed only as 'desirable'. The listing states: Schedule Code 'TL - Time Limited'; Background Check Required 'No'; Drug Test Required 'No'; full-time, in-office, salary '$58.00' (unit not stated). OED owns the lab and is Valar's landlord there (mine-014); Valar reported first electricity from Ward 250 at the lab on July 1, 2026. The listing does not say whether the position is new or a replacement, or who led lab safety before; it does show that a Radiation Safety Officer role and radiological license conditions already exist at the lab. Ward 250's own nuclear safety basis is Valar's, under DOE's authorization; this job is the state's lab-wide safety lead.
- Safety Manager (req2646), Utah San Rafael Energy Lab, Orangeville: Utah state job listing (Utah Department of Natural Resources, Office of Energy Development (State of Utah careers site), 2026-09-25) primary government “Schedule Code – TL - Time Limited”
- Castle Country (Valar Atomics) primary company
The Wellington City Council's ten most recent notices on the Utah Public Notice Website (work meetings and regular meetings of 12 and 26 August, 9, 14 and 23 September 2026, and the signed 26 August minutes) list no item on Valar, a reactor, trust land or the parcel north of town, and the 26 August minutes (read by OCR) do not mention them. The Trust Lands memo places the parcel in unincorporated Carbon County, so the county, not the city, is the land-use authority (csite-015). A rescan of all 26 council notices from 13 May to 23 September 2026 (agenda text on the notice website) found no such item either.
- Wellington City Council: notices (Aug 12 to Sept 23, 2026) (Utah Public Notice Website) primary government
- CITY COUNCIL MINUTES 8-26-26 signed (Wellington; read by OCR) (Wellington City (Utah Public Notice Website), 2026-08-26) primary government
- 09.17.2026 TLA Board Packet (Item 10A: SULA 2095-OBA Board of Trustees Memorandum, Carbon County letter, lease map) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-09-17) primary government “located within unincorporated Carbon County”
Utah Code 73-3-6 requires the State Engineer to publish notice of a water-right application once a week for two successive weeks in a newspaper of general circulation in the county of the source and of use (and on the state's legal-notice site), and the notices set a deadline for written protests. ETV News, delivered to every home in Carbon and Emery, carries these 'NOTICE TO WATER USERS' notices. Its search feed returned 159 of them, from June 2018 to 23 September 2026, 61 published between 11 October 2023 and 23 September 2026 (26 with Emery County applications); all were read. None names Valar Atomics or a nuclear use, and none concerns Section 16, T14S R11E (the Wellington lease) or industrial water near Orangeville for Valar. The Carbon applications are mostly irrigation and canal-company changes along the Price River; the Emery ones include coal, power-plant and ranch uses, and a 23 September 2026 notice lists a Trust Lands gravel-operation well 22 miles east of Castle Dale (protests due 20 October). This fits what Valar says so far: its current water comes through Orangeville's system with shares turned in to the city (loc-017), and no record read shows a state application for that; the 1,000 additional shares are 'in the discussion phase'. It also means no public protest window has yet opened on any Valar water use. The Trust Lands memo says the Wellington site must buy existing rights and move them by a publicly advertised change application (mine-015, mine-017). ETV's search may not return every notice, and the Emery County Progress, which may also carry them, did not answer (sources_not_read); the state's legal-notice website was not searched.
- Utah Code 73-3-6: Publication of notice of application (amended 2024) (Utah State Legislature, 2024-05-01) primary government “once a week for a period of two successive weeks in a newspaper”
- ETV News public notices: 'NOTICE TO WATER USERS' from the Utah State Engineer (search feed pages 1-15: 159 notices, June 2018 to 23 Sept 2026; 61 since 11 Oct 2023) (Utah Division of Water Rights (legal notices published in ETV News)) primary government
- NOTICE TO WATER USERS (Emery County applications; protests due Oct. 20, 2026) (Utah Division of Water Rights (legal notice published in ETV News), 2026-09-23) primary government
The Washington Sun (Mara Hoplamazian and Jade Lozada, published and updated 18 September 2026) reported that the largest data-center proposal it found on BLM land 'appears to be' a 10,200-acre project from Valar Atomics at a site near Green River, Utah, and that Valar had a second Utah proposal it called the 'Raceway Gigasite', with no estimated size. An editor's note added after publication says Valar contacted the paper, confirmed it had applied 'for survey access' at the 10,200-acre site, and that a company spokesperson said it had decided not to pursue the project. On 29 September 2026 BLM's public layer still showed UTUT106784007 as 'Pending' (last modified 26 May 2026) and titled for a reactor and data center, not a survey. No BLM case named 'Raceway' appears in any public MLRS layer; the only other Valar case with a site name is 'Project Beehive' (mine-006). Whether 'Raceway' and 'Beehive' are the same site is not shown in any record read.
- Trump Is Considering More Data Centers on Public Lands Than Previously Known (The Washington Sun (Mara Hoplamazian and Jade Lozada), 2026-09-18) news “After considering the site, the company has decided to no longer pursue the project”
- BLM Natl MLRS Rights of Way (ROW) (feature layer and query results) (Bureau of Land Management (MLRS)) primary filing “Green River Gigasite Small Modular Reactor/Data Center”
The Washington Sun reported that several local officials said they had not been aware of the federal government's deliberations on data-center proposals on public land; that local officials and advocates in Utah, Arizona, Oregon, Idaho and Wyoming said they were not aware of many of the projects; and that many proposals are not easily found on BLM's website. The only Utah voice it quotes by name is Lexi Tuddenham, executive director of the advocacy group HEAL Utah, who said there is little public awareness of the Utah projects; no Carbon or Emery County official is quoted. A search of the Federal Register for 'Valar Atomics' on 29 September 2026 returned one document, a DOE notice of 6 July 2026 on a Defense Production Act 'Nuclear Fuel Cycle Consortium' agreement; nothing from BLM. BLM's NEPA register (eplanning.blm.gov) loads its search results by script and answered our reader with an error page, so whether a NEPA project exists for these cases could not be checked by our tools (see open questions).
- Trump Is Considering More Data Centers on Public Lands Than Previously Known (The Washington Sun (Mara Hoplamazian and Jade Lozada), 2026-09-18) news “Several local officials told The Sun they weren't aware of the federal government's deliberations”
- Federal Register document search: "Valar Atomics" (API results) (Office of the Federal Register) primary government
- Trump Is Considering More Data Centers on Public Lands Than Previously Known (The Washington Sun (Mara Hoplamazian and Jade Lozada), 2026-09-18) news “There is little public awareness of those projects in Utah”
In ETV News's coverage tagged to Valar (the 14 items from 16 July to 23 September 2026 in its search feed), the first report of the Carbon County land deal is 'Valar Atomics secures land agreement for Carbon County project' (Stephanie Olsen, 18 September 2026), the day after the Trust Lands vote. Each of the ten earlier items was checked: none mentions Wellington, trust land or a lease. They covered, among other things, Valar's presentation to the East Carbon City Council on 21 July, an August energy summit where Valar's Jess Housekeeper spoke of plans to eventually manufacture reactors and fuel (no site named), the One Utah Summit, Orangeville council updates, and the September open house and planned Carbon County town hall. The Carbon County Commission's 19 August minutes of a Valar presentation also do not name the site (mine-013). The Salt Lake Tribune's 24 September article on Carbon County data centers could not be read (paywall).
- ETV News search feed for 'valar' (RSS) (ETV News) news
- Valar Atomics secures land agreement for Carbon County project (ETV News (Stephanie Olsen), 2026-09-18) news
- East Carbon Council discusses animal safety, sewer rates and nuclear energy updates (ETV News (Stephanie Olsen), 2026-07-23) news
- Leaders look to coal, nuclear and new industry for growth at local energy summit (ETV News (Kevin Butler), 2026-08-14) news
- Commission honors Spectrum Paint owner and announces Valar Atomics open house (ETV News (Stephanie Olsen), 2026-09-04) news “the company plans to hold a town hall specifically for Carbon County residents”
Per the September memorandum, current authorizations on Section 16 include easements for fiber optic lines, a power line and a county road, a livestock grazing permit (GP 22396) and a special use lease to the Utah National Guard (SULA 1321) on the south-east quarter (160 acres). The Guard lease lets engineering battalions train in maneuvers, mobility and survival; they 'may construct bunkers and ditches, etc., but may not discharge munitions', and there are no structures on it. Staff are working with the Guard to move that lease so Valar can take the whole section; the costliest part is expected to be a cultural-resource survey of the new site, paid for by Valar. The grazing permit would be ended before construction, with 'as much notice as possible' to the permittee. The memo does not say which county road crosses the parcel or name the easement holders. The state's RDCC records show the Guard lease (SULA 1321) was reviewed there in 2001 (csite-032). Two state records give different figures for what the section earns now: the memo says about $4,000 a year, while the approved August minutes record staff telling a trustee about $4,000 a month from the Utah National Guard.
- 09.17.2026 TLA Board Packet (Item 10A: SULA 2095-OBA Board of Trustees Memorandum, Carbon County letter, lease map) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-09-17) primary government “They may construct bunkers and ditches, etc., but may not discharge munitions.”
- 09.17.2026 TLA Board Packet (Item 10A: SULA 2095-OBA Board of Trustees Memorandum, Carbon County letter, lease map) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-09-17) primary government “generated little income (approximately $4,000 per year)”
- 08.20.2026 FINAL TLA Minutes (Utah Trust Lands Administration (Utah Public Notice Website), 2026-09-17) primary government “approximately $4,000 per month from the Utah National Guard”
Pulling together the government records on Valar and Carbon County (details in carbon_site.json and mining.json). Earliest public hints came in Emery County, not Carbon (and at the April 2026 hearing Valar also promised 'to be open with all plans', gov-038): the state lab director told Emery's June 2025 hearing that Valar was 'looking at manufacturing in Emery or Carbon County' (gov-020), and at Emery's April 2026 land-sale hearing a commissioner called the lab-side purchase 'an intermediate step' while Valar looks for 'a larger piece of property with water' (gov-022). State steps: Trust Lands mapped the Wellington parcel on 9 April 2026 (mine-048); the state's RDCC notice of 20 April 2026 described an unnamed industrial and power project (csite-032); the Trust Lands board first named Valar on a public agenda on 10 August 2026 (csite-018) and approved the lease with a purchase option on 17 September 2026 (mine-011), its chair having spoken of working so the proposal 'is approved' (ppl-019). Carbon County: its commissioners signed a support letter on 29 June 2026 that no county agenda shows (mine-013, csite-026). Federal: no DOE, NRC or Federal Register record names a Carbon site (csite-020, gov-029); BLM lists separate pending Valar land applications in Emery and elsewhere (mine-006). Not found as of 2026-09-29: any Carbon County zoning, permit, development or incentive action for Valar (csite-012, csite-029); any GOED incentive for a Carbon site (csite-024 is Emery only); any Utah Energy Research Board or legislative item naming the Wellington site (csite-031, gov-019).
- Minutes of a Public Hearing of the Board of Emery County Commissioners, June 17, 2025 (Emery County Commission (Utah Public Notice Website), 2025-06-17) primary government “They are looking at manufacturing in Emery or Carbon County.”
- Emery County Commission Meeting Minutes, April 7, 2026 (Emery County Commission (Utah Public Notice Website), 2026-04-07) primary government “They are looking for a larger piece of property with water”
Valar's appearances before Carbon County public bodies and audiences in 2026, with what the record of each shows: 24 June, Price City Council, public comment: Cory Gardner and Harry Hansen on Ward 250 reaching 'full power' and a future community event (ETV, ppl-026); the city's minutes record only 'an update on the progress of the company'. 1 July, Carbon County Commission: commissioners celebrated Valar's Emery reactor and NVIDIA plan (ETV; minutes, csite-026). 21 July, East Carbon City Council: four Valar staff presented the test reactor's start, helium cooling, local hiring and tours by appointment (ETV, 23 July); the posted agenda lists no Valar item, and East Carbon's minutes for July and September were not posted as of 29 September (its latest posted minutes are for 16 June). 12 August, the Carbon & Emery Energy Collaborative in Price: plans to manufacture reactors and fuel (loc-002). 12 August, Price City Council work session: the mayor welcomed Valar's Jess Housekeeper and colleagues 'to highlight the new nuclear energy plant in Orangeville', and future plans for that facility (workshop minutes). 19 August, Carbon County Commission, 'Valor Atomics presentation': Max Ukropina and Cory Gardner on the Orangeville reactor, which they called 'walk-away safe', local hiring, and a town hall in Price and an open house 'within the next 30 to 45 days' (minutes; mine-013). 1 September, East Carbon City Council: a Valar representative 'formally introduced the company' and announced the open house (ETV, 4 Sept); the agenda listed 'Valar presentation'. 2 September, Carbon County Commission: open house on 10 September and a town hall for Carbon County residents in late September or early October (ETV; minutes, csite-026). 9 September, Price council work session: staff reported a 'Valar Atomics field trip' set for 24 September (workshop minutes). 10 September, open house in Orangeville for both counties (loc-001). None of these records mentions Wellington, trust land, a lease or a Carbon site; the state board heard the lease on 20 August and approved it on 17 September in Salt Lake City (mine-014, mine-011). Price's regular council minutes of 22 July, 12 August, 26 August and 9 September have no Valar item. The records are summaries (ETV reports and minutes), not transcripts, so a passing mention cannot be ruled out; the 19 August county meeting audio would settle that one meeting (carbon_site.json open questions). The promised Carbon County town hall had not been found held or scheduled as of 29 September 2026 (csite-028). Earlier, in October 2025, the local paper had reported a Valar plan for a Carbon County manufacturing hub, without a site (loc-034).
- Price City Council celebrates Valar Atomics reaching full power ahead of schedule (Stephanie Olsen) (ETV News, 2026-06-25) news
- 06-24-2026 Minutes, Price City Council meeting (Price City, 2026-06-24) primary government
- Price City Council notices: minutes of 22 July, 12 August (meeting and work session), 26 August and 9 September (meeting and work session) 2026, all read (Utah Public Notice Website) primary government
- Carbon County Commissioners urge safety ahead of July 4th, reflect on freedom and democracy (Stephanie Olsen) (ETV News, 2026-07-03) news “the first government-approved commercial reactor”
- East Carbon Council discusses animal safety, sewer rates and nuclear energy updates (Stephanie Olsen) (ETV News, 2026-07-23) news
- East Carbon City Council meeting agenda, July 21, 2026 (East Carbon City, 2026-07-21) primary government
- Leaders look to coal, nuclear and new industry for growth at local energy summit (Kevin Butler) (ETV News, 2026-08-14) news “This is our home. We wanna stay here”
- East Carbon City Council honors firefighters for wildfire service (Stephanie Olsen) (ETV News, 2026-09-04) news
- East Carbon City Council meeting agenda, September 1, 2026 (item 5: Valar presentation) (East Carbon City, 2026-09-01) primary government
- Commission honors Spectrum Paint owner and announces Valar Atomics open house (Stephanie Olsen) (ETV News, 2026-09-04) news
- Community gets closer look at Valar Atomics during open house (Scottie Kraync) (ETV News, 2026-09-14) news “as we grow here in your backyard, in your community”
- Valar Atomics secures land agreement for Carbon County project (Stephanie Olsen) (ETV News, 2026-09-18) news
- Minutes of the Price City Council Workshop, August 12, 2026 (Price City, 2026-08-12) primary government “to highlight the new nuclear energy plant in Orangeville”
- Minutes of the Price City Council Workshop, September 9, 2026 (Price City, 2026-09-09) primary government “Valar Atomics field trip scheduled for September 24, 2026”
- Aug 19, 2026 Commission Meeting Minutes (Carbon County Board of Commissioners; scanned, read as page images) (Carbon County Commission, 2026-08-19) primary government “within the next 30 to 45 days”
- East Carbon City Council notices (latest posted minutes: 16 June 2026) (Utah Public Notice Website) primary government
- What’s actually happening at the Utah San Rafael Energy Lab? (Susanna Watts) (ETV News, 2025-10-10) news “their current plan is to build a manufacturing hub in Carbon County”
The Wellington section is held for the Public Schools Trust (csite-002). Trust Lands says 'nearly all' the revenue it earns is deposited in the Permanent School Fund, and that each year the fund's gains, interest and dividends are distributed to every public school in Utah by enrollment through the School LAND Trust program. So the $400,000 bonus and rent from Valar (mine-011; ETV reported about $35 million over 50 years) go into that statewide fund, not to Carbon County schools as such; a Carbon school gets its enrollment share like any other. Property taxes on any buildings would go to local taxing entities, including the Carbon County School District, subject to any incentive (none found for Carbon, csite-029). The school beneficiaries' advocate supported the lease (csite-028). Other school and college ties found: Valar was among the donors the Emery High National Honor Society thanked for its 17 August back-to-school event (ETV, 19 Aug 2026); a Southern Utah University engineering student interned at Valar's Orangeville site (SUU release, September 2026); Valar presented to USU Eastern's Eastern Leaders Academy (March 2026, loc-022). No agreement between Valar and the Emery County School District appears in its board's agendas and minutes posted on the state notice site from April to September 2026 (read; the 8 April minutes mention Valar only as one of the local businesses at a school's career day), and the Carbon School District board's page there listed no notices when read on 29 September 2026.
- From Trust Lands to Your School (Utah Trust Lands Administration) primary government “Nearly all of the revenue Trust Lands generates is deposited into the Permanent School Fund.”
- Valar Atomics secures land agreement for Carbon County project (Stephanie Olsen) (ETV News, 2026-09-18) news
- Community comes together for Emery High NHS Back-to-School event (ETV News, 2026-08-19) news “including Valar Atomics”
- SUU mechanical engineering student transforms classroom knowledge into real-world impact at Valar Atomics (SUU press release) (ETV News, 2026-09-19) primary government
- Emery County School District Board of Education notices (agendas and minutes, April to September 2026) (Utah Public Notice Website) primary government
- Carbon County School District Board of Education (public body page; no notices listed) (Utah Public Notice Website) primary government
- Emery County School District Board of Education minutes, April 8, 2026 (Emery County School District, 2026-04-08) primary government “Career Day highlighting local businesses (TSJ construction, Valor Atomics, and helicopter pilot)”
At its 17 September 2026 meeting in Salt Lake City, the Trust Lands board took up the proposed SULA 2095 OBA with Valar Atomics, Inc. as an action item. The auto-generated transcript posted with the meeting records a motion to approve 'SULA 2095 OBA on the terms set forth in the board memorandum', a second, and the chair calling the vote unanimous. Terms in the memorandum: an initial lease of 480 acres (N1/2 and SW1/4 of Sec. 16), with the other 160 acres added if a Utah National Guard lease there is moved; 50 years plus two optional 25-year extensions; a $400,000 up-front bonus; $30 per acre a year in years 1-5, rising to $625 per acre by year 8, with CPI and 25-year appraisal adjustments; and an option to buy all or part at the greater of appraised value or the present value of 50 years of rent (about $10.2 million if bought in year 10, per the staff table). Staff said an independent appraisal valued the land at $750 an acre ($480,000 for 640 acres). As of 29 September 2026 the official minutes of the 17 September meeting were not yet among the posted attachments.
- 09.17.2026 TLA Board of Trustees Meeting Audio Transcript (auto-generated) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-09-17) primary government “move to approve. Sula 2095 OBA on the terms set forth in the board memorandum”
- 09.17.2026 TLA Board Packet (Item 10A: SULA 2095-OBA memorandum, Carbon County letter, lease map) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-09-17) primary government
- Trust Lands Administration Board of Trustees Meeting, September 17, 2026 (notice and attachments) (Utah Public Notice Website, 2026-09-17) primary government
- Valar Atomics secures land agreement for Carbon County project (ETV News (Stephanie Olsen), 2026-09-18) news “the board unanimously approved the agreement”
At the 20 August 2026 board meeting the public comments came from the three Carbon County commissioners, the Utah Office of Energy Development's deputy director Jake Garfield (whose office owns the San Rafael lab and is Valar's landlord there), Valar's director of Utah operations Jess Housekeeper, and one online commenter, an educator, who spoke about school trust funding. At the 17 September meeting the commenters were Commissioner Jensen in the room, Commissioners Haddock and Martines online, another Office of Energy Development deputy director (Tracy Rees), and five people who said they work for Valar, including its public-affairs staffer Harry Hansen, Jess Housekeeper and Cory Gardner. No comment opposing the lease is recorded in either transcript or in the August minutes; Commissioner Jensen acknowledged 'a few in our community who will push back'. Both meetings were held at 102 South 200 East in Salt Lake City, with online attendance possible; the notices were posted on the Utah Public Notice Website on 10 August and 8 September 2026. In August the board chair said the board wanted to step carefully and would work with Valar 'to make sure that this proposal is approved'. The memoranda record committee discussions on 20 and 28 July (Surface Resources) and 25 August 2026 (Energy & Minerals); the Surface Resources Committee 'discussed the need for full transparency' and asked Valar to keep up local outreach.
- 2026-08-20 TLA Board of Trustees Meeting Audio Transcript (auto-generated) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-08-20) primary government
- 09.17.2026 TLA Board of Trustees Meeting Audio Transcript (auto-generated) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-09-17) primary government “we realize that there are a few in our community who will push back”
- 08.20.2026 FINAL TLA Minutes (Utah Trust Lands Administration (Utah Public Notice Website), 2026-09-17) primary government
- 8.20.2026 TLA Board Packet (Discussion Item 9A: SULA 2095 OBA, Board Meeting Discussion Memorandum) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-08-20) primary government “the committee discussed the need for full transparency regarding the proposed project”
- 09.17.2026 TLA Board Packet (Item 10A: SULA 2095-OBA memorandum, incl. 25 Aug 2026 Energy & Minerals Committee discussion) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-09-17) primary government
- Trust Lands Administration Board of Trustees Meeting, September 17, 2026 (notice and attachments) (Utah Public Notice Website, 2026-09-08) primary government
At both Trust Lands hearings Carbon County Commissioner Larry Jensen said no coal had been produced in Carbon County for about four years (over four years, in August) and that the county's one remaining mine, Skyline, was producing in Sanpete County. The Utah Geological Survey's table of coal production by mine (2002-2024) shows the Carbon County mines Dugout Canyon, West Ridge and Horizon with no output after 2019, 2015 and 2012 respectively, and Skyline #3 output assigned to Carbon County last in 2018 (941,447 tons), with 2019-2023 output assigned only to Sanpete and Emery. Statewide output was 7.0 million tons in 2023, the lowest since 1975, and 7.4 million in 2024. The board chair's September remark that this was the 'first year in history' with no Carbon County coal is not borne out: the table shows none in 2020 through 2024 as well.
- 09.17.2026 TLA Board of Trustees Meeting Audio Transcript (auto-generated) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-09-17) primary government “There's not been a single ton of coal produced in Carbon County”
- Table 2.8 Coal Production in Utah by Coal Mine, 2002-2024 (Utah Geological Survey, 2025) primary government
- Utah mining 2024: Metals, industrial minerals, uranium, and coal (Circular 139) (Utah Geological Survey, 2025) primary government
Emery County Commission agenda and minutes of 18 August 2026 list two items: a temporary moratorium on Level II and Level III conditional use permits while ordinances are updated, and updating ordinances so that large-scale industrial projects, among them solar, data centers and nuclear development, are classified as Level III conditional use permits; the minutes record the item titles with no discussion or vote. The 15 September 2026 agenda lists an ordinance 'establishing a temporary, 180 day moratorium' on accepting, processing and considering Level II and III applications (mine-043); only an audio recording of that meeting is posted, so the outcome was not read. At the 21 July 2026 meeting a resident gave an informational presentation on data centers that also raised concerns about Valar and solar projects; no discussion followed. No Emery County conditional use permit item for Valar was found in a scan (29 Sept 2026) of 527 Emery County public notices from 2019 to 2026 (commission, planning and zoning, reinvestment agency, economic development board); its Ward 250 building permit was voted by the commission in September 2025 (gov-021).
- Emery County Commission Meeting Minutes, August 18, 2026 (Emery County Commission (Utah Public Notice Website), 2026-08-18) primary government “SOLAR, DATA CENTERS, NUCLEAR DEVELOPMENT, ETC BEING CLASSIFIED AS LEVEL III CONDITIONAL USE PERMITS”
- Emery County Commission Meeting, September 15, 2026 (notice and agenda) (Utah Public Notice Website, 2026-09) primary government “establishing a temporary, 180 day moratorium”
- Emery County Commission Meeting Minutes, July 21, 2026 (Emery County Commission (Utah Public Notice Website), 2026-07-21) primary government
The Emery County Commission's 15 September 2026 agenda, posted on the Utah Public Notice Website on 14 September, lists for decision an ordinance setting 'a temporary, 180 day moratorium' on accepting, processing and considering Level II and Level III conditional use permit applications. The agenda does not say what prompted it or whether it concerns data centers; only an audio recording of the meeting is posted, no minutes, so the outcome was not checked. The county also noticed a 5 October 2026 public hearing on a utility-scale solar ordinance.
- Emery County Commission Meeting, September 15, 2026 (agenda) (Utah Public Notice Website (Emery County Commission), 2026-09-15) primary government “a temporary, 180 day moratorium on the acceptance, processing and consideration”
- Notice of Public Hearing: Emery County Utility-Scale Solar Energy Systems Ordinance (Utah Public Notice Website (Emery County Commission), 2026-09-22) primary government
A Notice of Location is posted at one of the claim markers (fld-001, fld-002; the photo was re-read for this check). It names Valar Atomics Inc as locator of the 'RW 453' Lode Mining Claim in the NW and NE quarters of Section 28, T14S R11E, Salt Lake Principal Meridian, Carbon County, located on the 12th (handwritten) of September 2026. Section 28 lies two sections (about two miles) south of Section 16, which the state approved leasing to Valar, in the same township. A fresh query of BLM's not-closed mining-claim layer on 29 September 2026 still shows only 10 open claims in Carbon County, none named RW or Valar; the nearest, the BLACK RIFLE placer (UT106782094), is about 9.4 km south-east of Section 16 (mine-002). That absence is expected for now: federal rules allow 90 days after location to record a claim with BLM (dir-005), and Utah law requires a copy of the notice to be recorded with the county recorder within 30 days of posting, about 12 October 2026 for RW 453 (mine-026, dir-004). The number 453 suggests a series, but one notice does not show how many claims exist. Section 16 itself is state trust land, which federal mining claims cannot cover (mine-021, mine-034); county parcel records show part of Section 28 is federal (dir-002). The notice does not name a mineral; the only mineral occurrences on record nearby are gravel pits and carbon dioxide (dir-003, disc-003). Other sources of stakes exist nearby: easements and a Guard lease on Section 16 (csite-003), Valar's own site surveys allowed under the lease (mine-015), and PacifiCorp's pending transmission line, which crosses sections 19, 29, 30, 34 and 35 of the township (mine-049). BLM's rights-of-way layer shows Valar's three pending cases unchanged (Green River, Beehive, and UTUT106833224, which BLM lists as a pending distribution line with no location; mine-006). Of the 7,139 Utah claims created in the 12 months to 29 September 2026, 77 still had no legal description on BLM's layer, so new claims can take time to appear.
- Photo of the Notice of Location posted at the RW 453 location monument (resident fieldwork, 2026-09) resident fieldwork “Valar Atomics Inc”
- BLM Natl MLRS Mining Claims - Not Closed (feature layer; envelope query around Carbon County) (Bureau of Land Management (MLRS)) primary filing
- BLM Natl MLRS Rights of Way (feature layer; query by customer name) (Bureau of Land Management (MLRS)) primary filing “Green River Gigasite Small Modular Reactor/Data Center”
- 43 U.S.C. 1744: Recordation of mining claims (Office of the Law Revision Counsel, U.S. House) primary government “within ninety days after the date of location of such claim”
- Utah Code 40-1-4: Copy of location notice to be recorded (Utah State Legislature) primary government “Within 30 days after the date of posting the location notice upon the claim”
- 30 U.S.C. 612: Unpatented mining claims (Office of the Law Revision Counsel, U.S. House) primary government “for any purposes other than prospecting, mining or processing operations”
The Notice of Location posted at the claim's location monument reads: locator Valar Atomics Inc, 20333 Normandie Ave, Torrance, CA 90501; the 'RW 453' Lode Mining Claim in quarter sections NW and NE of Section 28, Township 14S, Range 11E, Salt Lake Principal Meridian, Carbon County, Utah; located on the 12th day of September 2026 (the day written by hand). The claim is about 1,500 by 600 feet (1,490 feet east and 10 feet west of the monument, 300 feet each side), which is the largest size a single lode claim may take. It ties the claim's NW corner to the permanent monument at the SE corner of Section 32 (see dir-001 for a problem with that tie). The number 453 suggests a numbered series of claims, but one notice does not show how many exist; BLM's public layer does not list any RW claim yet (dir-005).
- Photo of the Notice of Location posted at the RW 453 location monument (resident fieldwork, 2026-09) resident fieldwork “Valar Atomics Inc”
ETV News (14 Sept 2026) reported Valar's public open house at its Orangeville site on Thursday, 10 September 2026, for Carbon and Emery residents: small-group tours of the Ward 250 building, food and entertainment. As ETV reported it, head of projects Max Ukropina said Valar has hired dozens of community members and wants to hire more; founder and CEO Isaiah Taylor said Valar chose Emery and Carbon counties after considering more than 22 states, and that Valar hopes to build hundreds of reactors in Carbon and Emery counties (ETV's paraphrase, not a quote); he was quoted hoping residents will come to work for Valar 'as we grow here in your backyard'. State Sen. David Hinkins spoke of industry easing residents' property taxes. The report does not mention the Wellington trust-land lease the Trust Lands board approved seven days later (mine-011; ETV, 18 Sept), any Carbon County site, a fuel factory or a timeline. When Valar's Harry Hansen (spelled Hanson in that report) announced the open house to the Carbon County Commission on 2 September, he called it a chance to 'come check out what’s going on here in Orangeville' and said Valar planned a town hall specifically for Carbon County residents in late September or early October, date not yet set (ETV, 4 Sept). Whether the Carbon site came up in the small-group tours is not in any record read.
- Community gets closer look at Valar Atomics during open house (Scottie Kraync) (ETV News, 2026-09-14) news “as we grow here in your backyard, in your community”
- Commission honors Spectrum Paint owner and announces Valar Atomics open house (Stephanie Olsen) (ETV News, 2026-09-04) news “come check out what’s going on here in Orangeville”
- Valar Atomics secures land agreement for Carbon County project (Stephanie Olsen) (ETV News, 2026-09-18) news “located about six miles north of Wellington and six miles east of Price”
ETV News (9 Aug 2026) reported that at the One Utah Summit (4-6 August 2026, Cedar City) Valar received the Utah Department of Natural Resources' Horizon Award, and that Isaiah Taylor joined DNR's head, Joel Ferry (ETV calls him commissioner), on the main stage for a session on Utah's role in nuclear innovation; Carbon Commissioner Larry Jensen received a leadership award at the same summit. DNR's 2025 strategic plan lists among the department's units the Office of Energy Development (which owns the San Rafael lab, is Valar's landlord, signed its MOU and runs the state's nuclear education campaign: mine-035, gov-011, gov-025), the Division of Water Rights, which it describes as the regulatory body directed by the State Engineer (the office that would decide any change application for the water Valar seeks, loc-017, mine-015), and the Division of Oil, Gas and Mining; its measures include the state's acquisition of the San Rafael lab from Emery County. An award is not a regulatory act, and the Division of Water Rights decides applications under state law with public notice and a right to protest. Organizationally, the same department houses the office that hosts Valar and, through a separate division, the regulator of the water it seeks.
- Castle Country takes center stage at One Utah Summit (Kevin Butler) (ETV News, 2026-08-09) news
- Utah Department of Natural Resources 2025 Strategic Plan (Utah Department of Natural Resources, 2025) primary government
- NOTICE TO WATER USERS (Emery County applications; protests due Oct. 20, 2026) (Utah Division of Water Rights (legal notice published in ETV News), 2026-09-23) primary government “Protests must be filed with the Division of Water Rights”
Flooding struck Emery County beginning 29 August 2026: on 1 September the Emery County Commission declared a state of emergency for flooding 'beginning on August 29, 2026' from severe thunderstorms and excessive rainfall (minutes), and ETV reported the commission later sought federal watershed help (21 Sept). Orangeville's council held an emergency working meeting on 31 August 2026 on the response, recording sandbagging, damage to the ballfield and a question about how many families in apartments were displaced (minutes); at the 1 September county meeting the sheriff thanked volunteers who helped with 'the flooding event in Orangeville', noting many properties had water damage (minutes). No record read mentions the Valar site. DOE's categorical exclusion says the site is outside FEMA-mapped flood hazard areas and about 100 feet above Cottonwood Creek, which it says eliminates flood risk and any hydraulic connection to the creek (safe-021). Whether roads to the site or emergency services were affected during the flood is not in any record read.
- Orangeville City Council, August 31 emergency working meeting minutes (Orangeville City, 2026-08-31) primary government
- Emery County Commission Meeting Minutes, September 1, 2026 (CM09012026) (Emery County Commission, 2026-09-01) primary government “the flooding event in Orangeville”
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (categorical exclusion B5.26) (U.S. Department of Energy, Office of Nuclear Energy, 2026-04-22) primary government “Elevated site position eliminates flood risk.”
- Emery County delays solar decision, pauses new conditional use permits (ETV News, 2026-09-21) news
DOE's environmental determination for Ward 250 (signed 22 April 2026) describes the Ward250 facility as a 'Reactor Complex and Fuel Laboratory' inside a security fence of about 2 acres, within the state-run Utah San Rafael Energy Research Center, a 20.6-acre site near Orangeville; the reactor complex is about 55 feet high and made of modular buildings on engineered foundations tied only to existing lab utilities. A joint update from the state lab and Valar, run in ETV News on 23 January 2026, said local contractors had moved and crushed about 40,000 cubic yards of material and poured over 4,000 cubic yards of concrete for foundations of the Ward 250 test reactor and a fuel fabrication facility. ETV (24 August 2026), reporting a business-chamber tour on 19 August, said the reactor was now enclosed in cement bricks that hide it from view, and described an operations center and exhaust equipment designed to detect radioactive particles and shut the exhaust off. Valar's open job posts (29 September 2026) staff both 'the reactor plant' and a 'pilot TRISO fuel fabrication facility' in Orangeville. Other things at or beside the lab are recorded elsewhere: Valar's proposed 10 MW gas-fired test heater, approved only for design (gov-014); other nuclear companies courting the lab (gov-031); the 112-acre county parcel next door that Valar is buying (gov-022, loc-014); and the unauthorized sewer tie-in (loc-015).
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (U.S. Department of Energy, Office of Nuclear Energy, 2026-04-22) primary government “comprises the Reactor Complex and Fuel Laboratory enclosed within a security-fenced area”
- Rapid construction from local contractors at Valar Atomics (USREL press release, Energy Corner) (Utah San Rafael Energy Lab and Valar Atomics, via ETV News, 2026-01-23) primary government “The site will house Valar’s fuel fabrication facility and the WARD 250 test reactor.”
- Emery County Business Chamber gets an up-close look at Valar Atomics progress (ETV News (Stephanie Olsen), 2026-08-24) news
- Valar Atomics job board (public Greenhouse feed, 92 postings) (Valar Atomics (via Greenhouse), 2026-09-28) primary company “Operators may be assigned to either the reactor plant or the pilot fuel fabrication facility”
The Utah Trust Lands Administration's 20 August 2026 board memorandum (Discussion Item 9A) names the applicant as Valar Atomics Inc. and the land as T14S, R11E, Section 16, 640 acres of state trust land about five miles north of Wellington, benefiting the Public Schools Trust. It confirms that the Special Use Lease Agreement 'SULA 2095 OBA' on the August agenda (orig-044) is this parcel. The stated purpose is an integrated nuclear energy, advanced manufacturing, critical mineral refining and data center campus: developing, manufacturing and operating high-temperature gas-cooled reactors (HTGRs) for power, plus possible TRISO fuel manufacturing, concrete batch plants, component manufacturing, hydrogen and synthetic fuels, data centers, water desalination and steel making. It is an 'Other Business Arrangement' because it includes an option to buy the land. Staff at the meeting described the site as about six miles east of Price and said Valar chose it after a multi-state search.
- 8.20.2026 TLA Board Packet (Discussion Item 9A: SULA 2095 OBA, Board Meeting Discussion Memorandum) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-08-20) primary government “an integrated nuclear energy, advanced manufacturing, critical mineral refining, and data center computing campus”
- 2026-08-20 TLA Board of Trustees Meeting Audio Transcript (auto-generated) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-08-20) primary government
At the 20 August 2026 board meeting Valar's head of projects, Max Ukropina, said the company talked to more than 20 states and that in 2024 he came to Utah and met the Office of Energy Development, the Governor's economic office, SERDA and Carbon County. The auto-transcript then renders him as saying 'the first property I looked at was actually property', apparently referring to the parcel under discussion, back when the plan was to make fuels from coal-plant flue gas; the garbled wording does not settle which property he meant. On 17 September another Valar speaker said 'Max came to look at sites in September', without a year. Ukropina said the Emery lab is no longer just a test facility but Valar's 'whole Utah operations', including its fuel facility, and that Valar is 'currently purchasing 110 acres north of the lab from Emery County'. The records differ on whether that purchase has closed: ETV News wrote on 28 July 2026 that, according to Valar, extra water shares would support development on 'the larger property Valar recently purchased from Emery County'; ETV reported on 20 August an 'ongoing annexation of Valar property into Orangeville City'; and the Utah Inland Port Authority wrote on 10 September 2026 that Valar 'has also purchased' more than 100 acres next to the state research center, inside its Castle Country Project Area. Staff described Valar as headquartered in Hawthorne, California (orig-036).
- 2026-08-20 TLA Board of Trustees Meeting Audio Transcript (auto-generated) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-08-20) primary government “currently purchasing 110 acres north of the lab from Emery County”
- Castle Country Project Area Builds Momentum Across Energy, Critical Minerals and Logistics (Utah Inland Port Authority, 2026-09-10) primary government “Valar has also purchased more than 100 acres adjacent to the state-owned research center”
- Emery County Commissioners Debate Solar, Data Centers and EMS Funding (ETV News (Kevin Butler and Julie Johansen), 2026-07-28) news “the larger property Valar recently purchased from Emery County”
- Growth, industry and community issues highlight Orangeville council meeting (ETV News (Kevin Butler and Julie Johansen), 2026-08-20) news “the ongoing annexation of Valar property into Orangeville City”
- 09.17.2026 TLA Board of Trustees Meeting Audio Transcript (auto-generated) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-09-17) primary government “Max came to look at sites in September.”
In July 2025 Valar told an Emery County town hall, and its slides said, that Ward 250 would be a test of about 12 months with 30 effective full-power days in a temporary facility (orig-045), and its safety agreement set a 12-month run and an 18-month life ending in decommissioning (orig-034). The same 2025 slide deck also projected 'Commercial Deployment by 2028', without naming a site. By August 2026 the company described the Emery lab as its 'whole Utah operations' including a fuel facility, was acquiring about 110 acres beside it (mine-018), had applied to BLM for a 10,270-acre site near Green River and a second site (mine-006), and won a lease of up to a century on the Carbon County parcel for a reactor, fuel and industrial campus (mine-010, mine-011).
- Valar Atomics + SRERC in Emery County (Valar Atomics (posted on Utah Public Notice Website), 2025-07-08) primary company “operates for 30EFPD, in 12 months in a temporary facility.”
- 2026-08-20 TLA Board of Trustees Meeting Audio Transcript (auto-generated) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-08-20) primary government “It's now our whole Utah operations that includes our fuel facility.”
- BLM Natl MLRS Rights of Way (ROW) (feature layer and query results) (Bureau of Land Management (MLRS)) primary filing
The staff memorandum (August and September versions) says the parcel has generated 'approximately $4,000 per year', mostly from the Utah National Guard lease; at the 20 August meeting staff told the board 'we are making $4,000 and some change' without saying per what period. The official 20 August 2026 minutes, approved and posted in September, record staff saying it yields approximately $4,000 per month from the Utah National Guard. The memorandum's figure is the one used to argue the Valar deal is a strong opportunity for the trust.
- 8.20.2026 TLA Board Packet (Discussion Item 9A: SULA 2095 OBA, Board Meeting Discussion Memorandum) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-08-20) primary government “approximately $4,000 per year”
- 08.20.2026 FINAL TLA Minutes (Utah Trust Lands Administration (Utah Public Notice Website), 2026-09-17) primary government “approximately $4,000 per month”
The minutes of the Trust Lands board's 20 August 2026 meeting (in the 17 September packet, on that day's agenda for approval) record that, answering an online question about jobs after construction, Valar's Max Ukropina and Jess Housekeeper said full development plans were still being finalized and that the current facility 'employs roughly 40 full-time local residents' and uses 50 to several hundred local contractors within a 20-30 mile radius, supported by six recruiters. Beside the other figures on record: on 1 July 2026 ETV reported Valar officials saying the company had hired about 50 local employees, not counting contractors; per loc-004, in April 2026 Valar told Ferron it employed 120 people in Emery County, many not living in Utah; in August it told Orangeville it had recently hired 40 people from the area; it projects 275 jobs for its state tax credit (fund-017); its job board lists 21 open Orangeville positions and 71 in California (plan-011). The figures mostly count different groups; the August figure is limited to full-time local residents, while the July figure's definition was not given; no payroll or headcount filing was found to check them.
- Board of Trustees Meeting Materials, September 17, 2026 (minutes of August 20, 2026 for approval, pages 10-11) (Utah Trust Lands Administration, via Utah Public Notice Website, 2026-09-17) primary government “their current facility employs roughly 40 full-time local residents”
- Emery County takes center stage as Valar and Nvidia power historic breakthrough (ETV News (Kevin Butler), 2026-07-01) news “hired approximately 50 local employees, not including contractors”
Valar's local faces in the public record: Jess Housekeeper, director of Utah operations, an Emery County native who told the Trust Lands board he left the area for about 15 years for work (Deseret News, Mar and Jun 2026; Trust Lands transcripts and minutes, Aug and Sept 2026); Harry Hansen, who said on 17 September 'I do public affairs for Valor Atomics' and whom Trustee Mike Mower praised on 20 August, with the Valar team, for answering many of the public's questions (auto-transcript); Cory Gardner, 'Valar's head of commercial development' per ETV News (25 Jun 2026), who spoke for Valar at the Price City Council, the Carbon County Commission on 19 August 2026 (mine-033) and the Trust Lands board. This Cory Gardner is not shown by any source read to be the former U.S. senator of the same name, and should not be confused with him. Mother Jones and The New Republic name Elijah Froh as Valar's director of business operations. None of these people appears in Valar's public safety documents, which name roles, not people. A Valar radiation-protection staff member (26 years in the field, 22 in Idaho) also spoke on 17 September and said he would hire and train local radiation technicians; he is described, not named.
- 09.17.2026 TLA Board of Trustees Meeting Audio Transcript (auto-generated) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-09-17) primary government “I do public affairs for Valor Atomics”
- 08.20.2026 FINAL TLA Minutes (Utah Trust Lands Administration (Utah Public Notice Website), 2026-09) primary government “Jess Housekeeper, Director of Utah Operations for Valor Atomics and an Emery County native”
- Price City Council celebrates Valar Atomics reaching full power ahead of schedule (ETV News, 2026-06-25) news “Gardner, Valar’s head of commercial development”
- Valar Atomics' nuclear reactor reaches criticality in Utah (Eva Terry) (Deseret News, 2026-06-18) news “Jess Housekeeper, Valar’s director of Utah operations”
- Mother Jones (Kiera Butler), 26 Feb 2026 (May+June 2026 issue) (Mother Jones, 2026-02-26) news “serves as Valar’s director of business operations”
- 2026-08-20 TLA Board of Trustees Meeting Audio Transcript (auto-generated) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-08-24) primary government “Harry Hanson's done an awesome job.”
The Utah Trust Lands Administration posted a notice that it had received an application, from an applicant it did not name, for Section 16, Township 14 South, Range 11 East, SLB&M, about 640 acres near Wellington in Carbon County, and invited competing bids to lease, buy or exchange it by August 7, 2026. The board's August 20, 2026 agenda lists a discussion item on a Special Use Lease Agreement (SULA 2095 OBA) for 640 acres in Carbon County with Valar Atomics. This was the first primary record found of Valar seeking a site outside the Emery County test lab. Later records settle what this fact first left open: the board memo gives Section 16 as the lease (csite-002), and the board approved the arrangement on September 17, 2026 (mine-011, csite-001). The notice named neither Valar nor a nuclear use (csite-005, mine-012).
- Board of Trustees Meeting Agenda Thursday, August 20, 2026, at 9:00 a.m. (Utah Trust Lands Administration (Utah Public Notice Website), 2026-08-20) primary government “located in Carbon County, Utah (640 +/- acres) with Valar Atomics”
- Public Notice - Business Opportunity - Carbon County (Utah Trust Lands Administration) primary government “has received an application on the following property near Wellington in Carbon County”
Carbon County Commission minutes, 19 August 2026, item 9 (the item right after the 'Valor Atomics presentation'): commissioners approved, contingent on Emery County's approval, on Commissioner Haddock's motion seconded by Commissioner Jensen (the motion carried), a joint $60,000 consulting agreement with John Cox of Utah Public Affairs Consulting 'to identify and secure economic development opportunities' across coal, natural gas, nuclear and advanced manufacturing, split $30,000 each with Emery County; Carbon's half comes from unused economic-development consulting funds; the commission approved it contingent on Emery's approval. Emery County's 1 September minutes approve 2027 rural county grant projects that include $30,000 (printed '$30,00') for a 'potential Economic Development Consultant' (the grant money comes from the state's rural county grants); one commissioner said he would rather Emery had its own consultant, not one shared with Carbon; on 15 September the commission 'agreed to move ahead with a possible partnership' with Carbon to hire the consultant (ETV). No record read shows the signed agreement, the contract text, or whether the consultant has any tie to Valar or other nuclear developers. On the same 19 August item 8, the minutes record Valar saying it 'relocated to the region from California two years ago'; Valar's job board still lists 71 of its 92 openings in Torrance, California (loc-019), and its Carbon claim notice gives a Torrance address (orig-036).
- Aug 19, 2026 Commission Meeting Minutes (Carbon County Board of Commissioners; scanned, read as page images) (Carbon County Commission, 2026-08-19) primary government “They relocated to the region from California two years ago”
- Carbon County Commission Meeting, August 19, 2026 (notice and agenda; items 8 and 9) (Carbon County Commission, 2026-08-19) primary government
- Emery County Commission Meeting Minutes, September 1, 2026 (CM09012026), item on 2027 Rural County Grant projects (Emery County Commission, 2026-09-01) primary government
- Emery County delays solar decision, pauses new conditional use permits (ETV News, 2026-09-21) news
Carbon County Commission minutes, 19 August 2026, 'Unscheduled Public Update': Commissioner Larry Jensen said the commission had lifted a long-standing non-disclosure agreement (NDA) to give an economic update, announcing that Georgia-Pacific had cancelled plans for a $600 million wallboard factory on county-owned land because of rising project costs. The plant would have employed 160 people using a gypsum mine in Emery County, and the minutes say the strict NDA was needed to protect the company's plans because the new plant would have closed two factories in California. The same meeting heard the 'Valor Atomics presentation' (loc-012) and approved the joint economic-development consultant (loc-029). A week earlier Commissioner Jared Haddock had said such agreements are typically required by companies, not the county (loc-002). This is a primary record that Carbon County has handled a major industrial prospect under an NDA and kept it from the public until the deal ended. It does not show an NDA with Valar: none appears in any record read, and the minutes do not say whether other NDAs are in force. A GRAMA request to the county would settle it (open_questions).
- Aug 19, 2026 Commission Meeting Minutes (Carbon County Board of Commissioners; scanned, read as page images) (Carbon County Commission, 2026-08-19) primary government “The strict NDA was necessary to protect the company's plans”
ETV News (24 Aug 2026) reported the Emery County Business Chamber's 'Lunch and Learn' tour of Valar's site on 19 August 2026. The report says the reactor is now enclosed in cement block walls; that the site has exhaust equipment designed to detect radioactive particles and shut off the exhaust if there is any potential for outside contamination; and that the helium-cooled design lets the reactor shut down within seconds, 'completely removing the risk of a meltdown'. That last sentence is the paper's narration of what the group learned on the company's tour and is not attributed to a named speaker, so it cannot be treated as Valar's exact words. The report also says Valar discussed 'potential plans' to produce reactors for industrial businesses so heavy power users can move off the grid, citing the Price firm Intermountain Electronics 'strictly as an example'. Set beside the record: Valar's own Nuclear Safety Design Agreement (October 2025 draft) analyses a bounding 'maximum hypothetical accident' that assumes TRISO fuel particle failures beyond demonstrated limits and a release of radioactive material, and estimates the resulting dose at the site boundary (safe-013, loc-035); the Union of Concerned Scientists calls TRISO 'far from meltdown-proof' (safe-025). No public monitoring data for the exhaust system has been published (safe-024). Supplying reactors to private businesses would be commercial use, which the DOE research pathway Ward 250 runs under does not cover; that would need separate licensing (safe-030).
- Emery County Business Chamber gets an up-close look at Valar Atomics' progress (Stephanie Olsen) (ETV News, 2026-08-24) news “completely removing the risk of a meltdown”
- Ward250 Nuclear Safety Design Agreement (Document 100403, Revision 02, marked draft, October 2025) (Valar Atomics, 2025-10) primary company “TRISO fuel particle failures exceeding demonstrated limits”
At Emery County's 7 April 2026 hearing on the land sale, residents raised truck traffic along Highway 29, and the state lab director told the hearing that the land was zoned as an industrial park for exactly this kind of expansion (ETV, 9 April). Earlier, on 19 February 2026, an Orangeville councilman asked for opinions on whether the city wants Valar to haul its 'nuclear parts' through town or to ask that they go around on the highway (minutes). On 7 July 2026 Emery County approved a memorandum of understanding with Orangeville for three speed-limit signs, contingent on partnerships and funding (ETV, 8 July), and on 13 August the Orangeville council approved its MOU with the county and the Utah Highway Patrol (minutes), city officials saying the signs had become more urgent with increased traffic from mining and Valar (ETV, 20 Aug). The council also noted coal trucks from the Fossil Rock mine, now in production, on Coal Haul Road, the road that serves the lab. No traffic study for Valar's site or the planned expansion was found in any record read.
- Emery Commission public hearing receives comments on the sale of property to Valar Atomics (ETV News, 2026-04-09) news
- Growth, industry and community issues highlight Orangeville council meeting (Kevin Butler) (ETV News, 2026-08-20) news
- Emery County Commission honors Ellertson, approves rodeo team donations (ETV News, 2026-07-08) news
- February 19, 2026 City Council Meeting Minutes (Orangeville; notice text) (Orangeville City, 2026-02-19) primary government “wants Valor to haul their nuclear parts through town”
- August 13, 2026 City Council Minutes (Orangeville) (Orangeville City, 2026-08-13) primary government “MOU with Emery County and UHP for Speed Limit Signs”
Records on whether Valar's purchase of Emery County parcel 04-0019-0030 (about 112 acres beside the lab, $394,500, gov-022) has closed: 7 July 2026, an Emery commissioner who signed the due-diligence extension said the land 'has been sold' (gov-022), and the extension itself gave 30 more days for a survey (ETV, 8 July). 28 July, ETV, reporting the 21 July county meeting, described 'the larger property Valar recently purchased' (mine-042). 13 August, Orangeville council minutes: Valar's Harry Hansen said Valar is 'waiting on a clean title to purchase the property', and the mayor said Valar was working on a title search and mineral rights and that annexation could begin 'once sale is finalized'. 20 August, Valar's Max Ukropina told the Trust Lands board Valar is 'currently purchasing' the land (mine-018). 10 September, the Utah Inland Port Authority wrote that Valar 'has also purchased' more than 100 acres there (gov-018). By Valar's own account in mid-August the purchase was not complete; whether it closed between 20 August and 10 September is not shown in any record read. A deed recorded with the Emery County Recorder would settle it.
- August 13, 2026 City Council Minutes (Orangeville) (Orangeville City, 2026-08-13) primary government “waiting on a clean title to purchase the property”
- Emery County Commission honors Ellertson, approves rodeo team donations (ETV News, 2026-07-08) news
Public records of local concern, residents described and not named: Wellington City's planning commission put 'Data Centers moratorium and/or strict guidelines' on its 1 April 2026 agenda (its minutes of that meeting were approved on 6 May but are not posted); its posted minutes for 6 May, 3 June and 5 August do not return to the item and mention neither Valar nor the trust-land site about six miles north of town, and record no public comments on 3 June or 5 August. At the Emery County Commission on 21 July 2026 a resident asked for a 180-day pause on data-center applications, proposed eight areas for rules (water, chemicals, noise, heat, water-rights transparency, ratepayer protection, emergency power, reclamation bonds) and questioned the county's sale of land to Valar and its annexation into Orangeville (ETV, 28 July; the commission's minutes list only an informational presentation, gov-024). Orangeville's 13 August minutes record a resident raising concerns with Valar at the city's planning meeting, and Cleveland Town's 13 August minutes record a resident's email asking for a moratorium on AI and data centers, which the council tabled for research. In Carbon County, the planning commission began drafting rules for 'highly contested industries' in August (csite-013), and the only comment at the Trust Lands hearings acknowledging opposition was a commissioner's reference to 'a few in our community who will push back' (mine-014). Officials in turn spoke of misinformation: an Orangeville councilman on 9 July ('mis- information on social media', minutes), ETV on 28 July about the water shares, and Orangeville's mayor saying data-center talk was speculation (ETV, 20 Aug). On 15 September Emery County approved a 180-day pause on new Level 2 and 3 permit applications (ETV, 21 Sept; loc-024). No local public hearing on Valar's Carbon site has been held as of 29 September 2026.
- Wellington City Planning & Zoning agenda, April 1, 2026 (item 4: Data Centers moratorium and/or strict guidelines) (Wellington Planning Commission, 2026-04-01) primary government
- Wellington City Planning and Zoning Minutes, May 6, 2026 (scanned, read as page images; approves the April 1 minutes, which are not posted) (Wellington Planning Commission, 2026-05-06) primary government
- Emery County Commissioners Debate Solar, Data Centers and EMS Funding (Kevin Butler) (ETV News, 2026-07-28) news
- August 13, 2026 City Council Minutes (Orangeville) (Orangeville City, 2026-08-13) primary government “has addressed some concerns with Valor during the Planning and Zoning Meeting”
- Cleveland Town Council Meeting Approved Minutes 8/13/2026 (notice text) (Cleveland Town, 2026-08-13) primary government
- July 9, 2026 City Council Meeting Minutes (Orangeville) (Orangeville City, 2026-07-09) primary government “Lots of mis- information on social media being spread currently”
- Growth, industry and community issues highlight Orangeville council meeting (Kevin Butler) (ETV News, 2026-08-20) news
- Wellington City Planning and Zoning Minutes, June 3, 2026 (scanned, read as page images) (Wellington Planning Commission, 2026-06-03) primary government “No Public Comments.”
- Wellington City Planning and Zoning Minutes, August 5, 2026 (scanned, read as page images) (Wellington Planning Commission, 2026-08-05) primary government “No public comments”
- Wellington Planning Commission notices, April to September 2026 (Utah Public Notice Website) primary government
- Emery County delays solar decision, pauses new conditional use permits (Stephanie Olsen) (ETV News, 2026-09-21) news “unanimously approved a 180-day pause”
The Utah Energy Research Board's amended agenda for 12 August 2026 (file dated 6 August 2026) places the meeting at the Utah San Rafael Energy Lab, 800 North Coal Haul Rd, Orangeville, 10 to 11 a.m., with a video and phone option. It lists a lab update (item 7), 'OTHER BUSINESS: Open to public comment' (item 13), and, after the meeting, a 'Tour of Utah San Rafael Energy Lab and Valar Atomics for Board Members'. The agenda has no item on a Valar project (gov-014) and does not say whether the public could join the tour. The board's first meeting, on 13 August 2025 in Salt Lake City, at which it approved 'the Valar Project', also closed with a public comment period, in which attendees, per the minutes, expressed appreciation for the board's formation (gov-013). The 12 August 2026 minutes were not read.
- Utah Energy Research Board Amended Agenda, August 12, 2026 (Utah Energy Research Board (Utah Public Notice Website), 2026-08-12) primary government “Tour of Utah San Rafael Energy Lab and Valar Atomics for Board Members”
- Utah Energy Research Board Amended Agenda, August 12, 2026 (Utah Energy Research Board (Utah Public Notice Website), 2026-08-12) primary government “OTHER BUSINESS: Open to public comment”
- Board Meeting Minutes, Utah Energy Research Board, August 13th, 2025 (Utah Energy Research Board (Utah Public Notice Website), 2025-11-13) primary government “The meeting included a public comment period”
Emery County Planning Commission minutes: 10 June 2026, a county commissioner said no formal data-center application had been filed though the county had had informal inquiries, and staff said current zoning has general setbacks but no standards specific to data centers; 8 July, members discussed ordinances for data-center water use, cooling, noise and siting, and, in the solar discussion, 'acknowledged previous shortcomings in notification procedures' after residents raised a lack of public maps and project information; 12 August, staff said several different versions of the county ordinances 'had been circulating, creating confusion', compiled one consolidated book as the starting point, and members discussed updating ordinances for emerging industries 'including nuclear projects, data centers, and solar'. On 18 August the County Commission listed putting nuclear development under its Level III conditional use permit and a moratorium on Level II and III permits, and on 15 September an ordinance for a 180-day moratorium (gov-024, mine-043). ETV reports that on 18 August the commission suspended new commercial solar applications and directed ordinance changes classifying large-scale industrial projects, 'including solar, data centers and nuclear facilities', as Level III conditional uses, with Commissioner Keven Jensen noting the county 'currently has little specific ordinance language' on data centers or nuclear development, and that on 15 September it unanimously approved a 180-day pause on new Level 2 and Level 3 applications, not affecting projects already in process (the minutes are not yet posted). For the Ward 250 building the commission voted the building permit itself (gov-021). Valar's lab-side parcel is headed for annexation into Orangeville, whose own 'Advanced Energy and Manufacturing' zone is being drafted (loc-013). Green River City's planning commission put 'Discuss Nuclear Reactors - When, where, why, how' and a matching data-centers item on its 21 July and 18 August 2026 agendas (state notice site; only audio of those meetings is posted).
- Emery County Planning Commission minutes, June 10, 2026 (Emery County Planning and Zoning Commission, 2026-06-10) primary government
- Emery County Planning Commission minutes, July 8, 2026 (Emery County Planning and Zoning Commission, 2026-07-08) primary government “Commission members acknowledged previous shortcomings in notification procedures”
- Emery County Planning Commission minutes, August 12, 2026 (Emery County Planning and Zoning Commission, 2026-08-12) primary government
- Solar moratorium approved in Emery County (ETV News, 2026-08-24) news “currently has little specific ordinance language addressing data centers or nuclear development”
- Emery County delays solar decision, pauses new conditional use permits (ETV News, 2026-09-21) news
- Green River City Planning & Zoning Meeting, July 21, 2026 (agenda items 3-4) (Green River City, 2026-07-21) primary government “Discuss Nuclear Reactors - When, where, why, how”
- Green River City Planning & Zoning Meeting, August 18, 2026 (agenda items 2-3) (Green River City, 2026-08-18) primary government “Discuss Nuclear Reactors - When, where, why, how”
ETV News (14 Aug 2026) reported the Carbon & Emery Energy Collaborative held on 12 August 2026 at the Southeastern Regional Development Agency's offices in Price. Carbon County Commissioner Jared Haddock said the county had lost roughly $1 billion in taxable value over the past decade and that one large data center could provide a tax base comparable to about 4,200 homes. He also addressed concerns about nondisclosure agreements connected to economic development projects, saying (as ETV paraphrased him) that such agreements are typically required by the private companies considering an area rather than by the county, and that another company was looking at bringing industry to Carbon County, with details limited. At the same event Valar's Jess Housekeeper spoke of plans to eventually manufacture reactors and fuel (loc-003). The report names no Valar site. Eight days later Haddock told the Trust Lands board the county had worked with Valar 'since the beginning' (ppl-020). One week after the summit, the commission's own minutes (19 Aug 2026) record it lifting a 'long-standing' NDA on a separate $600 million factory prospect that had been cancelled (loc-036). No nondisclosure agreement between Carbon County and Valar appears in any record read; neither the report nor the minutes say one exists.
- Leaders look to coal, nuclear and new industry for growth at local energy summit (Kevin Butler) (ETV News, 2026-08-14) news “typically required by private companies considering an area”
- Aug 19, 2026 Commission Meeting Minutes (Carbon County Board of Commissioners; scanned, read as page images) (Carbon County Commission, 2026-08-19) primary government “lifted a long-standing non-disclosure agreement (NDA)”
Trust Lands' public notice for the parcel (now archived) said the agency had received an application on 640 acres in Sec. 16, T14S R11E near Wellington and invited competing bids to lease, buy or exchange it by 5 p.m. on 7 August 2026 (with $51,100 in deposits and fees). It did not name the applicant or say what the land would be used for. The board memorandum says notices were also posted in the local newspaper (not named), on the agency website, and sent to existing lessees, permittees and adjoining landowners under rule R850-30-500; that notice ran for 30 days on the state Resource Development Coordinating Committee (RDCC) dashboard and went to the Carbon County Commission and the Southeastern Regional Development Agency; and that no competing offers came in. The only agency comment recorded is from the Division of Water Rights.
- Public Notice - Business Opportunity - Carbon County (Utah Trust Lands Administration) primary government “has received an application on the following property near Wellington in Carbon County”
- 8.20.2026 TLA Board Packet (Discussion Item 9A: SULA 2095 OBA, Board Meeting Discussion Memorandum) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-08-20) primary government “No competitive offers were received prior to the application deadline.”
Signed minutes of the 4 August 2026 Planning Commission meeting (scanned; read by OCR) record the zoning administrator presenting a map of possible development areas with a one-mile buffer around cities for 'big infrastructure projects' and a half-mile buffer around county addresses, limited to the Mining & Grazing zone. A commissioner proposed a conditional overlay permit for 'highly contested industries' and said he did not want large computer companies to 'fly under the guise of Industrial zoning'; members listed possible conditions (water use, evaporation, heat, power supply, the county's finances). The administrator asked members to list conditions and said he would like a public hearing in November 2026, aiming to finish the code update by year end. Valar, nuclear power and the Wellington parcel are not mentioned. The parcel lies about five miles from Wellington (csite-002), outside a one-mile city buffer.
- 2026-08-04 AUG MINUTES-SIGNED (Carbon County Planning Commission; scanned, read by OCR) (Carbon County Planning Commission (Utah Public Notice Website), 2026-08-04) primary government “fly under the guise of Industrial zoning”
Orangeville City records: on 11 December 2025 the mayor told the council he would like to see Valar annexed into the city (minutes; he had first raised annexation in September 2025). On 17 March 2026 a special service district asked Emery County that Valar's parcel be annexed into Orangeville (gov-022), and on 19 May the county sent annexation notices (gov-022); on 21 May the Castle Valley Special Service District board reviewed pending annexations including property near Orangeville 'that may be developed by Valor', noting recent state law changes that allow a streamlined annexation by landowner petition (minutes). The city's 11 June minutes record staff 'working on annexation requirements' and the mayor meeting Valar about annexation. On 9 July council minutes record staff 'working on Nuclear Energy Ordinance', and that the city had sent a draft of 'the nuclear energy industry ordinance' being coded to allow Valar to be annexed; the annexation process was to begin at the August meeting with a Valar representative present. The Planning and Zoning Commission's 16 July minutes record an agenda item 'Ordinance I-2 Advanced Energy and Manufacturing District', with Valar's Jess Housekeeper present as its representative: 'There needs to be a plan for an ordinance for this company and future companies', he 'explained the wants and needs for this company', a public meeting would need to be posted by 30 July in draft form, and 'Everything needs to go through the attorneys from the City and Valar.' The commission's later agendas (11 August, 8 September, 17 September work meeting) do not list the I-2 ordinance, and no public hearing on it was found in the council's or the planning commission's notices through the 8 October 2026 council notice (a hearing on a cemetery fee). On 13 August the mayor said annexation could begin once the sale is final (loc-014). The planning commission's 8 September agenda and the council's 10 September agenda list an 'Updated Annexation Policy', the council's item 'to reflect legislative changes'. At the county, commissioners said on 21 July that annexation would put the land under Orangeville's authority for services and future land-use decisions (ETV, 28 July).
- September 11, 2025 City Council Minutes (Orangeville; notice text) (Orangeville City, 2025-09-11) primary government
- December 11, 2025 City Council Minutes (Orangeville) (Orangeville City, 2025-12-11) primary government “he would like to see them annexed into the city”
- June 11, 2026 City Council Minutes (Orangeville) (Orangeville City, 2026-06-11) primary government “Mayor will be meeting with Valor regarding annexation”
- July 9, 2026 City Council Meeting Minutes (Orangeville) (Orangeville City, 2026-07-09) primary government “we have sent a draft of the nuclear energy industry ordinance”
- Orangeville City Planning and Zoning Commission minutes, July 16, 2026 (notice text) (Orangeville City Planning and Zoning, 2026-07-16) primary government “Everything needs to go through the attorneys from the City and Valar.”
- Orangeville Planning and Zoning Commission agenda, August 11, 2026 (Orangeville City Planning and Zoning, 2026-08-11) primary government
- Orangeville Planning and Zoning Commission agenda, September 8, 2026 (Orangeville City Planning and Zoning, 2026-09-08) primary government
- Orangeville Planning and Zoning Commission work meeting agenda, September 17, 2026 (Orangeville City Planning and Zoning, 2026-09-17) primary government
- Orangeville City Council agenda, September 10, 2026 (Orangeville City, 2026-09-10) primary government
- August 13, 2026 City Council Minutes (Orangeville) (Orangeville City, 2026-08-13) primary government “Once sale is finalized Annexation process can begin”
- Orangeville City Council notices through the 8 October 2026 public hearing notice (Utah Public Notice Website) primary government
- Emery County Commissioners Debate Solar, Data Centers and EMS Funding (Kevin Butler) (ETV News, 2026-07-28) news
- CVSSD Regular Meeting Minutes, May 21, 2026 (approved; scanned, read as page images) (Castle Valley Special Service District, 2026-05-21) primary government “property near Orangeville that may be developed by Valor”
- Orangeville Planning and Zoning Commission notices, May to September 2026 (Utah Public Notice Website) primary government
The Trust Lands memorandum cites public workshops hosted by Carbon County, SERDA and the Utah Office of Energy Development, in which Valar took part, as part of the outreach behind the lease (mine-012, mine-014). The Office of Energy Development's events page lists a 'Carbon County - Community Nuclear Series' at the Carbon County Event Center in Price on 21 May and 18 June (both described as a look at how modern SMRs work) and 16 July 2026 (how modern nuclear waste is handled, stored and reused). The listings do not mention Valar, Wellington, trust lands or a planned campus. Staff told the board in September that further sessions were held in August and the week before the 17 September meeting; those are not on the events page. Whether the Wellington site was discussed at any session is not in the records read.
- Events - Utah Office of Energy Development (Utah Office of Energy Development) primary government
- 8.20.2026 TLA Board Packet (Discussion Item 9A: SULA 2095 OBA, Board Meeting Discussion Memorandum) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-08-20) primary government
- 09.17.2026 TLA Board of Trustees Meeting Audio Transcript (auto-generated) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-09-17) primary government
The newspaper notice the Trust Lands memo mentions without naming the paper (csite-005, mine-012) is ETV News's 'TRUST LANDS OPPORTUNITY', published 15, 22 and 29 July 2026: Trust Lands 'has received an application on the following property near Wellington' (T14S R11E, Section 16, about 640 acres) and will take bids to lease, buy or exchange it by 5 p.m. on 7 August 2026; a bidder must submit a bid, a development plan and an application with $50,000 earnest money and $1,100 in fees; details by phone or at the Monticello office. It names no applicant, no use and no lease number (the lease was already numbered SULA 2095 and mapped by 9 April, mine-048). The first printing gave 23 days to prepare a competing bid and development plan; the web notice had gone up on 8 July (csite-005). The same agency's notices in the same paper do sometimes state the use: a 19 August 2026 notice for 319.55 acres of Carbon County trust land says the application is 'for a commercial photovoltaic solar power generation project', and a 24 June 2026 notice describes an application to remove sand and gravel; a December 2025 Emery notice gives no use but cites its lease number (SULA 2087). Trust Lands' rule lets a notice include information that does not breach the confidentiality of the application (csite-005), so naming the use was a choice, not a requirement; the record does not say why the Wellington notice omitted it.
- TRUST LANDS OPPORTUNITY (legal notice: Township 14 South, Range 11 East, Section 16, near Wellington) (Utah Trust Lands Administration (legal notice published in ETV News), 2026-07-15) primary government “has received an application on the following property near Wellington”
- PUBLIC NOTICE (Trust Lands: application to lease 319.55 acres in Carbon County for a commercial photovoltaic solar project) (Utah Trust Lands Administration (legal notice published in ETV News), 2026-08-19) primary government “for a commercial photovoltaic solar power generation project”
- PUBLIC NOTICE (Trust Lands: application to remove sand and gravel, T13S R9E Sec. 25, Carbon County) (Utah Trust Lands Administration (legal notice published in ETV News), 2026-06-24) primary government
- PUBLIC NOTICE (Trust Lands: application to lease 79.95 acres, T17S R8E Sec. 34, Emery County, Reference SULA 2087) (Utah Trust Lands Administration (legal notice published in ETV News), 2025-12-17) primary government
The GOED board's executive summary for Valar Atomics Inc. (9 July 2026) adds to csite-024 and gov-033: timeline '2026'; Emery County (county class 5); capital investment $1,299,110,000; 275 full-time jobs at an average wage of $137,567; projected new state wages of $337,864,790, new state revenue of $213,474,999 and withholding of $11,402,937 over 10 years. The credit is 50% of new incremental state tax revenue above the prior 12-month baseline, paid yearly after the revenue is received, capped at $106,737,499, with a contractual recapture of any excess. Conditions: meet the job projections at 100% of the county average wage, keep the operation in Utah for the 10-year incentive period, count only jobs and revenue created after board approval, and get a local incentive proposal approved by GOED's Incentives Committee, since incentives are 'site specific and subject to local incentive participation'. The company overview says Valar aims to power data centers, hydrogen production and synthetic fuels from 'gigasites'. Set beside the record: on 7 April 2026, asked what incentives the county had given Valar, the answer recorded was 'None', and a commissioner added that Valar had 'not even asked' for a tax incentive (gov-033); the state credit cannot be earned without a local incentive, and none for Valar had been found on county agendas through September 2026 (gov-033); in April 2026 Valar said it employed 120 people in Emery County, many not living in Utah (loc-004). The capital figure covers far more than the one test reactor described to residents in 2025 (orig-045).
- GOED Public Board Materials, July 9, 2026: GOED Board Executive Summary, Valar Atomics Inc. (Board of the Governor's Office of Economic Development (Utah Public Notice Website), 2026-07-09) primary government “Incentives are site specific and subject to local incentive participation.”
- GOED Public Board Materials, July 9, 2026: Proposed Motion (Valar Atomics Inc.) (Board of the Governor's Office of Economic Development (Utah Public Notice Website), 2026-07-09) primary government “Must commit to keep operation in Utah for the length of the incentive period”
Re-reading the GOED board's 9 July 2026 materials and minutes (csite-024 has the incentive terms): the executive summary describes a $1,299,110,000 Emery County project with 275 jobs averaging $137,567, and says the up-to-$106,737,499 REDTIF credit (half of new state tax revenue for 10 years, paid only after the revenue comes in) is 'site specific and subject to local incentive participation', with a local incentive proposal needing GOED Incentives Committee approval. Per the minutes, Valar's Harry Hansen cited the NVIDIA chip demonstration and 'a waterless data center in Orangeville'; Valar's Cory Gardner said Valar plans 'to install additional commercial units in the area', that the fastest path to turning reactors on is selling power 'behind the meter' to avoid interconnection queues, that its near-term strategy is 'behind-the-meter customers willing to pay a premium', and that no one has yet sold power from an advanced reactor in America. The minutes list Emery County Commissioner Jordan Leonard among the visitors under 'Valar Atomics' (they do not say why) and record him speaking in support. Set beside the record: three months earlier, at the county's 7 April hearing, the answer recorded to 'what incentives has the county given you?' was 'None', with a commissioner adding Valar had 'not even asked' for a tax incentive (gov-022); no local incentive for Valar appears on the Emery County Commission's or its Community Reinvestment Agency's agendas through September 2026 (Utah Public Notice Website scan, 29 Sept 2026); and DOE's legal basis for authorizing Ward 250 without the NRC is that pilot reactors do not produce commercial electric power (safe-030, gov-007), so sold power from 'commercial units' would need NRC licensing (csite-010).
- GOED Public Board Materials, July 9, 2026 (Valar Atomics Inc. executive summary) (Governor's Office of Economic Opportunity (Utah Public Notice Website), 2026-07-09) primary government “Incentives are site specific and subject to local incentive participation.”
- GOED Board Meeting Minutes, July 9, 2026 (posted with the Sept 10, 2026 meeting) (Governor's Office of Economic Opportunity (Utah Public Notice Website), 2026-09-10) primary government “they plan to install additional commercial units in the area”
- Emery County Commission Meeting Minutes, April 7, 2026 (Emery County Commission (Utah Public Notice Website), 2026-04-07) primary government “they have not even asked for any tax incentive”
ETV News (16 July 2026) reported that at the Orangeville City Council meeting of 9 July 2026 a councilman said Orangeville ambulance availability was 13% during the past month, against 24% the month before; that closure of the Orangeville-Castle Dale ambulance garage was being considered if staffing could not be fixed; and that the county had tabled the EMS district's funding request. On 21 July the Emery County Commission voted to direct the first $200,000 of state payment-in-lieu-of-taxes money each year for five years to the emergency medical district, to raise on-call pay by $2 an hour (ETV, 28 July). Valar's safety agreement asks to plan for on-site emergencies only and relies on coordination with Emery County Emergency Management, Emery County Fire and local responders (safe-016); no public emergency plan or drill record for Ward 250 was found (safe-016). How often an ambulance would be available for the Valar site, which lies on Coal Haul Road west of Orangeville (Castle Dale minutes, 12 March 2026), is not in any record read. The city's own minutes confirm the 13% figure for June (9 July); record on 11 June the fire chief saying the ambulance had been 'only available 14% of the time' and a council report that county ambulance arrival times were averaging 25 minutes and that stations might be combined; and record the city fire chief saying on 19 February that he would meet Valar on its fire safety plan and reporting on 12 March that he had gone through Valar's safety protocols and 'everything is looking well'.
- Orangeville City Council approves resolutions, discusses EMS and Valar (Kevin Butler) (ETV News, 2026-07-16) news
- Emery County Commissioners Debate Solar, Data Centers and EMS Funding (Kevin Butler) (ETV News, 2026-07-28) news
- July 9, 2026 City Council Meeting Minutes (Orangeville) (Orangeville City, 2026-07-09) primary government “Orangeville Ambulance had a 13% availability for the month of June”
- June 11, 2026 City Council Minutes (Orangeville) (Orangeville City, 2026-06-11) primary government “County ambulance arrival time is averaging 25 minutes”
- February 19, 2026 City Council Meeting Minutes (Orangeville; notice text) (Orangeville City, 2026-02-19) primary government “will meet with valor on the Fire Safety Plan for the facilities”
- March 12, 2026 Regular Session Minutes (Orangeville) (Orangeville City, 2026-03-12) primary government “met with Valar Atomics to go through there safety protocols”
- Castle Dale City Council Meeting Minutes, March 12, 2026 (approved; scanned, read as page images) (Castle Dale City, 2026-03-12) primary government “the site is located on Coal Haul Road west of Orangeville”
What local records show about Valar's water: 11 December 2025, Orangeville approved a future 8-inch water line for Valar's new building, Valar saying it 'acquired the necessary water shares', on condition that fees are paid and the correct shares turned in (minutes). 19 February 2026, the utility district approved a $20,000 connection contingent on all shares being submitted to Orangeville (loc-015). 9 July 2026, Orangeville minutes: the 1,000 water shares under discussion are 'still in the discussion phase' and not for the data center; Valar told the county on 21 July the extra shares would support future development on the land it is buying (mine-042). For scale, the mayor told the council in November 2025 that the city itself held 998.4 Class A and 94 Class B shares of Cottonwood Creek irrigation water and was still 89 shares short. On 16 July 2026 the utility district reported 'critically low reservoir levels' and Orangeville's secondary water at 233 acre-feet for the year. Which company's shares Valar holds or seeks, and how much water 1,000 shares represents, is not stated in any record read. Utah Division of Water Rights records, where a change of use would be filed and advertised, could not be searched: its search pages sit under a path its robots.txt closes to all automated readers (sources_not_read).
- December 11, 2025 City Council Minutes (Orangeville) (Orangeville City, 2025-12-11) primary government “they have acquired the necessary water shares”
- July 9, 2026 City Council Meeting Minutes (Orangeville) (Orangeville City, 2026-07-09) primary government “The 1000 water shares is not part of the data center”
- November 13, 2025 City Council Minutes (Orangeville; notice text) (Orangeville City, 2025-11-13) primary government “right now the city has 998.4 Class A shares and 94 Class B shares”
- CVSSD Regular Meeting Minutes, July 16, 2026 (approved; scanned, read as page images) (Castle Valley Special Service District, 2026-07-16) primary government “critically low reservoir levels raise concerns”
- CVSSD Regular Meeting Minutes, February 19, 2026 (approved) (Castle Valley Special Service District, 2026-02-19) primary government
- Orangeville City Council approves resolutions, discusses EMS and Valar (Kevin Butler) (ETV News, 2026-07-16) news
- Emery County Commissioners Debate Solar, Data Centers and EMS Funding (Kevin Butler) (ETV News, 2026-07-28) news
- Utah Code 73-3-6: Publication of notice of application (amended 2024) (Utah State Legislature, 2024-05-01) primary government “once a week for a period of two successive weeks in a newspaper”
- NOTICE TO WATER USERS (Emery County applications; protests due Oct. 20, 2026) (Utah Division of Water Rights (legal notice published in ETV News), 2026-09-23) primary government “Protests must be filed with the Division of Water Rights”
ETV News reported on 16 July 2026 that at the Orangeville City Council's 9 July meeting Valar's Harry Hansen said the 1,000 water shares Valar is seeking to buy would support possible future expansion and are not meant for a data center, as some rumours suggested. ETV's 28 July 2026 report on the Emery County Commission's 21 July meeting said Valar had recently announced plans to create or obtain as many as 1,000 water shares over the coming years; that, according to Valar, the company already has the water for the proposed NVIDIA data center; and that the extra shares would support possible future developments on the larger property Valar recently purchased from Emery County (mine-018). At that commission meeting Valar representatives offered to speak with residents one-on-one afterwards; a resident asked for a 180-day pause on new data-center applications while zoning standards are written; and Commissioner Dennis Worwood said no formal building application for a data center had been received and that planning and zoning should set standards first.
- Emery County Commissioners Debate Solar, Data Centers and EMS Funding (ETV News (Kevin Butler and Julie Johansen), 2026-07-28) news
- Orangeville City Council approves resolutions, discusses EMS and Valar (ETV News (Kevin Butler and Julie Johansen), 2026-07-16) news “would support possible future expansion and are not intended for a data center”
At the 1 July 2026 event at the Orangeville site (orig-042), ETV reported that Valar's Max Ukropina and NVIDIA representatives 'discussed a collaboration to explore' nuclear-powered AI factories, including a proposed 30-megawatt facility in Emery County, and that the reactor was raised to 37% power to supply electricity to a server hosting a website. KSL/Deseret (6 July) wrote that the companies are 'exploring the deployment' of a 30 MW data center fully powered by their reactor. Valar's Series B post (4 August) calls it 'a collaboration on a waterless 30 MW AI factory'. No contract, memorandum or NVIDIA release was found: a search of nvidia.com returned nothing on Valar, and no filing names a Valar-NVIDIA agreement. In July Valar told the state economic board of 'a waterless data center in Orangeville' (gov-033); in June its public-affairs representative told Orangeville the reactor's energy has no set purchaser (loc-016). Scale: 30 MW is 300 times Ward 250's 100 kW heat rating, and more than that in electricity, since only part of the heat becomes electricity. No reactor Valar has built or had authorized could supply it; it would take a fleet or much larger reactors, which for sold power would need NRC licensing (csite-010, safe-030). If ETV's 37% is of the 100 kW rating, the demonstration ran at roughly 37 kW of heat, and ETV says the electricity came from a thermoelectric generator, which turns only part of the heat into electricity; KSL/Deseret's line that the reactor 'is now generating 100 kilowatts of electricity' (orig-042) fits neither figure.
- Emery County takes center stage as Valar and Nvidia power historic breakthrough (ETV News (Kevin Butler), 2026-07-01) news “discussed a collaboration to explore nuclear-powered AI factories”
- New partnership touts nuclear-powered AI with minimal water use (KSL.com (Eva Terry, Deseret News), 2026-07-06) news “exploring the deployment of a 30 megawatt data center”
- Announcing our $1B Series B Led By Sequoia (Valar Atomics, 2026-08-04) primary company “a collaboration on a waterless 30 MW AI factory”
No power purchase agreement, utility contract or named customer for Valar was found as of 29 September 2026. What the record shows instead: in June 2026 Valar's public-affairs representative told Orangeville the reactor's energy has no set destination or purchaser (loc-016); in July Valar told the state economic board its fastest path is selling to 'behind-the-meter customers willing to pay a premium', skipping grid interconnection (gov-033); in August it told a local business chamber it might build reactors for heavy industrial users, naming a local manufacturer 'strictly as an example' (ETV, 24 August); NVIDIA's role is an announced study (plan-010); and on 17 September, just before the Carbon lease vote, Valar's Harry Hansen told the Trust Lands board that Valar was at the point where site control 'becomes the next conversation when it comes to off-takers', after which it could talk about bringing in buyers for the power (auto-generated meeting transcript). Abroad, Bilyonaryo reported on 2 July 2026 that Meralco, the Philippines' largest electricity distributor, would hold talks with Valar 'in the coming days', according to its chief operating officer, who added that Meralco is open to other small-reactor technologies and that any investment must rest on proven designs. No agreement from those talks was found. No U.S. utility (Rocky Mountain Power/PacifiCorp or others) was found naming Valar in a search of the web; the Utah Public Service Commission's docket site answered with a bot check and could not be searched. Selling Ward 250's power is outside DOE's research-only basis for authorizing it (safe-030).
- MVP opens talks with US firm Valar Atomics on next-gen nuclear reactor (Bilyonaryo (staff), 2026-07-02) news “will hold talks with Valar representatives in the coming days”
- Emery County Business Chamber gets an up-close look at Valar Atomics progress (ETV News (Stephanie Olsen), 2026-08-24) news “strictly as an example”
- Orangeville City Council Regular Meeting Minutes, June 11, 2026 (Orangeville City, via Utah Public Notice Website, 2026-06-11) primary government “the energy does not currently have a set destination or purchaser”
- 09.17.2026 TLA Board of Trustees Meeting Audio (auto-generated transcript) (Utah Trust Lands Administration, via Utah Public Notice Website, 2026-09-17) primary government “Valor's at the point where site control becomes the next conversation”
ETV News (3 July 2026) reported the Carbon County Commission meeting of Wednesday 1 July 2026 (ETV's text gives 'June 2' and 'June 1', but its publication date, the fire restrictions ahead of the Fourth of July and the NVIDIA announcement place it on 1 July; the commission's 1 July minutes record the same celebration, csite-026). As ETV reported it, Commissioner Jared Haddock described Ward 250 as having recently become 'the first government-approved commercial reactor' to achieve a self-sustaining reaction outside a federal lab, and Commissioner Tony Martines said that because Valar's reactor is gas-cooled and NVIDIA's chips are air-cooled, the planned data center won't need water. Set beside the record: Valar's own February 2026 release says Ward 250 is a research reactor and 'not a commercial power plant' (loc-003); DOE's pilot is for research and 'not' to demonstrate commercial suitability (gov-007); DOE's 'first DOE authorized reactor built outside of a national laboratory' holds (orig-010). On water, Valar's own account to Emery County was that the data center would use a closed-loop cooling system 'designed for low water consumption' and that it already had the water it needs, while seeking up to 1,000 more shares for other projects (ETV, 28 July; mine-042). The 'first outside a federal lab' part holds; 'commercial' and 'won't need water' go beyond what Valar and DOE say.
- Carbon County Commissioners urge safety ahead of July 4th, reflect on freedom and democracy (Stephanie Olsen) (ETV News, 2026-07-03) news “the first government-approved commercial reactor”
- Valar Atomics welcomes community for reactor facility open house (Valar Atomics press release) (ETV News, 2026-02-24) primary company “it is not a commercial power plant”
- Emery County Commissioners Debate Solar, Data Centers and EMS Funding (Kevin Butler) (ETV News, 2026-07-28) news
Deseret News (Eva Terry, July 1, 2026) reported an event at Valar's Orangeville site with Taylor, an NVIDIA energy-policy director, Utah energy office director Emy Lesofski and State Sen. David Hinkins, where the companies said they are exploring a 30 megawatt data center fully powered by Valar's reactors. The article says Ward 250 was 'now generating 100 kilowatts of electricity'; that wording cannot match the 100 kW thermal limit in Valar's safety agreement (orig-034): a reactor limited to 100 kW of heat cannot deliver 100 kW of electricity, because turning heat into electricity always loses part of it. The figure is most likely the thermal rating reported as electric. The article quoted no independent expert or critic.
- New partnership touts nuclear-powered AI with minimal water use (Deseret News, 2026-07-01) news “it is now generating 100 kilowatts of electricity”
Deseret News reports that U.S. Rep. Celeste Maloy (Utah) joined Valar's team in the control room in the final stretch to criticality on 18 June 2026. At the 1 July 2026 'Watts Next?' event in Orangeville, state Sen. David Hinkins, who spoke of his own history with Orangeville and Emery County, thanked the Legislature and the state Community Impact Board for supporting the project so that its cost did not fall on local taxpayers (ETV News); the Deseret News also placed him and OED director Emy Lesofski at the event (orig-042). Utah legislative interim committees heard an item on Valar's nuclear test reactor in June 2025 and a Valar-NVIDIA example in August 2026 (csite-031). None of these public appearances concerned the Carbon County site, and no legislator's statement on the Carbon lease was found as of 2026-09-29. What the Community Impact Board funded, and for whom, was not read in this pass (open question).
- Valar Atomics' nuclear reactor reaches criticality in Utah (Eva Terry) (Deseret News, 2026-06-18) news “In the final stretch toward criticality, Utah Rep. Celeste Maloy joined the team.”
- Emery County takes center stage as Valar and Nvidia power historic breakthrough (ETV News, 2026-07-01) news “prevented the cost from being placed on local taxpayers”
The Trust Lands packets include a letter on Carbon County Board of Commissioners letterhead dated 29 June 2026, addressed to the 'SITLA Board of Trustees' and signed by Commissioners Tony Martines, Jared Haddock and Larry Jensen, supporting Valar's desire to locate 'north of Wellington on SITLA lands' and saying the county had worked with Valar for over a year; it does not mention nuclear power or a reactor. The commission's agendas and minutes posted on the Utah Public Notice Website for its meetings of 6 May through 16 September 2026 (read by OCR; most are scanned images; the 5 August meeting was cancelled; 16 September minutes not yet posted) contain no item approving that letter and no item on the Wellington site. Valar appears in commissioners' remarks on 1 July 2026 (celebrating the Emery reactor and a data-center partnership), in a 19 August 2026 'Valor Atomics presentation' about the Orangeville operation and planned public events (the minutes add that commissioners highlighted the tax benefits 'the plant will bring', without saying where), and in a 2 September 2026 announcement of an Orangeville open house and a planned Carbon County town hall. By contrast, Emery County put its support letter for Valar on a public agenda (17 February 2026, orig-046).
- 09.17.2026 TLA Board Packet (Notification Item 10A: SULA 2095-OBA memorandum, Carbon County letter, lease map) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-09-17) primary government “Carbon County has been working with Valor Atomics for over one year”
- Carbon County Board of Commissioners: notices (May 6 to Sept 16, 2026 agendas and minutes) (Utah Public Notice Website) primary government
- Aug 19, 2026 Commission Meeting Minutes (Carbon County Board of Commissioners; scanned, read by OCR) (Carbon County (Utah Public Notice Website), 2026-08-19) primary government “Valor Atomics presentation”
DOE's June 18, 2026 release says Ward 250 completed a zero-power fueled criticality demonstration at the Utah San Rafael Energy Lab in Emery County, the first DOE-authorized reactor built outside a national laboratory. DOE calls it the second of several reactors expected to go critical by the July 4 deadline in the May 2025 executive order; Antares Nuclear's Mark-0 at Idaho National Laboratory was first earlier that month. Energy Secretary Chris Wright and Isaiah Taylor are quoted; Taylor says the site was empty nine months earlier. DOE describes criticality as a sustained chain reaction that must precede power generation.
- Department of Energy Celebrates Second Advanced Reactor Achieving Criticality (U.S. Department of Energy, 2026-06-18) primary government “Nine months ago, this was an empty site.”
- Valar’s Ward 250 reaches criticality in Utah (American Nuclear Society (Nuclear Newswire), 2026-06-22) news
Orangeville City Council minutes, 11 June 2026, public comment: Valar's Harry Hansen, who said he has a background with the state energy office, answered council questions. Asked how many local workers were hired, he said he would get an accurate number. Asked whether Valar's second building is another reactor, he said it is not: Valar will manufacture its own fuel there, the fuel is 'extremely safe', and 'Once completed they will be the largest manufacturer of this fuel in the United States'. Asked whether the energy would go to data centers, he said data centers 'could be purchasers' but the energy has no set destination or purchaser yet. Set beside the record: the fuel building matches the lab's January 2026 release and Valar's QA plan for a 'Valarin' TRISO fuel facility (loc-003, orig-038); no DOE safety authorization for the fuel line has been made public (safe-031); the 'largest' claim is about the future and cannot be tested now; selling Ward 250's energy would fall outside DOE's research-only basis for authorizing it (safe-030).
- June 11, 2026 City Council Minutes (Orangeville) (Orangeville City, 2026-06-11) primary government “Once completed they will be the largest manufacturer of this fuel”
State records show the San Rafael lab hosting or courting several nuclear developers besides Valar: NuCube (MOU with OED, 6 May 2025 per OED's slides; named with Valar to legislators in June 2025, gov-019), which POWER reports was instead selected with Idaho State University in April 2026 for DOE's Launch Pad USA, to site its test reactor on ISU's Pocatello campus; Natura Resources, which holds an NRC construction permit for a molten-salt reactor in Texas and whose project at the lab (medical isotopes, a planned test reactor) the Energy Research Board approved the same day as Valar's (13 Aug 2025, gov-013), and which OED told legislators is leasing 'the majority of the space' at the lab (Oct 2025); and Nuclea Energy, a Canadian company, whose MOU to explore siting a 3.5 MW electric test reactor the board approved on 11 February 2026 and OED signed on 2 June 2026, with OED offering to 'support licensing conversations' with DOE and the NRC and to help explore deployment 'beyond test reactors'. Valar itself proposed a 10 MW gas-fired heater for power-cycle tests (gov-014), is buying the 112-acre parcel next door for fuel fabrication and manufacturing (gov-022), and plans a TRISO fuel line (safe-031). The lab told its board in February 2026 it was adding perimeter fencing and ID checks 'to meet DOE standards'. No public safety analysis or environmental review for these other projects was found in the records read, as of 2026-09-29.
- Memorandum of Understanding between OED and Nuclea Energy USA Inc. (OED26142), signed June 2, 2026 (Utah Office of Energy Development, 2026-06-02) primary government “OED is willing to support licensing conversations with both the Department of Energy”
- Utah Energy Research Board Meeting Minutes, February 11, 2026 (Utah Energy Research Board, 2026-05-13) primary government “to explore siting a 3.5 MW electric test reactor at the lab”
- Board Meeting Minutes, Utah Energy Research Board, August 13th, 2025 (Utah Energy Research Board, 2025-11-13) primary government
- Office of Energy Development Update, PUET Interim Committee, October 15, 2025 (Utah Office of Energy Development, 2025-10-15) primary government
- From Pilot to Launch: DOE Names First Four Nuclear Energy Launch Pad Developers (Sonal C. Patel) (POWER, 2026-04-28) news
Nuclear siting in Emery County is not only Valar. Near Green River, Blue Castle Holdings leased water rights totalling 53,600 acre-feet from the Kane County (29,600) and San Juan County (24,000) water conservancy districts for a proposed nuclear power plant; the Utah Court of Appeals affirmed approval of the change applications in July 2016 against a challenge by HEAL Utah and others, noting the project still needed an environmental review and an NRC early site permit application (2016 UT App 153). On 27 May 2026 Fulcrum Point Holdings (a Hi Tech Solutions affiliate) announced a joint venture with Blue Castle (KSL; Holtec's release is dated 28 May and Utah Business carried the Fulcrum release on 29 May) to take the project through federal licensing with Holtec SMR-300 reactors, which can use air cooling; Emery Commissioner Jordan Leonard and the governor's energy adviser are quoted in support. Neither release gives an NRC filing date; the Fulcrum release's company description puts the multi-unit Blue Castle project at up to 2,200 megawatts, while KSL noted the announcement did not specify the Green River capacity. KSL (27-28 May) reported HEAL Utah's concerns about water use, the Colorado River and waste. At the 30 June 2026 Carbon/Emery economic development committee, a Hi Tech Solutions director said the site had been studied, land and access secured, and the project was in the application process (ETV). The Emery Commission voted in September 2025 to support Green River as a site for a state nuclear project (gov-021). Separately, Valar filed a 10,270-acre 'Green River Gigasite' reactor and data-center application with BLM in February 2026, which it later told a reporter it had dropped while BLM still lists it pending (mine-006, mine-008). No record read connects the Blue Castle project to Valar. The NRC's site refused our reader, so no NRC filing for either could be checked.
- HEAL Utah v. Kane County Water Conservancy District, 2016 UT App 153 (No. 20140429-CA) (Utah Court of Appeals, 2016-07-21) primary government
- Holtec International's SMR-300 Chosen to Power the Green River Advanced Nuclear Project in Utah (Holtec International, 2026-05-28) primary company
- Fulcrum Point Holdings, a Hi Tech Solutions affiliate, announce joint venture with Blue Castle to advance nuclear project in Green River, Utah (press release) (Fulcrum Point Holdings (via Utah Business), 2026-05-29) primary company
- Green River nuclear energy plans revived, add to Utah's potential nuclear portfolio (Tim Vandenack) (KSL.com, 2026-05-27) news
- Carbon/Emery economic development committee discusses nuclear energy, business grants, and coal exports (Kevin Butler) (ETV News, 2026-07-06) news
ETV News (28 May 2026) reported that at the 26 May Carbon/Emery economic development group, a USU Eastern deputy vice president said the Price campus is hiring two or three faculty to launch an engineering curriculum, starting with fundamentals in fall 2026, aiming to enroll students by fall 2027. At the 30 June meeting, the new USU Eastern engineering program was noted as favorable for a nuclear plant and its employees (ETV, 6 July). A USU Eastern release printed by ETV (26 March 2026) says Valar spoke at the Eastern Leaders Academy's economic development day. A USU Eastern professor's housing study counted Valar's workforce (loc-010), and USU Eastern hosted an Economic Development Summit in October 2025 (ETV, 6 Oct 2025). No USU Eastern training agreement, nuclear technician program or funding tie with Valar was found in the records read; Valar's Orangeville job posts ask for years of experience and several say 'willing to relocate to Orangeville' (job board, 29 Sept; loc-019), and a Valar radiation-protection staffer told the Trust Lands board he would hire and train local radiation technicians (ppl-009).
- USU Eastern Engineering, Ridge Road Growth, PacifiCorp IRP Presented to Carbon/Emery EDC (Kevin Butler) (ETV News, 2026-05-28) news
- Carbon/Emery economic development committee discusses nuclear energy, business grants, and coal exports (Kevin Butler) (ETV News, 2026-07-06) news
- Economic growth & development in focus at Eastern Leaders Academy (USU Eastern press release) (ETV News, 2026-03-26) primary government
- The importance of the Economic Development Committee stressed by many (ETV News, 2025-10-06) news “the Economic Development Summit at USU Eastern in October”
- Valar Atomics job board (Greenhouse public board API; Orangeville postings) (Valar Atomics) primary company “Willing to relocate to Orangeville, UT area for operations.”
Emery County Commission minutes, 19 May 2026, item 17: the commission passed (2-0) 'a resolution removing parcel 04-0019-0030 from the UIPA Castle Country Industrial Park Project Area', a commissioner saying annexation into Orangeville 'makes it a little cleaner with taxes'. Two days later, on 21 May 2026, the Utah Inland Port Authority board adopted Castle Country plan Amendment #3; the final plan posted with that meeting still lists '04-0019-0030' ('San Rafael Energy Research Center') among the project area's parcels (gov-018). UIPA staff told the UIPA board on 4 August 2026 that Valar's operations 'will be expanding into the Castle Country project area', and UIPA's 10 September 2026 news post says Valar's 100-plus acres are 'located within the Castle Country Project Area'. Amendment #3 itself was one of a batch of 'recruitment incentive clarifications and minor adjustments' across several project areas and changed no acreage (15,370.25 acres before and after), so the county's request is not reflected in it. No UIPA resolution removing the parcel was found on the 2026 UIPA board agendas read (March to October), and UIPA's 2026 trigger resolution for Castle Country covers only other parcels (gov-018). Which record is current, and so whether future property tax on Valar's land flows mostly to UIPA or to local taxing entities, cannot be settled from the public record as of 2026-09-29. On 7 July 2026 commissioners also discussed asking UIPA for inland-port funds for speed-limit signs on the road used by workers at Valar and a nearby mine.
- Emery County Commission Meeting Minutes, May 19, 2026 (Emery County Commission (Utah Public Notice Website), 2026-05-19) primary government “removing parcel 04-0019-0030 from the UIPA Castle Country Industrial Park Project Area”
- Castle Country Project Area Plan & Budget Amendment #3 (FINAL), adopted May 21, 2026 (Utah Inland Port Authority, 2026-05-21) primary government “San Rafael Energy Research Center: 04-0019-0030”
- Castle Country Project Area Builds Momentum Across Energy, Critical Minerals and Logistics (Utah Inland Port Authority, 2026-09-10) primary government “The property is located within the Castle Country Project Area”
- Emery County Commission Meeting Minutes, July 7, 2026 (Emery County Commission (Utah Public Notice Website), 2026-07-07) primary government
- Utah Inland Port Authority (UIPA) Board Meeting, May 21, 2026 (agenda) (Utah Public Notice Website, 2026-05) primary government “Project Area Recruitment Incentive Clarifications and Minor Adjustments”
The Carbon County Commission's 20 May 2026 agenda listed, for possible approval, a partnership with ALTIGEN ('Jurassic Spark Project') on a natural gas pipeline right-of-way across BLM land. The minutes (scanned; read by OCR) say Altigen intends to build natural gas power plants on private property east of Wellington; that BLM offered Carbon County the option to hold the right-of-way for a pipeline across the North Coal Creek area; that Altigen will bear all environmental work, costs, maintenance and erosion control, and the county is not paying; and that the commission voted to enter 'the beginning stages' of the right-of-way. No BLM right-of-way case naming Altigen or Carbon County created since June 2025 appears in BLM's public layer as of 29 September 2026. No record read links this project to Valar.
- May 20, 2026 Commission Meeting Minutes (Carbon County Board of Commissioners; scanned, read by OCR) (Carbon County (Utah Public Notice Website), 2026-05-20) primary government “Altigen intends to build natural gas power plants on private property east of Wellington”
- 5.20.2026 Agenda (Carbon County Board of Commissioners) (Carbon County (Utah Public Notice Website), 2026-05-20) primary government
- BLM Natl MLRS Rights of Way (ROW) (feature layer and query results) (Bureau of Land Management (MLRS)) primary filing
From the Emery County Commission's minutes. 20 Jan 2026: the commission began 'the disposition process' for parcel 04-0019-0030 ('the property next to the Research Center') 'solely for the purpose of economic development'. 17 Feb: a letter of support for Valar passed; the MOU for Valar's site-suitability testing on the parcel was 'Tabled' (the agenda listing is in orig-046). 17 March: the county's property ordinance required 30 days' notice to neighbors, posting three weeks before sale, and 'sealed bids'; the commission added a section letting it sell under state statute 17-78-103 (notice, public comment and fair value by two appraisals, no bidding) when a parcel is not posted within 30 days; the county attorney said he had not reviewed the new wording and Commissioner Worwood voted no for that reason; the same meeting then approved selling the parcel to Valar under 17-78-103, subject to a hearing and two appraisals, and let Valar use it as a staging area if the county were released from liability. 7 April hearing: Valar said it wants the land for 'Fuel fabrication and manufacturing' and possible temporary employee housing; the state lab director said the state also wanted to buy it, for 'contiguous ownership to maintain safety', and asked whether a bid process could be requested; Commissioner Worwood answered that the county followed state requirements and called the sale 'an intermediate step' while Valar looks for 'a larger piece of property with water'; asked about incentives, the answer recorded was 'None'. 19 May: the commission (2-0) approved the purchase and sale agreement at $394,500, the average of two appraisals, sent annexation notices for the parcel and the lab parcel into Orangeville, and passed a resolution removing the parcel from the Inland Port project area (gov-023). 7 July: a 30-day due-diligence extension, already signed by one commissioner, was ratified; he said the land 'has been sold' to Valar. Other items in these minutes: on 17 March a local special service district asked that Valar annex the parcel into Orangeville, and the sheriff reported a recent meeting with Valar on safety. No recorded deed was read (open question).
- Emery County Commission Meeting Minutes, January 20, 2026 (Emery County Commission (Utah Public Notice Website), 2026-01-20) primary government “solely for the purpose of Economic Development”
- Emery County Commission Meeting Minutes, February 17, 2026 (Emery County Commission (Utah Public Notice Website), 2026-02-17) primary government
- Emery County Commission Meeting Minutes, March 17, 2026 (Emery County Commission (Utah Public Notice Website), 2026-03-17) primary government “as of this meeting has not reviewed the section wording”
- Emery County Commission Meeting Minutes, April 7, 2026 (public hearing on sale of parcel 04-0019-0030) (Emery County Commission (Utah Public Notice Website), 2026-04-07) primary government “the State is interested in contiguous ownership to maintain safety”
- Emery County Commission Meeting Minutes, May 19, 2026 (Emery County Commission (Utah Public Notice Website), 2026-05-19) primary government “The asking price would be $394,500.00.”
- Emery County Commission Meeting Minutes, July 7, 2026 (Emery County Commission (Utah Public Notice Website), 2026-07-07) primary government “has been sold by the county to Valar”
- Utah Code 17-78-103, Acquisition, management, and disposal of property (effective 5/6/2026) (Utah State Legislature, 2026-05-06) primary government
At the 19 May 2026 Emery County Commission meeting, OED Deputy Director Tracy Rees presented the Office of Energy Development's 'statewide nuclear education and community outreach campaign'. Per the minutes, commissioners asked about safety and new technology and about funding; she said the subject-matter experts 'are not paid because they believe in the technology', that OED first meets county commissioners, city councils and mayors to hear local concerns and uses that to shape each community event, and that the state wants people to understand nuclear 'so communities can engage in a meaningful way'. The regional development agency's board heard 'Nuclear Community Campaigns' updates in May and July 2026 (csite-031), and the public workshops later cited as outreach were general nuclear classes that did not mention the Wellington site (mine-047). OED is also the landlord and promoter of Valar's project (ppl-018, gov-011). No campaign budget, contractor or list of experts was found in the records read.
- Emery County Commission Meeting Minutes, May 19, 2026 (Emery County Commission (Utah Public Notice Website), 2026-05-19) primary government “the SME’s are not paid because they believe in the technology”
Emery County's commissioners in 2026 are Dennis Worwood (chair), Jordan Leonard and Keven Jensen (ETV News). On 17 February 2026 they commended Valar 'for their transparency' when the reactor arrived and approved a support letter (orig-046); Jensen said 'your visions and values line-up with ours'. At an April 2026 public hearing on selling county land next to the lab to Valar (ETV, 9 Apr 2026), state lab director Jaron Wallace, answering a concern about truck traffic, spoke of the economic benefits and noted the land was zoned as an industrial park for such expansion; when residents asked about a buffer zone, the reply, as ETV put it, was that 'with these small reactors the fence line is all the buffer zone needed' (ETV does not say who replied), and Worwood and Leonard, who had toured the nuclear project at Kemmerer, Wyoming, 'concurred with Valar'. Jensen noted permits would still come from the county; a letter of commitment to sell was approved subject to two appraisals, and a 10-acre staging-area agreement with a liability waiver. Set beside the record: Valar's own safety agreement puts the accident-analysis boundary 400 m from the reactor, farther than the 20.6-acre lab's fence reaches (safe-014), and estimates up to 5 rem for a worker 100 m away in its worst-case accident (safe-013). The buffer-zone answer, as reported, is not what Valar's own analysis assumes.
- Emery Commission public hearing receives comments on the sale of property to Valar Atomics (ETV News, 2026-04-09) news “with these small reactors the fence line is all the buffer zone needed”
- Valar Atomics announce the arrival of nuclear reactor to Emery County (ETV News, 2026-02-19) news “your visions and values line-up with ours in this area.”
The NSDA's accident doses are calculated for a site boundary 400 m from the reactor, described as 'the nearest point of public access', with the nearest residence at about 800 m and the nearest group at 1,200 m. DOE's categorical exclusion describes USREL as 'a 20.6-acre site', with Ward 250's reactor complex and fuel laboratory inside a security-fenced area of about 2 acres; ETV News (October 2025) reported Valar's allotment at the lab as 11 acres. A circle of 400 m radius covers about 124 acres (pi x 400 m squared = 502,655 square metres), so no point on a 20.6-acre site can be 400 m from every edge of it. The 400 m boundary must therefore run over land outside the lab, and no record read says who controls public access there. The NSDA's own dispersion factors show why it matters: the one it uses at 100 m is 16 times the one at 400 m (4.0e-3 versus 2.5e-4 s/m3), and its worst-case dose at 100 m is under 5 rem. Our check: the 100 m factor meets DOE's prescribed default, but the 400 m factor is 3.1 to 12.3 times lower than standard rural methods give for the paper's stated weather, so its 400 m bounds may be low by that factor (still far below 25 rem). In August 2026 Valar said it was buying about 110 acres north of the lab from Emery County, and later state records describe the land as purchased (mine-018); that could put more nearby land under Valar's control, but it post-dates the October 2025 NSDA and no record read says whether it covers the 400 m circle. No public copy of the approved DSA's site description, which would define the boundary, was found. DOE's categorical exclusion says 'Radiation monitoring and controlled access are maintained during operations', without saying where. No DOE document read sets 400 m as a required exclusion boundary for Ward 250; it is the distance at which Valar's draft paper calculates public doses.
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (status: Draft; issued for Public Release) (Valar Atomics, 2025-10) primary company “400m to site boundary, 800m to nearest residence”
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (categorical exclusion B5.26) (U.S. Department of Energy, Office of Nuclear Energy (Idaho), 2026-04-22) primary government “a 20.6-acre site in a rural area of central Utah”
- What's actually happening at the Utah San Rafael Energy Lab? (ETV News, 2025-10-10) news “Their buildings are currently under construction in their 11-acre allotment.”
DOE's categorical exclusion for Ward 250 states that no major emission sources exist within 10 miles of the site. The Utah Geospatial Resource Center's power-plant layer places the Hunter coal plant (listed at about 9.6 million tonnes of CO2 a year; the layer's figures carry a 2008 adjustment date) about 9.5 km (6 miles) and the Huntington coal plant (about 5.9 million tonnes) about 15 km (9 miles) from a point beside the lab (safe-021); given the reference point's uncertainty of about 2 km, Hunter is clearly inside 10 miles and Huntington is near that line. ANS's Nuclear Newswire describes the site as 'flanked by gigawatt-scale coal stations and active coal mines'. The NSDA separately screens out industrial fire hazards on a 10-mile separation. The CX sentence appears in its air-quality section, where the point is background air quality; it does not change the radiological analysis, but as written it is contradicted by the state's data.
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (categorical exclusion B5.26) (U.S. Department of Energy, Office of Nuclear Energy (Idaho), 2026-04-22) primary government “No major emission sources exist within 10 miles.”
- PowerPlants_CO2 (Utah Geospatial Resource Center layer of power plants, distance query) (Utah Geospatial Resource Center) primary government
- Valar's Ward 250 reaches criticality in Utah (American Nuclear Society, Nuclear Newswire, 2026-06-22) news “flanked by gigawatt-scale coal stations and active coal mines”
Right-of-entry permit application 7675 (Trust Lands permit map, 18 February 2026) covers nearly all of Section 16, T14S R11E, SLB&M, north of Wellington: 634.32 acres (the map leaves out a small southeast corner). Trust Lands' map for Special Use Lease Agreement No. 2095, produced 9 April 2026 and posted by the RDCC on 20 April 2026 as a 'Lease Agreement with possible option to purchase' (project 87203), covers the north half and southwest quarter of the same section: 480 acres. The Trust Lands board memorandum says the Utah National Guard's lease, SULA 1321, occupies the section's southeast quarter (160 acres). The board approved SULA 2095 with Valar Atomics on 17 September 2026, per the meeting transcript (mine-011). No record read names the applicant for 7675 or shows the permit was issued.
- Right of Entry No. 7675 - Geotechnical Survey (permit map) (Utah Trust Lands Administration (via the RDCC project register), 2026-02-18) primary government “Right of Entry No. 7675 - 634.32 Acres”
- Special Use Lease Agreement No. 2095 (lease map) (Utah Trust Lands Administration (via the RDCC project register), 2026-04-09) primary government “N2, SW4 - Section 16 - 480 Acres”
- RDCC project register: projects 87096-87099 (Right-of-Entry Permits #7672, #7674, #7675, #7676) and 87203 (SULA 2095) (Utah Resource Development Coordinating Committee (Public Lands Policy Coordinating Office), 2026-02-19) primary government “to evaluate the feasibility of a potential industrial and manufacturing development”
- 09.17.2026 TLA Board Packet (Notification Item 10A: SULA 2095 OBA memorandum) (Utah Trust Lands Administration, 2026-09-14) primary government “The UNG lease (SULA 1321) occupies 160 acres of the 640-acre section”
Emery County's minutes of the 7 April 2026 public hearing on selling parcel 04-0019-0030 record Valar's commercial development representative, Cory Gardner (spelled 'Gardiner' there), saying the company is part of the community and will 'promise to be open with all plans', and Commissioner Keven Jensen saying Valar 'has been transparent'. Set beside the record: at that hearing Valar described its plans for the Emery parcel (fuel fabrication, manufacturing, possible temporary employee housing), and Commissioner Dennis Worwood said the sale was 'an intermediate step' while Valar looks for 'a larger piece of property with water' (gov-022), but no Carbon County site was named; the state's lease map for the Wellington section is dated two days later, 9 April 2026 (mine-048); the state's 20 April public notice named neither Valar nor nuclear (csite-032); and the first public agenda naming Valar with the Carbon site came on 10 August 2026 (csite-018). On the other side of the ledger, Valar did open its Emery facility to the public: on 17 February 2026 it told the commission it would hold open houses, the first on 24 February 2026. The gap is between a general promise of openness and a public record that did not show the Carbon site for four months; what Valar knew about the Wellington lease on 7 April is not in the records read.
- Emery County Commission Meeting Minutes, April 7, 2026 (public hearing on sale of parcel 04-0019-0030) (Emery County Commission (Utah Public Notice Website), 2026-04-07) primary government “we are part of this community and promise to be open with all plans”
- Emery County Commission Meeting Minutes, February 17, 2026 (Emery County Commission (Utah Public Notice Website), 2026-02-17) primary government “Valar will hold a number of open house events for the public”
At the same 7 April 2026 Emery County hearing, a resident asked about safety buffer zones; Valar's representative answered that every design has to be reviewed and approved by the Department of Energy. Asked about 'turmoil' between the state and the NRC, Valar's Max Ukropina said past laws had been burdensome and that President Trump had loosened some regulations. Set beside the record: for Ward 250 the answer holds, since DOE alone authorizes it (safe-001, gov-005). For what Valar has described next it is incomplete: three months later Valar told the state's incentive board it plans 'additional commercial units in the area' and behind-the-meter power sales (gov-033); the executive order behind the DOE route covers reactors that do not produce commercial electric power (gov-005); and DOE's own releases, and Hogan Lovells' summary of the law, place later commercial licensing with the NRC (gov-007, gov-032, csite-010). DOE's Launch Pad USA pathway can authorize non-federal sites, but no record read shows Valar using it for another site (gov-010).
- Emery County Commission Meeting Minutes, April 7, 2026 (public hearing on sale of parcel 04-0019-0030) (Emery County Commission (Utah Public Notice Website), 2026-04-07) primary government “every design has to be reviewed and approved by the Department of Energy”
- GOED Board Meeting Minutes, July 9, 2026 (Governor's Office of Economic Opportunity (Utah Public Notice Website), 2026-09-10) primary government “they plan to install additional commercial units in the area”
- Executive Order 14301 (90 FR 22591) (Federal Register (GPO govinfo), 2025-05-29) primary government “that do not produce commercial electric power”
ETV's report (9 April 2026) of Emery County's 7 April hearing on selling the 112-acre parcel beside the lab says Valar's representatives explained they needed more land to expand their factory and ready the reactor, and, asked what they planned to build, replied that plans were not firm yet but they were considering expansion and 'maybe even housing'. Later in the same meeting the commission approved a real-estate use agreement letting Valar use 10 acres south of the lab as a laydown and staging area during construction, with a waiver of liability. The county's own minutes add that Valar named 'fuel fabrication and manufacturing' for the parcel and that a commissioner called the sale an 'intermediate step' while Valar looked for a larger property with water (gov-022, gov-038); the sale price was $394,500 and closing was not confirmed as of mid-August (loc-014); Orangeville is drafting an advanced-energy zoning district and annexation for the land (loc-013); Valar is seeking up to 1,000 more water shares for future development there (loc-017). The Wellington lease map was drawn two days after this hearing (mine-048).
- Emery Commission public hearing receives comments on the sale of property to Valar Atomics (ETV News, 2026-04-09) news “plans are not firm yet but are considering expansion and maybe even housing”
BLM's public rights-of-way layer (queried 29 September 2026) shows PacifiCorp as applicant on a pending 'Power Transmission Line' case, UTUT106794107 (created 6 April 2026; 14,262 acres of mapped legal area), whose legal description runs from T13S R10E in Carbon County south-east through Emery County to T25S R21E. It includes parts of sections 19, 29, 30, 34 and 35 of T14S R11E, the township that holds Section 16 (approved for leasing to Valar); those sections' centres lie roughly 2 to 4 miles from the centre of Section 16. In the township directly north (T13S R11E) and in T13S R10E, Urban Oil & Gas Group LLC has eight road, pipeline and water-facility rights-of-way whose records were created in August 2026 (seven 'Authorized', one road 'Pending'). The other new Carbon County cases since June 2025 are a PacifiCorp distribution line (T13S R7E), a Price City water facility (T12S R9E) and a Union Pacific communications site (T13S R10E). No record read links any of these to Valar.
- BLM Natl MLRS Rights of Way (ROW) (feature layer and query results) (Bureau of Land Management (MLRS)) primary filing
- BLM National PLSS CadNSDI, PLSS Section layer (Bureau of Land Management) primary government
Emery County's legal notice for the sale of parcel 04-0019-0030, headed 'Proposed Property Transaction of Parcel 04-0019-0030 between Emery County and Valar Atomics', ran in ETV News on 25 March and 1 April 2026 under Utah Code 17-78-103, announcing a public hearing on 7 April 2026 at 3:00 p.m. in Castle Dale and a price set by the average of two independent appraisals. The hearing was held and reported (ETV, 9 April; minutes, gov-022). By contrast, Trust Lands' notice for the Wellington section, posted on its website from 8 July 2026 and printed in ETV News on 15, 22 and 29 July (loc-032), named neither the applicant nor the use (csite-005, mine-012), and the state's April RDCC notice called it an unnamed 'large-scale industrial project' (csite-032). Emery County's hearing concerned a sale of county land, which state law makes subject to notice and a hearing; Trust Lands' arrangement is exempt from its ordinary lease rule (csite-004). The different treatment follows different rules; the result is that Emery residents were told Valar's name before the vote and Carbon residents were not.
- PUBLIC HEARING NOTICE: Proposed Property Transaction of Parcel 04-0019-0030 between Emery County and Valar Atomics (Emery County (legal notice published in ETV News), 2026-03-25) primary government “Proposed Property Transaction of Parcel 04-0019-0030 between Emery County and Valar Atomics”
- Emery Commission public hearing receives comments on the sale of property to Valar Atomics (ETV News, 2026-04-09) news
Castle Valley Special Service District (CVSSD) runs water and sewer for Castle Valley towns including Orangeville. Its approved minutes of 19 February 2026 record Valar's Jess Housekeeper presenting Valar's plans (by video), the board approving a $20,000 outside-district water connection for Valar contingent on all water shares being submitted to Orangeville, and the manager reporting that Valar 'will be required to apply to' the state Division of Water Quality (DWQ) for a sewer discharge permit, which DWQ would administer for four years, and that no sewer connection would be approved until DWQ approved the permit. The approved minutes of 19 March 2026 (whose opening line misdates the meeting to 19 February) record the manager's update: sewer plans 'were not submitted to the State as required', water service work was paused pending DWQ approval, 'Valar tied into the county sewer system without prior authorization', Valar was asking for ordinary sanitary sewer service for restrooms only with no process water, a site visit with the regional DEQ engineer was planned, and water service would not be provided until all sewer permits and approvals were in place; no action was taken. The district's May, July and August 2026 minutes (read; the June minutes, approved on 16 July, are not posted) do not return to the sewer issue, though the May minutes discuss annexing property near Orangeville 'that may be developed by Valor', and its 17 September agenda lists no Valar item. DOE's categorical exclusion puts water use under 1,000 gallons a day for domestic use, with no process-water discharges (safe-021), which matches the restrooms-only request. Whether DWQ issued a permit, and whether the tie-in the minutes report was corrected or penalized, is not in any record read.
- CVSSD Regular Meeting Minutes, February 19, 2026 (approved) (Castle Valley Special Service District, 2026-02-19) primary government “Valor will be required to apply to DWQ for a sewer discharge permit.”
- CVSSD Regular Meeting Minutes, March 19, 2026 (approved) (Castle Valley Special Service District, 2026-03-19) primary government “Valar tied into the county sewer system without prior authorization”
- CVSSD Regular Meeting Minutes, May 21, 2026 (approved; scanned, read as page images) (Castle Valley Special Service District, 2026-05-21) primary government
- CVSSD Regular Meeting Minutes, July 16, 2026 (approved; scanned, read as page images) (Castle Valley Special Service District, 2026-07-16) primary government
- CVSSD Board Meeting Minutes, August 20, 2026 (approved) (Castle Valley Special Service District, 2026-08-20) primary government
- Castle Valley Special Service District Board of Directors (public body 1361): notices June 2025 to September 2026 (Utah Public Notice Website) primary government
- CVSSD Notice of Regular Board Meeting, September 17, 2026 (agenda) (Castle Valley Special Service District, 2026-09-17) primary government
Castle Dale City Council minutes of 12 March 2026 record Valar's director of Utah operations, Jess Housekeeper, saying 'The reactor requires minimal water—about 10 acre-feet for industrial use' and that it mainly uses helium cooling. The minutes give no time period for the 10 acre-feet. If it is a yearly figure, 10 acre-feet is about 3.26 million gallons, or roughly 8,900 gallons a day on average. DOE's categorical exclusion for Ward 250, signed six weeks later (22 April 2026), describes water use only as 'less than 1000 gallons/day for domestic use', says no process water is discharged and that sanitary waste goes through the lab's infrastructure, and does not mention any industrial water use. The utility district's minutes say Valar asked for restroom sewer service only, with no process water (loc-015). The figures may describe different things (the reactor alone versus the whole site with its fuel laboratory, consumption versus a water-right allotment, or a yearly versus a one-time amount); no record read reconciles them. Separately, Valar says it holds the shares for its current needs and seeks up to 1,000 more for future development (loc-017).
- Castle Dale City Council Meeting Minutes, March 12, 2026 (approved; scanned, read as page images) (Castle Dale City, 2026-03-12) primary government “The reactor requires minimal water—about 10 acre-feet for industrial use”
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (categorical exclusion B5.26) (U.S. Department of Energy, Office of Nuclear Energy, 2026-04-22) primary government “Water consumption is less than 1000 gallons/day for domestic use.”
- CVSSD Regular Meeting Minutes, March 19, 2026 (approved) (Castle Valley Special Service District, 2026-03-19) primary government “standard sanitary sewer service only for restrooms, with no process water proposed”
ETV News (24 Feb 2026) reported a USU Eastern professor's presentation to the Emery County Business Chamber's housing committee on growth in Carbon and Emery counties: about 1,100 temporary units (motel rooms and RV spaces), roughly 100 homes for sale in Carbon and 20 in Emery, median price above $400,000; Valar's nuclear test project planning to employ about 40 technicians and contractors who would compete for short-term rentals; and 300-400 miners expected at Fossil Rock looking for long-term housing. The same professor updated the Carbon/Emery economic development committee on his 'Housing Analysis for Carbon and Emery Counties' on 27 January 2026, prompting discussion of population growth from Valar and Fossil Rock (ETV, 30 Jan; that meeting heard of 170 homes for sale in Carbon and 18 in Emery). At Emery's 7 April hearing Valar named possible housing among uses for the land it was buying (ETV; gov-022). The larger job numbers Valar gave the state in July 2026 (275, loc-004) and the Carbon campus plan are not reflected in any housing study read. Orangeville's council adopted a 180-day moratorium on new short-term rental applications on 8 January 2026, a councilman saying 'with the nuclear hiring staff' the housing effect was unknown (minutes), and at a May 2026 public hearing on rental rules a councilman said more housing will be needed to support the mines and Valar (minutes).
- Housing Committee hears about coming population growth and housing crisis (ETV News, 2026-02-24) news “planning to employ about 40 technicians and contractors”
- January 8, 2026 City Council Meeting Minutes (Orangeville) (Orangeville City, 2026-01-08) primary government “with the nuclear hiring staff”
- May 14, 2026 Public Hearing Minutes (Orangeville) (Orangeville City, 2026-05-14) primary government “more housing needed to support the mines, Valor Atomics, etc.”
- Economic Development Committee discuss housing and well permitting (Julie Johansen) (ETV News, 2026-01-30) news “Housing Analysis for Carbon and Emery Counties”
On 19 February 2026 the state's Resource Development Coordinating Committee (RDCC) posted four applications for Trust Lands right-of-entry (site-study) permits as projects 87096 to 87099, numbered 7672, 7674, 7675 and 7676. Comments were due 3 March and the stated start was 6 March. Each notice says that Trust Lands 'has received a Right-of-Entry (ROE) permit application' for cultural-resource surveys, geotechnical investigations and similar studies 'to evaluate the feasibility of a potential industrial and manufacturing development', and that 'No permanent development is proposed under the Right-of-Entry authorization.' Trust Lands' permit maps, dated 18 February 2026, give the areas: 7672, 1,812.94 acres near Green River (T20S R15E and T21S R15-16E, Emery County); 7674, 5,381.59 acres south and west of Price (T14-15S R9-10E, Carbon County); 7675, 634.32 acres, nearly all of Section 16, T14S R11E, north of Wellington (Carbon County; the map leaves out a small southeast corner); 7676, 487.83 acres in Sections 2 and 16, T16S R13E (Emery County). That is 8,316.68 acres in all. The notices record that local governments were contacted on 19 February. The only state comments were Division of Wildlife Resources recommendations of 3 March 2026: three of the areas are crucial year-long pronghorn habitat; white-tailed prairie dogs, burrowing owls and kit foxes could occur; and hawks are known to nest near two of the areas. No applicant is named in the four notices, the four maps or the comment letters, and no record read shows the permits were issued: the register lists all four as 'State Comment Published'.
- RDCC project register: projects 87096-87099 (Right-of-Entry Permits #7672, #7674, #7675, #7676) and 87203 (SULA 2095) (Utah Resource Development Coordinating Committee (Public Lands Policy Coordinating Office), 2026-02-19) primary government “to evaluate the feasibility of a potential industrial and manufacturing development”
- Right of Entry No. 7672 - Geotechnical Survey (permit map, file ROE_7672_SULA_1622_02182026.pdf) (Utah Trust Lands Administration (via the RDCC project register), 2026-02-18) primary government “Right of Entry No. 7672 - 1,812.94 Acres”
- Right of Entry No. 7674 - Geotechnical Survey (permit map) (Utah Trust Lands Administration (via the RDCC project register), 2026-02-18) primary government “Right of Entry No. 7674 - 5,381.59 Acres”
- Right of Entry No. 7675 - Geotechnical Survey (permit map) (Utah Trust Lands Administration (via the RDCC project register), 2026-02-18) primary government “Right of Entry No. 7675 - 634.32 Acres”
- Right of Entry No. 7676 - Geotechnical Survey (permit map) (Utah Trust Lands Administration (via the RDCC project register), 2026-02-18) primary government “Right of Entry No. 7676 - 487.83 Acres”
- Public Lands Policy Coordinating Office letter on Right-of-Entry Permit #7674 (Division of Wildlife Resources comments) (Utah Public Lands Policy Coordinating Office, 2026-03-03) primary government “within crucial year-long pronghorn habitat”
Right-of-entry permit application 7672 (1,812.94 acres; Trust Lands permit map, 18 February 2026) lies within Sections 32 and 36 of T20S R15E, Sections 10 and 11 of T21S R15E and Section 6 of T21S R16E, near Green River in Emery County. The permit map file is named for, and draws beside it, Special Use Lease Agreement No. 1622 (2,441.03 acres); no record read names that lease's holder. Overlaid on BLM's case map for Valar's pending 'Green River Gigasite' right-of-way application (UTUT106784007), Section 32 of T20S R15E lies wholly inside the application's outer boundary and is the only hole in the case map (about 637 acres): state land the application surrounds. The case map also covers about 467 acres of Section 6, T21S R16E (the part that is not state land); the permit application's state land there lies outside it. Sections 36, 10 and 11 lie outside it; they border it, but no part falls inside it. No record read names the applicant for 7672 or shows the permit was issued. BLM still lists Valar's application as pending; Valar told a reporter it has decided not to pursue the site (mine-008).
- Right of Entry No. 7672 - Geotechnical Survey (permit map, file ROE_7672_SULA_1622_02182026.pdf) (Utah Trust Lands Administration (via the RDCC project register), 2026-02-18) primary government “Right of Entry No. 7672 - 1,812.94 Acres”
- BLM Natl MLRS Rights of Way: case UTUT106784007, 'Green River Gigasite Small Modular Reactor/Data Center' (case map) (Bureau of Land Management (MLRS)) primary filing “Green River Gigasite Small Modular Reactor/Data Center”
- BLM PLSS CadNSDI first division (sections) for the listed townships (Bureau of Land Management (Cadastral National Spatial Data Infrastructure)) primary government
- RDCC project register: projects 87096-87099 (Right-of-Entry Permits #7672, #7674, #7675, #7676) and 87203 (SULA 2095) (Utah Resource Development Coordinating Committee (Public Lands Policy Coordinating Office), 2026-02-19) primary government “to evaluate the feasibility of a potential industrial and manufacturing development”
- Trump Is Considering More Data Centers on Public Lands Than Previously Known (The Washington Sun (Mara Hoplamazian and Jade Lozada), 2026-09-18) news “After considering the site, the company has decided to no longer pursue the project”
Minutes of the Emery County Fire Protection Special Service District: 17 November 2025, item 'Getting 3rd Party to Review Plans for Nuclear Power Plant': the district was asked to approve fire plans for the 'Nuclear test plant' at Orangeville; the chair had called the State Fire Marshal's office, which 'didn't want to touch it'; the board tabled it to get information on the fire code and whether there was adequate water flow (GPM) for the building classification. 15 December 2025: the chair said he would sign the fire protection plans as soon as the paperwork arrived (safe-016). 17 February 2026 (the minutes' header reads 'Tuesday, February 17th, 2025', misprinting the year), item 'Valar Atomics': fire chiefs were asked to review building plans; 'State agencies declined to perform plan review and recommended third-party review'; responsibility may fall to the district or a local fire authority because there is no county fire inspector; the review concerns building fire-code compliance, not reactor design. 16 March 2026: 'The issue has been addressed with chiefs and is not currently a concern.' The April, May and June 2026 minutes do not return to it. Separately, Emery County's commission voted Valar's building permit itself on 2 September 2025 because its building department had not issued one (gov-021), and Orangeville's fire chief reported on 12 March 2026 that he had gone through Valar's safety protocols (loc-008). No record read says whether a third-party plan review was done, who did it, or what it found.
- Emery County Fire Protection SSD meeting minutes, November 17, 2025 (Emery County Fire Protection Special Service District, 2025-11-17) primary government “Ben called the State Fire Marshall and they didn’t want to touch it.”
- Emery County Fire Protection SSD meeting minutes, December 15, 2025 (Emery County Fire Protection Special Service District, 2025-12-15) primary government
- Emery County Fire Protection SSD meeting minutes, February 17, 2026 (header misprints the year as 2025) (Emery County Fire Protection Special Service District, 2026-02-17) primary government “State agencies declined to perform plan review and recommended third-party review.”
- Emery County Fire Protection SSD meeting minutes, March 16, 2026 (Emery County Fire Protection Special Service District, 2026-03-16) primary government “The issue has been addressed with chiefs and is not currently a concern.”
- Emery County Fire Protection SSD notices, April to September 2026 (April, May and June minutes read, no Valar item; July has no minutes posted, August cancelled, September audio only) (Utah Public Notice Website) primary government
The Emery County Commission's February 17, 2026 meeting notice lists two Valar items: approving or denying a county letter of support to Valar Atomics, and approving or denying an MOU letting Valar perform site suitability testing on parcel 04-0019-0030. This indicates Valar was already studying a site in Emery County beyond the state lab by early 2026. Valar's Castle Country page says the commission backed the project unanimously. The outcome of the MOU item and the parcel's location are not given in the notice; see local.json.
- Emery County Commission Meeting (notice, February 17, 2026) (Utah Public Notice Website (Emery County Commission), 2026-02-17) primary government “allowing them to perform site suitability testing on parcel 04-0019-0030”
BLM's public rights-of-way layer lists Valar Atomics as 'Applicant' on three pending cases, all filed with the Price Field Office (the office that handles most rights-of-way cases in Carbon and Emery counties in the same layer): (1) UTUT106784007, 'Green River Gigasite Small Modular Reactor/Data Center', a FLPMA land-use case, 'Pending' since 13 February 2026 (last modified 26 May 2026), 10,270.61 acres in T20S-T21S, R14E-R16E, north-west of the town of Green River in Emery County; (2) UTUT106801248, 'Project Beehive Small Modular Reactor/Data Center', 'Pending' (disposition date 13 April 2026, record created 30 April, last modified 15 September 2026), with no land description or map in the public layer; (3) UTUT106833224, filed under BLM's 'Oil and Gas Pipelines' product with the commodity 'DISTRIBUTION LINE', created 23 July 2026, 'Pending', also with no land shown and no case name. None of the three involves mining claims. No Federal Register notice naming Valar for any of them was found (mine-009).
- BLM Natl MLRS Rights of Way (ROW) (feature layer and query results) (Bureau of Land Management (MLRS)) primary filing “Green River Gigasite Small Modular Reactor/Data Center”
Minutes of the Utah Energy Research Board's 11 February 2026 meeting (held at the lab in Orangeville and online; agenda item 'Valar Supercritical CO2 Demonstration'): lab director Jaron Wallace presented a Valar proposal to build a 10 MW thermal natural-gas-powered heater to test supercritical CO2 power generation and other technologies; Valar would fund the whole $20 million project, which 'will eventually become the property of the lab', and asked for completion by June 2026. Members questioned the June timeline and asked for risk management and contract exit clauses; the board voted to enter an agreement for 'Phase 1', the first $400,000 of design, engineering and execution planning, and to re-evaluate before construction (Phase 2). The same meeting heard that Valar was 'on track for a July 4th operational deadline', that the lab was growing from five to eight employees, and that new perimeter fencing and ID checks were being added 'to meet DOE standards'. The board's 13 May 2026 minutes record no Phase 2 vote, and its 12 August 2026 agenda lists no item on the project. This project is not mentioned in any Valar document or state release read, and no air-quality permit for a 10 MW gas heater was found (DAQ's lists could not be searched, carbon_site.json).
- Utah Energy Research Board Meeting Minutes, February 11, 2026 (Utah Energy Research Board (Utah Public Notice Website), 2026-05-13) primary government “Valor Atomics will fund the entire $20 million project”
- Amended Utah Energy Research Board Meeting Wednesday, February 11, 2026 (notice and agenda) (Utah Public Notice Website, 2026-02-03) primary government “DISCUSSION/MOTION: Valar Supercritical CO2 Demonstration - Dr. Jaron Wallace”
- Utah Energy Research Board Meeting Minutes, May 13, 2026 (Utah Energy Research Board (Utah Public Notice Website), 2026-05-13) primary government
- Utah Energy Research Board Amended Agenda, August 12, 2026 (Utah Energy Research Board (Utah Public Notice Website), 2026-08-12) primary government
Ward 250 is not built to supply the grid: its July 2026 electricity demonstration used a thermoelectric generator and ran one server (ETV; plan-010). The next step Valar has shown is a heat-to-electricity program. On 11 February 2026 the Utah Energy Research Board heard a Valar proposal, presented by the lab director, to build a 10 MW (thermal) natural-gas-powered heater at the lab to test supercritical-CO2 power generation; Valar would fund the whole $20 million, the equipment would become lab property, and Valar asked for completion by June 2026. The board approved only a $400,000 'Phase 1' of design and planning, to re-evaluate before construction (gov-014). No Phase 2 approval, air permit or completion was found. Valar's job board (29 September 2026) has eight turbomachinery roles in Torrance for a 'secondary loop Brayton cycle' on helium, supercritical CO2 or air, with 'a purpose-built test facility program' (plan-011); the posts do not say where that facility will be. DOE's environmental review of Ward 250 says 'No combustion processes occur' at the reactor; a gas-fired heater at the same lab would be a separate project with its own review, and none was found.
- Utah Energy Research Board Meeting Minutes, February 11, 2026 (Utah Energy Research Board, via Utah Public Notice Website, 2026-02-11) primary government “Valor requested an aggressive completion date of June 2026.”
- Director Instrumentation, Control, and Electrical - Power Conversion (Torrance, California) (Valar Atomics (via Greenhouse), 2026-06-30) primary company “secondary loop Brayton cycle”
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (U.S. Department of Energy, Office of Nuclear Energy, 2026-04-22) primary government “No combustion processes occur.”
- Emery County takes center stage as Valar and Nvidia power historic breakthrough (ETV News (Kevin Butler), 2026-07-01) news “converted into electricity through a thermoelectric generator”
The state lab and Valar's joint update of 23 January 2026 (run by ETV) says site work for the Ward 250 reactor and the fuel fabrication facility included earthmoving and crushing of about 40,000 cubic yards by TSJ Construction, blasting by 3 Rivers Blasting under contract to TSJ, and more than 4,000 cubic yards of foundation concrete from Nelson's Construction; the lab added cameras, access controls, a planned security checkpoint and a new perimeter fence. The Utah Energy Research Board heard on 11 February 2026 that Valar was 'on track' for its July 4 goal and that the reactor vessel was due at the site shortly; the unfueled reactor arrived by air at Hill AFB on 15 February and then by road (orig-030). DOE's April 2026 environmental review describes construction in the past tense (plan-004). Earlier records name Kiewit (engineering and construction), Goree (design) and Sprung (building) (orig-067); Emery County's commission itself voted the building permit because the county building department had not issued one (gov-021); a utility district recorded an unauthorized sewer tie-in (loc-015); the State Fire Marshal declined the fire review (loc-018). No record read says the fuel building is finished.
- Rapid construction from local contractors at Valar Atomics (USREL press release, Energy Corner) (Utah San Rafael Energy Lab and Valar Atomics, via ETV News, 2026-01-23) primary government “moved and crushed approximately 40,000 cubic yards of material”
- Utah Energy Research Board Meeting Minutes, February 11, 2026 (Utah Energy Research Board, via Utah Public Notice Website, 2026-02-11) primary government “The reactor vessel is scheduled to arrive at the site shortly.”
The Utah Geological Survey's 'Utah mining 2024' (Circular 139, 2025) says Energy Fuels is the only uranium producer in Utah, having restarted its Beaver, La Sal and Pandora mines in early 2024 (29,780 tons of ore worth about $13 million), and that its mill outside Blanding is the only conventional uranium mill in the United States; not all the uranium it processes is from Utah ore. It lists the Velvet-Wood mine near Monticello (plan approved in early June 2025 after a federal fast-track), Anfield's plan to restart the Shootaring Canyon mill near Ticaboo in 2027, IsoEnergy's Tony M project and the Harts Point exploration project. None is in Carbon or Emery County. Utah DEQ licenses the White Mesa mill (license UT1900479) since Utah became an Agreement State for uranium mills in August 2004.
- Utah mining 2024: Metals, industrial minerals, uranium, and coal (Circular 139) (Utah Geological Survey, 2025) primary government “Energy Fuels is currently the only uranium producer in Utah.”
- White Mesa Uranium Mill: Energy Fuels Resources (USA) Inc. (Utah Department of Environmental Quality) primary government
The NSDA asks DOE to tailor its emergency-management order (NE O 151.1) to 'on-site emergency response only (no off-site planning required)', justified by the worst-case boundary dose and an 800 m distance to the nearest residence (Appendix C.3); it says 'Emergency planning requirements remain limited to on-site response'. It commits to coordination with Emery County Emergency Management, Emery County Fire and local responders: familiarization tours, table-top exercises, hazard information, direct notification links and annual coordination meetings. DOE-STD-1271 lets contractors use equivalent NRC or industry standards 'except where noted'; its Emergency Management entry (NE O 151.1) lacks the explicit 'may choose ... an alternative' sentence most other sections carry, and the Nuclear Innovation Alliance reads the standard as allowing equivalents 'except for Emergency Planning and Cybersecurity'. The standard's general text does still let a contractor request a 'self-generated equivalent' or an exemption for any listed item, decided by DOE's approval authority, so a request like Valar's is not ruled out on its face. Valar's web summary does not list emergency planning among the alternatives DOE approved (safe-005). Local record: the Emery County Fire Protection District's 15 December 2025 minutes record the board discussing the 'nuclear test plant proposed in Orangeville' and its fire protection plans, and the outgoing chair saying he would sign them when the paperwork arrived. No public emergency plan for Ward 250, no record of a table-top exercise, and no public notification arrangement for residents were found as of 29 September 2026. In comments to DOE (March 2026), Uranium Watch said news coverage of the Valar reactor gave no information on emergency response planning, spent fuel or who to contact. The paper's justification (p.54) calls boundary doses under 0.5 rem well below EPA's Protective Action Guides. EPA's lowest guide is 1 rem, a factor of 2, and the paper does not address EPA's 5 rem child-thyroid guide for potassium iodide, although it names iodine-131 as the main dose contributor.
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (status: Draft; issued for Public Release) (Valar Atomics, 2025-10) primary company “Emergency planning requirements remain limited to on-site response”
- DOE-STD-1271-2025, Authorization Pathway for Nuclear Facilities (August 2025; DOE standard, copy posted by the Nuclear Innovation Alliance) (U.S. Department of Energy, Office of Nuclear Energy, 2025-08) primary government “NE O 151.1 Comprehensive Emergency Management System”
- A Review of Recent DOE Updates to Its Reactor Authorization Process (Nuclear Innovation Alliance) analysis “Except for Emergency Planning and Cybersecurity, the Standard allows the Contractor to use any equivalent”
- Emery County Fire Protection District Meeting Minutes, December 15, 2025 (Emery County Fire Protection Special Service District, 2025-12-15) primary government “The Board discussed the nuclear test plant proposed in Orangeville”
- Comments regarding DOE categorical exclusion for advanced nuclear reactors, Docket DOE-HQ-2025-0405 (NIRS and 25 co-signing groups incl. HEAL Utah and Uranium Watch) (Nuclear Information and Resource Service et al., 2026-03-04) analysis “did not provide any information about the operation of the test reactor”
- DOE-STD-1271-2025, Authorization Pathway for Nuclear Facilities (August 2025; DOE standard, copy posted by the Nuclear Innovation Alliance) (U.S. Department of Energy, Office of Nuclear Energy, 2025-08) primary government “The Contractor may also request a self-generated equivalent requirement”
The Utah San Rafael Energy Lab's FAQ page (a State of Utah site; created 3 Sept 2024, last modified 19 Nov 2025 per its WordPress record; read 29 Sept 2026) answers 'What is the permit and regulatory process for a test reactor?' by saying 'the planned reactor' is a research and test reactor that will go through 'the 10 CFR Part 50 process just like a full sized nuclear power plant would', meeting 'Class 104 standards', that 'The state and county will also negotiate details', and that operators 'will have to maintain a 10 CFR Part 55 operator license', with 'frequent testing by the NRC'. The page was first published on 3 September 2024, before Valar's MOU, and parts of it read as generic text (it describes worst cases involving 'pressurized steam' and a 'containment building', features of water-cooled plants rather than helium-cooled Ward 250), but it is about Valar's project: re-read on 29 September 2026, it names Valar Atomics several times, and its spent-fuel answer says 'Valar Atomics will not produce spent reactor fuel with this reactor' (disc-021, disc-033). It remains the lab's live public answer. Ward 250, the only reactor operating at the lab, is authorized by DOE under 10 CFR 830 with no NRC license planned (safe-001), and its operators are qualified under a research-reactor industry standard, with no NRC operator licences involved (safe-017); the county has no approval role over the reactor (gov-020). The lab's own Valar page, also live, says Ward 250 reached 'full-power fueled criticality' on 18 June (DOE, ANS and UIPA all describe a zero-power test; orig-012), that its fuel will 'remain impossible to melt' (see safe-025), and calls the lab 'the premier independent site for commercial advanced nuclear deployment' and a route 'directly from localized testing to the commercial grid', while DOE describes the pilot reactor itself as research that does 'not demonstrate reactors for commercial suitability', though DOE also calls the program a fast track toward later commercial licensing (gov-007). The state is Valar's host and landlord, not its regulator (ppl-018).
- FAQs | Utah San Rafael Energy Lab (Utah San Rafael Energy Lab (Utah Office of Energy Development), 2025-11-19) primary government “the 10 CFR Part 50 process just like a full sized nuclear power plant would”
- Valar Atomics | Utah San Rafael Energy Lab (Utah San Rafael Energy Lab (Utah Office of Energy Development)) primary government “the premier independent site for commercial advanced nuclear deployment”
- energylab.utah.gov page record for 'faq' (created 2024-09-03, modified 2025-11-19) (Utah San Rafael Energy Lab (WordPress API), 2025-11-19) primary government
- Second round of Launch Pad selections includes eight newcomers (American Nuclear Society, Nuclear Newswire, 2026-08-25) news “achieved zero-power fueled criticality with its 100-kWt Ward 250”
Valar's QA Program Description (October 2025; status 'Approved', and Valar's post says DOE approved it) covers not just the Ward 250 reactor but a 'Valarin Fuel Fabrication Facility' at the Utah San Rafael Energy Research Center; together they are called the Valar Atomics San Rafael (VASR) Facility. It says the fuel lab will make TRISO particles in graphite compacts using German HOBEG technology with modern improvements. This matches Valar's stated aim to make its own fuel beside its reactors (orig-014) and its fuel-line pilot selection (orig-032). Whether the fuel lab has been built or authorized is not stated in the sources read; see plans_ops.json.
- Ward250 San Rafael Facility Quality Assurance Program Description (Document 100474, Rev. 02) (Valar Atomics, 2025-10) primary filing “leveraging proven German HOBEG technology with modern process improvements”
Valar's NSDA says that while Ward 250 is under DOE authority, Valar will coordinate with Utah DEQ, the Division of Waste Management and Radiation Control, Emery County Emergency Management, Emery County Fire and local responders; that state representatives 'may observe but not direct DOE regulatory activities'; and that 'The State of Utah maintains agreements with DOE regarding notification and coordination for nuclear facilities within the state', including environmental data sharing and emergency coordination. No such Utah-DOE agreement was found in state or DOE sources searched on 29 September 2026. The state's own pieces: the Office of Energy Development owns the lab and is Valar's landlord (mine-035); it advertised for a lab-wide Safety Manager in September 2026 (dir-006); Utah's 2026 H.B. 78 created a Nuclear Energy Regulatory Office and conditions spent-fuel storage on a DWMRC permit (csite-023). In its 2025 lawsuit post, Valar argued small test reactors could be regulated by states, some of which were creating regulatory bodies (safe-028).
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (status: Draft; issued for Public Release) (Valar Atomics, 2025-10) primary company “State representatives may observe but not direct DOE regulatory activities”
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (status: Draft; issued for Public Release) (Valar Atomics, 2025-10) primary company “The State of Utah maintains agreements with DOE regarding notification and coordination”
- Valar Atomics is Suing the NRC (The Nuclear Necessity and our decision to sue the NRC) (Valar Atomics (Isaiah Taylor), 2025-04-07) primary company
Two ETV News items from 2025, eleven months or more before the Wellington lease vote, show that a Valar project in Carbon County was in the local paper in general terms. On 17 September 2025 ETV printed the state Office of Energy Development's groundbreaking release (orig-067); its 'About Valar Atomics' paragraph says Valar 'is building America’s first nuclear gigasites', which it defines as clusters of thousands of high-temperature reactors. On 10 October 2025 an ETV article on the San Rafael lab, quoting lab director Jaron Wallace, reported that after about three years, once Valar completes its reactor and proves it can be run safely, 'their current plan is to build a manufacturing hub in Carbon County', which could bring hundreds of jobs to Carbon and Emery; it also said Valar was looking at powering data centers. The article does not say who told ETV about the Carbon plan, names no site, and says nothing about trust land or reactors in Carbon County. In sum, a Carbon County project by Valar was public in general terms from October 2025; the Wellington location, the trust-land lease and the plan for a reactor, fuel and industrial campus there were not found in any local record before the state vote (loc-011, loc-012, loc-032). The lease was approved about eleven months after the article, sooner than the 'after three years' it described.
- Valar Atomics breaks ground on test reactor at the Utah San Rafael Energy Lab (ETV News reprint of a Utah Office of Energy Development release) (ETV News, 2025-09-17) news “Valar Atomics is building America’s first nuclear gigasites”
- What’s actually happening at the Utah San Rafael Energy Lab? (Susanna Watts) (ETV News, 2025-10-10) news “their current plan is to build a manufacturing hub in Carbon County”
ETV News (10 Oct 2025) quoted Jaron Wallace, director of the state-run Utah San Rafael Energy Lab that hosts Ward 250: 'Any nuclear company is required to show no dose at the site boundary during an accident event', adding that in the worst case 'the site boundary and thus the public will never see a dose of radiation above background'; the article also paraphrased him that Valar must prove no damage or radiation can pass the fence line of its 11 acres. Set beside the record: Valar's own Ward250 Nuclear Safety Design Agreement (revision 02, October 2025, marked draft) models a bounding 'maximum hypothetical accident' that assumes fuel-particle failures beyond demonstrated limits, a breach of the pressure boundary and stable, light-wind weather (Class F, 1 m/s) that the paper calls the most conservative. It puts the dose at the 400-metre site boundary below 0.5 rem (500 millirem) in one section and below 100 millirem in another, and below 0.1 rem at the nearest home about 800 metres away (safe-013). It measures these against a 25 rem evaluation guideline, not against zero. DOE's categorical exclusion gives natural background radiation in central Utah as about 100-120 millirem a year, and the routine public dose limit as 100 millirem a year. So the company's own analysis does not show 'no dose' at the boundary: it shows a small calculated dose in an accident it treats as a worst case, far below the guidelines it uses. Whether the lab director meant routine operation or a different standard is not in the record; this rests on one news report of his words.
- What’s actually happening at the Utah San Rafael Energy Lab? (Susanna Watts) (ETV News, 2025-10-10) news “Any nuclear company is required to show no dose at the site boundary”
- Ward250 Nuclear Safety Design Agreement (Document 100403, Revision 02, marked draft, October 2025) (Valar Atomics, 2025-10) primary company “Preliminary results indicate site boundary doses below 0.5 rem Total Effective Dose Equivalent”
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (categorical exclusion B5.26) (U.S. Department of Energy, Office of Nuclear Energy, 2026-04-22) primary government “Natural background radiation in central Utah is approximately 100-120 mrem/year.”
ETV News (Susanna Watts, 10 October 2025) reported that the Utah Office of Energy Development bought the San Rafael Energy Lab in July 2024 after Emery County had run it for two years, that Valar's buildings were going up on an 11-acre allotment there, and that Valar must show that under worst-case conditions no damage or radiation passes the fence line of those 11 acres. At the Trust Lands hearings the Office of Energy Development's deputy directors said their office owns and operates the lab and that Valar is its tenant on state land. Valar later said it was buying about 110 acres north of the lab from Emery County (mine-018).
- What's actually happening at the Utah San Rafael Energy Lab? (ETV News (Susanna Watts), 2025-10-10) news “Their buildings are currently under construction in their 11-acre allotment.”
- 2026-08-20 TLA Board of Trustees Meeting Audio Transcript (auto-generated) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-08-20) primary government “the state agency that is that owns and operates the San Rafael Energy Lab”
ETV News (10 October 2025) quoted Jaron Wallace, identified as director of the Utah San Rafael Energy Lab (a state office), saying any nuclear company must show no dose at the site boundary in an accident, that in the worst case the public 'will never see a dose of radiation above background', and that Valar must prove radiation cannot pass the fence line of its 11 acres. Valar's own NSDA, dated the same month, does not claim zero: its worst-case analysis gives up to 0.1 or 0.5 rem at a 400 m boundary and up to 5 rem at 100 m (safe-013), and its standard is the 25 rem evaluation guideline, and it also cites a 1 rem figure labelled 'USNRC NPUF', which matches the NRC's test for sizing an emergency planning zone (1 rem over 96 hours, 10 CFR 50.33(g)(2)); neither is zero. As reported, the director's description (no dose at the boundary) differs from both the figures the NSDA measures against and the company's own analysis.
- What's actually happening at the Utah San Rafael Energy Lab? (ETV News, 2025-10-10) news “Any nuclear company is required to show no dose at the site boundary”
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (status: Draft; issued for Public Release) (Valar Atomics, 2025-10) primary company
The Utah Office of Energy Development's release on the Ward 250 groundbreaking, published September 17, 2025 by Utah Business and ETV News, says the Utah San Rafael Energy Lab and Valar 'today' announced the groundbreaking of a site for the state's first nuclear test reactor, and also that the launch coincides with the 24th anniversary of 9/11, which fell on September 11, 2025; Valar's Ward 250 page gives 09.17.2025 (orig-007). The release itself does not settle the ceremony date; state and county records do: the Office of Energy Development's October 2025 update to legislators and Emery County's minutes put it on 11 September 2025 (gov-015, gov-021). The release names Kiewit Corporation for engineering and construction, Goree for architecture and design, and Sprung for the building; Valar's July 2025 slides had described a temporary facility (orig-045). It quotes the lab director, the energy office director and Taylor, and ends with Valar's own description: gigasites of thousands of high-temperature reactors making fuels cheaper than oil, Ward Zero completed in just 10 months, and the world's first binding Coordinated Research Project for an advanced reactor with PNRI (orig-064, orig-066). A state agency's release carried these company claims without qualification.
- Valar Atomics breaks ground on test reactor at the Utah San Rafael Energy Lab (Utah Office of Energy Development release) (Utah Office of Energy Development (published by Utah Business), 2025-09-17) primary government “Valar Atomics has chosen the Kiewit Corporation for engineering and construction”
- Valar Atomics breaks ground on test reactor at the Utah San Rafael Energy Lab (ETV News, 2025-09-17) news “coincides with the 24th anniversary of 9/11”
- Ward 250 | Valar Atomics (Valar Atomics) primary company “Ward 250 Groundbreaking 09.17.2025”
Gov. Spencer Cox launched 'Operation Gigawatt' on 8 October 2024, a plan to double Utah's power production in ten years, one of whose four goals is policies 'to enable clean, reliable energy like nuclear and geothermal'; his January 2026 update credits it with 'breaking ground on a nuclear test reactor'. A search of the governor's website (WordPress search API, 29 Sept 2026) for 'Valar' returns a single item: his public schedule for 8-14 September 2025, which lists '10:00 a.m. Speak at Valar Atomics groundbreaking', San Rafael Energy Research Center, Orangeville, on a Thursday. That schedule's day labels do not match its own title (it heads the week 'Sept. 8 - Sept. 14' but labels the days Sept. 8, 2, 3, 4 and 5), so the schedule alone does not fix the date; the Thursday of the titled week was 11 September. The Office of Energy Development's written update to the Legislature's Public Utilities, Energy and Technology Interim Committee (15 October 2025) states that Valar 'held groundbreaking for a nuclear test reactor on September 11, 2025', which matches the state release's 9/11-anniversary line; Valar's Ward 250 page gives 09.17.2025, the day the release was published (orig-007, orig-067). On the state's records, 11 September 2025 is the date; Valar's date does not match. The governor first described the Valar deal publicly on Bloomberg TV and to KUTV in May 2025 (ppl-018, orig-065); no governor's press release, executive order or signed agreement naming Valar was found on governor.utah.gov. On 28 April 2025 Utah leaders signed an MOU with Idaho National Laboratory that envisions a new Utah Advanced Nuclear and Energy Institute as a hub linking INL, the state's universities, OED and the San Rafael lab.
- NEWS RELEASE: Gov. Cox unveils 'Operation Gigawatt' (Office of the Governor of Utah, 2024-10-08) primary government “Enhancing Utah's policies to enable clean, reliable energy like nuclear and geothermal”
- NEWS RELEASE: Gov. Spencer J. Cox and Lt. Gov. Deidre M. Henderson Public Schedule 9/8/25-9/14/25 (Office of the Governor of Utah, 2025-09-07) primary government “Speak at Valar Atomics groundbreaking”
- governor.utah.gov post search for 'Valar' (1 result), run 2026-09-29 (Office of the Governor of Utah) primary government
- Gov. Cox marks one-year anniversary of 'Built Here' strategic plan with update on key metrics (Office of the Governor of Utah, 2026-01-30) primary government “breaking ground on a nuclear test reactor”
- Utah Leaders Sign Memorandum of Understanding with Idaho National Laboratory (Office of the Governor of Utah, 2025-04-28) primary government
- Office of Energy Development Update, Public Utilities, Energy, and Technology Interim Committee, October 15, 2025 (items 2-8) (Utah Office of Energy Development (Utah Legislature meeting materials), 2025-10-15) primary government “held groundbreaking for a nuclear test reactor on September 11, 2025”
Valar's Ward 250 page lists 'Ward 250 Groundbreaking' on 09.17.2025, and its Castle Country page lists a local news item from September 2025 about breaking ground at the Utah San Rafael Energy Lab. DOE's June 18, 2026 release quotes Taylor saying the site was empty nine months before criticality, consistent with a September 2025 start. Local-coverage details are in local.json. State records settle the ceremony date: the Office of Energy Development's slide update to the Legislature's interim committee (15 October 2025) says Valar 'held groundbreaking' on September 11, 2025, Emery County's 2 September 2025 minutes say ground would be broken 'on September 11', and the county economic board's minutes schedule it for that Thursday (gov-015, gov-021). 17 September 2025 is the day the joint state-Valar release was published (orig-067), which is the date Valar's page shows (disc-040).
- Ward 250 | Valar Atomics (Valar Atomics) primary company “Ward 250 Groundbreaking 09.17.2025”
- Department of Energy Celebrates Second Advanced Reactor Achieving Criticality (U.S. Department of Energy, 2026-06-18) primary government
The Emery County Commission's minutes of 2 September 2025, item 16: 'Valor Atomics is getting ready to break ground' at the San Rafael Energy Research Center 'on September 11' and hopes to start 'next year on July 4th'; 'The Building department has not issued a building permit, so this is the process to move forward.' The commission voted 3-0 to approve a building permit for Valar 'so they can move forward with their project'. No building-code review, plans or conditions are recorded in the minutes. The same meeting voted to support Green River as a potential site for the state energy office's nuclear power generation project after the governor's agreement with TerraPower. The county's economic development board minutes of 9 September 2025 note the Valar groundbreaking 'scheduled for Thursday at 9:30 a.m.', i.e. 11 September (gov-015). Earlier county-state steps: on 19 November 2024 the commission approved selling the San Rafael Energy Research Center to the State of Utah (Division of Facilities Construction and Management) for $2,111,444, and on 4 February 2025 extended contract #231366 with OED to June 2025 so the county could keep being reimbursed for bills it paid on the state's behalf at the lab.
- Emery County Commission Meeting Minutes, September 2, 2025 (Emery County Commission (Utah Public Notice Website), 2025-09-02) primary government “The Building department has not issued a building permit, so this is the process”
- 9-Sept 2025 CEO Board Meeting Minutes (Emery County Economic Development Board, posted with notice 1021269) (Emery County Economic Development Board (Utah Public Notice Website), 2025-09-09) primary government “Valar Atomics groundbreaking scheduled for Thursday at 9:30 a.m.”
- Emery County Commission Meeting Minutes, November 19, 2024 (Emery County Commission (Utah Public Notice Website), 2024-11-19) primary government “Proposed purchase price is $2,111,444.00.”
- Emery County Commission Meeting Minutes, February 4, 2025 (Emery County Commission (Utah Public Notice Website), 2025-02-04) primary government “continue to be reimbursed for the bills EC is paying on behalf of the State”
Utah law (Title 79, Chapter 6, Part 10) creates the Utah Energy Research Board inside OED to oversee the San Rafael Energy Lab; the lab must receive and evaluate project proposals and recommend them, and the board 'shall review the project proposals' and make 'final decisions on approval' (79-6-1005); the lab may contract with users, with revenue going to the Utah Energy Research Fund (79-6-1004(2)(d)). The board's first meeting, noticed on the Utah Public Notice Website, was held 13 August 2025 at the State Capitol, 10:00 to 10:35 a.m. Per its approved minutes, members took the oath, appointed Jaron Wallace lab director, and then heard 'Project Valar', 'a 250-kilowatt microreactor test site' that 'recently received approval' from DOE; they discussed private funding, returning the site to a 'Greenfield' state and financial assurance for liability; Emery County Commissioner Dennis Worwood, a board member, 'noted strong public support' in Emery County; the motion to approve, made by member Larry Howell and seconded by Worwood, passed 7-0. Set beside the record: by then OED had signed its MOU (16 May), Valar had held its Emery town hall (8 July) and DOE had announced its selection a day earlier (12 August), a selection, not an authorization; DOE's OTA began 22 October 2025 (gov-003). The same meeting approved a Natura Resources molten-salt project at the lab. The minutes record that the meeting closed with a public comment period, in which attendees expressed appreciation for the board's formation.
- Utah Code Title 79, Chapter 6, Part 10, Utah San Rafael State Energy Lab (79-6-1001 to 1005, with 2025 amendments) (Utah State Legislature) primary government “make final decisions on approval of project proposals for funding and implementation”
- Utah Energy Research Board Meeting 08-13-2025 (notice and agenda) (Utah Public Notice Website, 2025-08) primary government “DISCUSSION/MOTION: VALAR - Dr. Jaron Wallace”
- Board Meeting Minutes, Utah Energy Research Board, August 13th, 2025 (Utah Energy Research Board (Utah Public Notice Website), 2025-11-13) primary government “Motion Passes to move forward with the Valar Project.”
- Department of Energy Announces Initial Selections for New Reactor Pilot Program (U.S. Department of Energy, 2025-08-12) primary government “DOE will initially work with 11 advanced reactor projects”
ETV News (Julie Johansen, July 9, 2025) reported the Emery County Commission's July 8, 2025 town hall in Castle Dale, requested by Valar after an MOU was signed and before its contract with the state lab was final. As reported, Valar said the company was about two years old, had a non-fueled test reactor near Los Angeles, aimed for July 4, 2026 (the nation's 250th birthday, hence 'Ward 250') with commercial development by 2028, expected about 40 employees for roughly 12 months of testing with local contractors for construction, and chose Utah because Carbon and Emery counties are the state's energy hub. A Valar slide deck posted on the state-run Utah Public Notice Website (file created July 8, 2025, server date 9 July 2025; 11 of its 12 pages are marked 'CONFIDENTIAL. DO NOT DISTRIBUTE.', yet the file is publicly posted; the public body and notice it is attached to were not identified) says the same: under 250 kW, 30 effective full-power days over 12 months in a temporary facility, commercial deployment by 2028.
- Not A Nuclear Plant Just Testing a Small Nuclear Reactor (ETV News (Emery Telcom), 2025-07-09) news “the nation’s 250 birthday, thus the name Valar Atomics Ward 250”
- Valar Atomics + SRERC in Emery County (Valar Atomics (posted on Utah Public Notice Website), 2025-07-08) primary government “Commercial Deployment by 2028”
July 8, 2025, Emery County town hall (as ETV News reported): Valar said it chose Utah because Carbon and Emery counties are the state's energy hub (orig-045). In 2024, by its head of projects' later account to the Trust Lands board, Valar had met Carbon County officials when its plan was to make fuels from coal-plant flue gas (mine-018). February 24, 2026: Valar's open-house notice invited residents of Carbon and Emery counties to the Emery site, its head of projects saying Valar wanted neighbors to understand exactly what it is building and why; the notice mentions only Ward 250. Between August 25 and September 9, 2026, Valar's site first linked its 'Castle Country' page, headed 'Carbon & Emery County, Utah', which promises gigasites but names no Carbon site (dir-008, mine-020, csite-027). Meanwhile the record shows a state lease map for the Wellington parcel produced April 9, 2026 (mine-048), a Carbon County support letter signed June 29, 2026 (mine-013), the first public agenda naming Valar for the site on August 10, 2026 (csite-018), a Valar mining claim staked September 12, 2026 (fld-002) and the board's approval on September 17, 2026 (mine-011). No Valar publication read names the Carbon County site as of 2026-09-29.
- Not A Nuclear Plant Just Testing a Small Nuclear Reactor (Julie Johansen) (ETV News, 2025-07-09) news “Carbon and Emery Counties are the hub of energy for Utah”
- Valar Atomics welcomes community for reactor facility open house (ETV News, 2026-02-24) news “understand exactly what we are building and why”
- Castle Country | Valar Atomics (Valar Atomics) primary company “Carbon & Emery County, Utah”
The Utah Investigative Journalism Project's 'Who is Valar Atomics?' (Eric Peterson, 8 July 2025, with Utah News Dispatch) is the only investigative piece on Valar by a Utah newsroom found; its report of engineers' CT-scan calculations is cited elsewhere here only as reported, with the engineers' inputs unknown, until their own posts are archived (the claim itself: safe-026; a worked check: pf-007). It also reported: that over a dozen advanced reactor companies were listed on the NRC's website, 'but not Valar', while co-plaintiff Deep Fission was; that Valar's top engineers came from Ultra Safe Nuclear, which went bankrupt and sold its intellectual property to Nano Nuclear (ppl-015), with a University of Utah law professor noting possible litigation over ideas staff learned at earlier employers; that TRISO fuel is very robust but very expensive, with engineer Nick Touran saying 'just the fuel cost alone prevents that from even making sense at all' for factory-built reactors, and that maintaining a thousand-reactor farm would kill the concept; Touran's warning, 'In nuclear, an incident anywhere is an incident everywhere'; Georgia Tech nuclear engineer Anna Erickson: 'I don't know how you can claim your design is so safe without doing engineering'; and the state energy office director: 'Just because we have that MOU, there's still not a commitment at the moment'. Valar and its head of operations did not respond to the reporter's requests. Other Utah coverage found is news or opinion, not investigation: Salt Lake Tribune editorials (May and November 2025), a Utah News Dispatch opinion column (March 2026) drawing on Mother Jones, and the Tribune's republication of ProPublica (dir-011).
- Who is Valar Atomics? (Eric Peterson, Utah Investigative Journalism Project with Utah News Dispatch) (Utah Investigative Journalism Project, 2025-07-08) news “In nuclear, an incident anywhere is an incident everywhere”
- Who is Valar Atomics? (same article: Anna Erickson) (Utah Investigative Journalism Project, 2025-07-08) news “I don't know how you can claim your design is so safe without doing engineering”
- Tribune editorial: Spencer Cox's nuclear dream for Utah deserves careful scrutiny (headline only; paywalled) (The Salt Lake Tribune, 2025-05-30) analysis
The New Republic (May 2026), from the audio recording of Valar's 8 July 2025 town hall in Castle Dale (see orig-045), reports: by then the site was picked and construction moving; when a resident asked if the reactor had run, head of projects Max Ukropina said 'We had it on since February. On and off, in different ways', which referred to the non-nuclear thermal prototype, and the resident concluded the reactor was technically untested; Taylor said Valar was 'hesitant to be the company that comes in and promises the world'; and when a resident raised Chernobyl and said the town did not want to be part of a race with China, Taylor asked how many people had died in the coal industry in Carbon and Emery counties and said 'the deaths are terrible, but power is important.' The magazine describes the residents as having had 'very little say'. The town hall itself was requested by Valar after the state MOU (orig-045); the state lab director says the contract followed about two weeks after Valar first said it wanted to build there (ppl-027). Residents who spoke are described, not named.
- Donald Trump Is Going Nuclear (Colin Jones) (The New Republic, 2026-05-26) news “the deaths are terrible, but power is important”
- Donald Trump Is Going Nuclear (Colin Jones) (The New Republic, 2026-05-26) news “We had it on since February. On and off, in different ways”
The first public county meeting on Valar followed news reports: at the 3 June 2025 Emery County Commission meeting a commissioner referred to 'the article floating around and on social media' about reactors at the San Rafael Energy Research Center and said a public hearing had been set for 17 June (its notice was posted 29 May). The minutes of that 17 June 2025 hearing on 'Nuclear Industries in Emery County' record the state lab director, Jaron Wallace, saying Valar 'would like to build nuclear reactors at the Research Center' and was 'looking at manufacturing in Emery or Carbon County', that another company, NuCube, was also interested, and that permitting 'will take some time'; later he said 'Transparency is imperative. We are not trying to keep anything from anyone', that the meeting was 'the first of many', and that safety was 'the number one priority'. Residents spoke both ways: several supported nuclear power and jobs; others asked whether the county has any control over a state-owned site, worried about being 'by-passed by the State', security, waste staying in the county, and cancer in families exposed in the past; one said she had not heard enough to be convinced. Set beside the record: the OED-Valar MOU signed a month earlier made the arrangement confidential and barred publicity without both parties' consent (gov-011); DOE's pathway gave the county no approval role over the reactor (safe-001). This is also the earliest public record found that ties Valar to Carbon County, fourteen months before the Trust Lands agenda of August 2026 (csite-018, ppl-027); it names the county, not a site.
- Minutes of a Public Hearing of the Board of Emery County Commissioners, June 17, 2025 (Nuclear Industries in Emery County) (Emery County Commission (Utah Public Notice Website), 2025-06-17) primary government “They are looking at manufacturing in Emery or Carbon County.”
- Emery County Commission Meeting Minutes, June 3, 2025 (Emery County Commission (Utah Public Notice Website), 2025-06-03) primary government “the article floating around and on social media”
- Public Hearing: Nuclear Industries in Emery County, June 17, 2025 (notice) (Utah Public Notice Website, 2025-06) primary government
KUTV (published May 28, 2025, from an interview the governor gave that week or the week before) reported Governor Spencer Cox's first account of the Valar arrangement: a memorandum of understanding letting Valar use the San Rafael Energy Research Center; a test reactor that would lead to energy production over the next ten years; a cost to the state of 'virtually nothing', with Utah just providing space and infrastructure; and safety assured by working with the Nuclear Regulatory Commission through planning, building and implementation. KUTV reported the reactor would not produce any energy, and that it had filed records requests for the MOU. In July 2025 the director of the Utah Office of Energy Development told the Utah Investigative Journalism Project the MOU was non-binding, that there was not yet a commitment, and that Valar would still have to follow all federal licensing rules. Set beside the later record: Ward 250 was authorized by DOE alone, with no NRC license planned (safe-001); Valar says, and Deseret News reported, that it generated electricity at the site on July 1, 2026 (orig-013, orig-042); the lab is state-owned and Valar is its tenant (mine-035); and the state approved up to $106.7 million in post-performance tax credits for Valar in July 2026 (csite-024). The oversight the governor described in 2025 was not the path the reactor took.
- Utah's new 'advanced' nuclear reactor for research, won't produce energy (KUTV 2News, 2025-05-28) news “just providing the space and infrastructure”
- Who is Valar Atomics? (Eric Peterson, with Utah News Dispatch) (The Utah Investigative Journalism Project, 2025-07-08) news “Just because we have that MOU, there’s still not a commitment at the moment”
BLM's public layers show 7 notice-level and 7 plan-level locatable-mineral cases in Emery County and none in Carbon. Of the 7 notices, 5 are for 'URANIUM AND OTHER MIN': PINON RIDGE BUCKMASTER (Pinon Ridge Mining LLC, authorized 2024), PEGASUS (ENERGY SANDS & JUPITER) (Pegasus Resources Inc, pending, 2024), SAHARA GREEN RIVER SOUTH (San Rafael Resources LLC, authorized 2024), 'MELINDA EXPLORATION PROJECT' (UTUT106713795, operator C2C NUCLEAR INC, created 24 January 2025, 640 acres mapped in T23S R15E, 'Pending'), and an unnamed notice (UTUT106721750, created 7 March 2025, T24S R10E, no operator shown, 'Pending'). The others are Georgia-Pacific Gypsum's 2025 gypsum exploration notice (authorized 13 June 2025) and an old rock notice. The 7 plans include the Kimmerle Green River #9 uranium plan (authorized 2015), gypsum quarries including the pending 'Powell Gypsum Quarry' (UTUT106759404, created 18 November 2025, T19S R11E), and gemstone and shale operations. The C2C notice sits in the same township as most of the 341 'SS' lode claims of 2024 (mine-003). No record read links any of these operators to Valar.
- BLM Natl MLRS Locatable Notices (feature layer and query results) (Bureau of Land Management (MLRS)) primary filing “MELINDA EXPLORATION PROJECT”
- BLM Natl MLRS Plans of Operations (feature layer and query results) (Bureau of Land Management (MLRS)) primary filing
The Utah Inland Port Authority (UIPA) board created the Castle Country Project Area on 24 June 2024 and enlarged it on 6 January 2025 (Amendment #1, +10,754 acres of Emery County parcels), 23 April 2026 (#2, Carbon County) and 21 May 2026 (#3); it now covers about 15,370 acres in Carbon and Emery counties including parts of Green River and Wellington. The plan's parcel list includes '04-0019-0030', labelled 'San Rafael Energy Research Center', in Section 24, T18S R7E; that is the 112.7-acre parcel Emery County let Valar test for site suitability in February 2026 and matches the roughly 110 acres Valar says it is buying (mine-046). The plan sends 75% of the growth in property tax to UIPA for 25 years (extendable 15), 25% to local taxing entities, projecting $72.9M to the project area; UIPA may use it for business incentives and public infrastructure districts. UIPA staff told its board on 4 August 2026 that Valar's operations 'will be expanding into the Castle Country project area', and UIPA's 10 September update says Valar 'has also purchased' more than 100 acres there. The only Castle Country business incentive on the board's 2026 agendas is for Anson Resources (3 September 2026); no UIPA incentive for Valar was found as of 29 September 2026. Tax-differential collection starts only when UIPA 'triggers' parcels by board resolution; its 2026 Castle Country trigger resolution (16 March 2026) covers only the Fossil Rock Area parcels, not 04-0019-0030. The parcel was placed in the zone in January 2025, four months before OED's MOU with Valar (gov-011). On 19 May 2026 the Emery County Commission voted to remove the parcel from the project area; UIPA's later records still include it (gov-023).
- Castle Country, A Utah Inland Port Project Area, Project Area Plan & Budget Amendment #3 (FINAL) (Utah Inland Port Authority (Utah Public Notice Website), 2026-05-21) primary government “San Rafael Energy Research Center: 04-0019-0030”
- APPROVED August 4, 2026 UIPA Board Meeting Minutes (Utah Inland Port Authority, 2026-09-03) primary government “Valar's operations will be expanding into the Castle Country project area.”
- Castle Country Project Area Builds Momentum Across Energy, Critical Minerals and Logistics (Utah Inland Port Authority, 2026-09-10) primary government
- Utah Inland Port Authority (UIPA) Board Meeting, September 3, 2026 (agenda: Resolution 2026-41 Anson Resources Incentive) (Utah Public Notice Website, 2026-09) primary government
- Amended Trigger Resolution for Castle Country Project, Resolution No. 2026-09 (adopted 16 March 2026) (Utah Inland Port Authority (Utah Public Notice Website), 2026-03-16) primary government “Tax year 2026 is established as Year One for Castle Country Project parcels”
Carbon Commission minutes show two earlier support-letter cases. On 16 October 2024, on an agenda item, the commission voted to approve a letter of support for a Division of Wildlife Resources land exchange and authorized the chair to sign it; the state's regional supervisor told the commission that the Governor's office always asks, on state land deals, whether the county has been notified. On 18 December 2024, when a conservation district asked for a support letter on an item not on the agenda, the deputy county attorney said the commission could not act on it that day because it was not on the agenda, 'but they can offer a letter of support'. For the 29 June 2026 Valar letter (mine-013) no agenda item or motion was found (csite-026), which fits the second pattern, not the first.
- October 16, 2024 Commission Meeting (Carbon County minutes; scanned, read by OCR) (Carbon County (Utah Public Notice Website), 2024-10-16) primary government “made a motion to approve a letter of support for the Division of Wildlife Resources”
- December 18, 2024 Commission Meeting (Carbon County minutes; scanned, read by OCR) (Carbon County (Utah Public Notice Website), 2024-12-18) primary government “we cannot act upon this today because it was not on the agenda”
On 20 December 2023 the Carbon County Commission, on a posted agenda item, adopted Resolution 2023-06 'Supporting the energy industry, more specifically nuclear power'. Per the minutes, Commissioner Jensen said it was meant to tell PacifiCorp/Rocky Mountain Power the community favoured nuclear plants and that 'we need to begin to educate the public about nuclear power'; it mirrored an Emery County resolution. The commission's minutes for January 2024 to April 2026 (50 sets, read by OCR in the research pass; the examples below were OCR'd again in this check) mention nuclear only in brief remarks: a 3 January 2024 recap of that resolution; Commissioner Martines phoning in on 16 October 2024 while returning from Idaho National Laboratory 'in conjunction with' the San Rafael Energy Research Center; and, on 18 February 2026, Commissioners Martines' and Jensen's report on the Ward 250 reactor's delivery to the Orangeville test site, which he called the first of three prototypes. The one Trust Lands item, on 5 November 2025, renewed a county road easement on trust land along Ridge Road and Miller Creek, not the Wellington parcel. The commission's posted agendas from 6 December 2023 to 16 September 2026 (73 notices) name Valar once: a 'Valor Atomics presentation' on 19 August 2026. Its minutes record an update on the Emery lab, plans for a town hall in Price and a reactor open house within 30 to 45 days, and commissioners highlighting 'the tax benefits the plant will bring'; they do not name the Wellington site or the lease the state board heard the next day (mine-013). The 2026 minutes also record commissioners celebrating Valar's criticality (1 July) and Valar announcing a Carbon County town hall for late September or early October (2 September); none names the parcel or the letter. No agenda or minutes name the Wellington parcel or the 29 June 2026 support letter, and none shows a Valar zoning change, development agreement, road-use agreement, tax abatement or other county approval for the site.
- December 20, 2023 Commission Meeting (Carbon County Board of Commissioners minutes; scanned, read by OCR) (Carbon County (Utah Public Notice Website), 2023-12-20) primary government “we need to begin to educate the public about nuclear power”
- Carbon County Board of Commissioners: notices, agendas and minutes, Dec 2023 to Sept 2026 (browse list) (Utah Public Notice Website) primary government
- November 5, 2025 Commission Meeting (Carbon County minutes; scanned, read by OCR) (Carbon County (Utah Public Notice Website), 2025-11-05) primary government “sections of Ridge Road and two sections of the road that goes south”
- October 16, 2024 Commission Meeting (Carbon County minutes; scanned, read by OCR) (Carbon County (Utah Public Notice Website), 2024-10-16) primary government “traveling home from the Idaho National Labs in conjunction with the San Rafael”
- Aug 19, 2026 Commission Meeting Minutes (Carbon County; scanned, read by OCR) (Carbon County (Utah Public Notice Website), 2026-08-19) primary government “highlighted the tax benefits the plant will bring to reduce local residents' personal property taxes”
- February 18, 2026 Commission Meeting (Carbon County minutes; scanned, read by OCR) (Carbon County (Utah Public Notice Website), 2026-02-18) primary government “This is the first of three prototypes that will be coming.”
- Sept 2, 2026 Commission Meeting Minutes (Carbon County) (Carbon County (Utah Public Notice Website), 2026-09-02) primary government “a town hall event dedicated specifically to Carbon County is planned”
- January 3, 2024 Commission Meeting (Carbon County minutes; scanned, read by OCR) (Carbon County (Utah Public Notice Website), 2024-01-03) primary government “we are saying that we could support nuclear energy”
Before Valar arrived, public money built the San Rafael Energy Research Center near Orangeville. In October 2020 Emery County won a $7 million infrastructure grant and a $491,000 loan at 0.5% from the state's Community Impact Board, for a coal pulverizer for coal gasification, carbon fiber and hydrogen fuel research, and a molten salt/thorium laboratory (ETV, 9 Oct 2020; another ETV story that month puts the package at $7.5 million). A May 2022 account by the county, published by ETV News, says about $15 million in grants had been awarded to build, renovate and equip the center; it names research projects funded by the federal EDA and DOE and lists the Impact Board, the Legislature and state offices among its government funders, without itemizing the total. The fiscal note on the fifth substitute of 2024 H.B. 410 says the bill appropriates $2,000,000 one-time for the state Office of Energy Development to buy the lab and shifts $1,000,000 a year from an existing state research-grant line into a new Utah Energy Research Fund for the lab and grants; it also estimates $245,000 a year for a lab director, which the office could absorb (the enacted bill is in gov-016). Emery County approved the sale to the state for $2,111,444 in November 2024 (gov-021). The state's May 2025 MOU has the energy office provide the site, infrastructure and shared facilities for Valar's test (gov-011). The terms on which Valar uses the state's site (rent, reimbursement, restoration money) are not public (open question), though the state board discussed 'the project's private funding' and financial assurance when it approved the project (gov-013).
- Emery County Receives $7 Million Grant for San Rafael Energy Research Center (Julie Johansen) (ETV News, 2020-10-09) news “The county was subsequently granted a large Infrastructure grant in the amount of $7 million.”
- Tech Corner: Emery County Commission Secures $7.5 million in Funding to Further San Rafael Energy Research Center (Jade Powell) (ETV News, 2020-10-28) news “secured $7.5 million in funding for the San Rafael Energy Research Center”
- What is the San Rafael Energy Research Center? (Scottie Kraync) (ETV News, 2022-05-11) news “approximately $15 million dollars in grant funding to construct/renovate the SRERC”
- Fiscal Note, H.B. 410 5th Sub. (Salmon), Utah San Rafael State Energy Lab, 2024 General Session (Utah Office of the Legislative Fiscal Analyst, 2024-02-27) primary government “appropriates $2,000,000 one-time General Fund in FY 2025 to the Office of Energy Development”
A 1957 USGS report for the Atomic Energy Commission (H. S. Johnson Jr., Bulletin 1046-D) says uranium ore in the San Rafael district of Emery County was first reported in 1914 at Temple Mountain, on the east flank of the Swell; the deposits were mined for radium, and possibly vanadium, during World War I and intermittently to 1942; geologists studied Temple Mountain for the Manhattan Engineer District during World War II; production rose quickly after the war; and from 1952 to 1956 output came mainly from the Temple Mountain deposits and Vernon Pick's Delta mine, with the Lucky Strike and 10 to 15 smaller deposits.
- Uranium Resources of the San Rafael District, Emery County, Utah: a Regional Synthesis (Bulletin 1046-D) (U.S. Geological Survey (H. S. Johnson, Jr.), 1957) primary government “The Temple Mountain deposits were mined for radium and possibly byproduct vanadium”
In the order Carbon and Emery audiences heard it, from local reports and releases: 8 July 2025, Valar's Castle Dale town hall, reported by ETV the next day under the headline 'Not A Nuclear Plant Just Testing a Small Nuclear Reactor': a test of about 12 months with about 40 staff (orig-045). 17 September 2025, the state's groundbreaking release printed in ETV ends with Valar's own description: it 'is building America’s first nuclear gigasites', clusters of thousands of reactors (orig-067, loc-034). 10 October 2025, ETV reported that after about three years Valar's 'current plan' was a manufacturing hub in Carbon County, no site named (loc-034). 23 January 2026, a lab release printed in ETV: the site will house Valar's fuel fabrication facility as well as Ward 250. 24 February 2026, Valar's open-house release: Ward 250 is a research reactor for engineering validation and 'it is not a commercial power plant'. 7 April 2026, Emery hearing on the land sale: plans for the extra land 'not firm yet', maybe housing (ETV); fuel fabrication and manufacturing (minutes, gov-022). 9 July 2026, to the state incentive board in Salt Lake City: 'additional commercial units in the area' (gov-033); 9 and 21 July, up to 1,000 water shares for future development (mine-042). 12 August 2026: plans to eventually manufacture reactors and fuel, with mass production as the long-term goal (ETV). 19 August: 'potential plans' to produce reactors for industrial users so they can move off the grid (ETV, loc-006). 10 September: hopes to build hundreds of reactors in Carbon and Emery (loc-001). 17 September: state lease for a Carbon reactor, fuel and industrial campus approved (mine-011). None of these statements contradicts the company's published 'gigasite' aim (orig-001), and that aim was printed in the local paper in September 2025; the 2025 'just testing' framing described the first reactor only. The gap is in timing and specifics: the size of the plan reached local audiences in pieces, a Carbon County plan was reported in general terms in October 2025, and no local statement read named the Wellington site before the vote (loc-012).
- Not A Nuclear Plant Just Testing a Small Nuclear Reactor (Julie Johansen; reports the 8 July 2025 town hall) (ETV News, 2025-07-09) news “Not A Nuclear Plant Just Testing a Small Nuclear Reactor”
- Rapid construction from local contractors at Valar Atomics (USREL press release) (ETV News, 2026-01-23) primary government “will house Valar’s fuel fabrication facility”
- Valar Atomics welcomes community for reactor facility open house (Valar Atomics press release) (ETV News, 2026-02-24) primary company “it is not a commercial power plant”
- Emery Commission public hearing receives comments on the sale of property to Valar Atomics (ETV News, 2026-04-09) news
- Leaders look to coal, nuclear and new industry for growth at local energy summit (Kevin Butler) (ETV News, 2026-08-14) news “This is our home. We wanna stay here”
- Emery County Business Chamber gets an up-close look at Valar Atomics' progress (Stephanie Olsen) (ETV News, 2026-08-24) news “completely removing the risk of a meltdown”
- Community gets closer look at Valar Atomics during open house (Scottie Kraync) (ETV News, 2026-09-14) news “as we grow here in your backyard, in your community”
- Emery County Commissioners Debate Solar, Data Centers and EMS Funding (Kevin Butler) (ETV News, 2026-07-28) news
- Valar Atomics breaks ground on test reactor at the Utah San Rafael Energy Lab (Utah Office of Energy Development press release) (ETV News, 2025-09-17) primary government “Valar Atomics is building America’s first nuclear gigasites”
- What’s actually happening at the Utah San Rafael Energy Lab? (Susanna Watts) (ETV News, 2025-10-10) news “their current plan is to build a manufacturing hub in Carbon County”
Job figures on the record, in order: at the 8 July 2025 town hall, about 40 employees for roughly 12 months of testing, with local contractors for construction (ETV, 9 July 2025; orig-045); at the Carbon/Emery economic development group's September 2025 meeting, Emery Commissioner Dennis Worwood said Valar planned to hire 20-40 more local employees (ETV, 6 Oct 2025); on 10 October 2025 ETV reported the research at the lab had 'only brought in a few dozen jobs', mostly engineers from outside the area, and that a later Carbon County manufacturing hub could bring hundreds (loc-034); on 11 December 2025 Valar's Jess Housekeeper told Orangeville's council Valar was looking for 30-40 workers over the next six months (minutes); in February 2026 a USU Eastern housing study presented to a local housing committee counted Valar as planning to employ about 40 technicians and contractors (ETV, 24 Feb 2026); on 15 April 2026 Housekeeper told Ferron's council that Valar employed 120 people in Emery County, 'a lot' of them not living in Utah, with 15-20 full-time employees at the site plus construction workers and electricians (minutes); on 9 July 2026 the state's economic development board approved a tax credit on Valar's projection of 275 jobs at an average wage of $137,567 in Emery County with $1.3 billion of investment (csite-024); on 13 August 2026 Valar's Harry Hansen told the Orangeville council Valar had recently hired 40 new employees from the Castle Country area (ETV, 20 Aug); on 19 August Valar told the Carbon County Commission it had hired local residents from closed coal operations (minutes); on 10 September Max Ukropina said Valar has hired dozens of community members (ETV, 14 Sept). Emery Commissioner Jordan Leonard said in August that local hiring by Valar had drawn workers from other local jobs, opening places for returning families (ETV, 14 Aug). No figure for jobs at the Carbon County campus appears in the Trust Lands records summarized in carbon_site.json. The figures are not in conflict on their face: they count different things (site staff, contractors, everyone working for Valar in Emery) at different stages, and the April figure shows that many of the people then working for Valar in Emery did not live in Utah. The 275-job figure is a projection tied to a state tax credit that is paid only after the new tax revenue comes in (csite-024); no public count of Valar's Utah payroll exists to check the local figures against.
- The importance of the Economic Development Committee stressed by many (ETV News, 2025-10-06) news “plans to hire 20-40 more local employees”
- Housing Committee hears about coming population growth and housing crisis (ETV News, 2026-02-24) news “planning to employ about 40 technicians and contractors”
- Growth, industry and community issues highlight Orangeville council meeting (Kevin Butler) (ETV News, 2026-08-20) news
- Community gets closer look at Valar Atomics during open house (Scottie Kraync) (ETV News, 2026-09-14) news “as we grow here in your backyard, in your community”
- Leaders look to coal, nuclear and new industry for growth at local energy summit (Kevin Butler) (ETV News, 2026-08-14) news “some workers have left other positions in the community”
- Not A Nuclear Plant Just Testing a Small Nuclear Reactor (Julie Johansen; reports the 8 July 2025 town hall) (ETV News, 2025-07-09) news “hire about 40 employees for about 12 months in the actual testing”
- What’s actually happening at the Utah San Rafael Energy Lab? (Susanna Watts) (ETV News, 2025-10-10) news “only brought in a few dozen jobs”
- December 11, 2025 City Council Minutes (Orangeville) (Orangeville City, 2025-12-11) primary government “looking for 30-40 workers over the next 6 months”
- Ferron City Council Minutes, April 15, 2026 (scanned, read as page images) (Ferron City, 2026-04-15) primary government “We actively employ 120 people. A lot of those are NOT living in Utah.”
- Aug 19, 2026 Commission Meeting Minutes (Carbon County Board of Commissioners; scanned, read as page images) (Carbon County Commission, 2026-08-19) primary government “actively hired local residents from closed coal assets”
Valar says its 'doors remain open through tours, town halls and straight answers' (csite-027). In Emery County the record bears out frequent public contact: at least 15 appearances counting the county commission's (gov-020 to gov-039). Those found besides the commission: Orangeville City Council, 11 December 2025 (water line; 30-40 workers over six months), 11 June, 9 July and 13 August 2026 (fuel building, water shares, title, town hall); Orangeville planning commission, 16 July 2026 (I-2 zone); Castle Valley Special Service District, 19 February 2026 (plans by video; a second Valar staff member also attended); Cleveland Town was told on 12 March that Valar had presented to that board; Castle Dale City Council, 12 March 2026 (construction, water, security); Ferron City Council, 15 April 2026 (how the reactor works; that testing is done at 'worse case scenario' [sic]; staffing: 120 people employed in Emery, many living out of state, loc-004); a farm bureau meeting on 30 April 2026 (ETV, 1 May); the Emery County Business Chamber tour, 19 August; open houses on 26 February and 10 September 2026; and the July 2025 town hall. The fire district put Valar on its agenda in February and March 2026 (loc-018). In Carbon County the appearances were fewer and none named the Wellington site (loc-012). What the record cannot show is how complete the answers were: minutes are summaries, and several statements made at these meetings go beyond the public safety record (loc-005, loc-006, loc-025, ppl-026).
- December 11, 2025 City Council Minutes (Orangeville) (Orangeville City, 2025-12-11) primary government
- June 11, 2026 City Council Minutes (Orangeville) (Orangeville City, 2026-06-11) primary government “Once completed they will be the largest manufacturer of this fuel”
- July 9, 2026 City Council Meeting Minutes (Orangeville) (Orangeville City, 2026-07-09) primary government “The 1000 water shares is not part of the data center”
- August 13, 2026 City Council Minutes (Orangeville) (Orangeville City, 2026-08-13) primary government “waiting on a clean title to purchase the property”
- Orangeville City Planning and Zoning Commission minutes, July 16, 2026 (notice text) (Orangeville City Planning and Zoning, 2026-07-16) primary government “Everything needs to go through the attorneys from the City and Valar.”
- CVSSD Regular Meeting Minutes, February 19, 2026 (approved) (Castle Valley Special Service District, 2026-02-19) primary government
- Cleveland Town Council Meeting Approved Minutes for 3/12/2026 (notice text) (Cleveland Town, 2026-03-12) primary government
- Castle Dale City Council Meeting Minutes, March 12, 2026 (approved; scanned, read as page images) (Castle Dale City, 2026-03-12) primary government “The reactor requires minimal water—about 10 acre-feet for industrial use”
- Ferron City Council Minutes, April 15, 2026 (scanned, read as page images) (Ferron City, 2026-04-15) primary government “All testing of the reactor is done at “worse case scenario””
- Production issues discussed at Farm Bureau meeting (ETV News, 2026-05-01) news
- Emery County Business Chamber gets an up-close look at Valar Atomics' progress (Stephanie Olsen) (ETV News, 2026-08-24) news “completely removing the risk of a meltdown”
- Valar Atomics celebrates its footprint with community open house (Stephanie Olsen) (ETV News, 2026-02-27) news
- Community gets closer look at Valar Atomics during open house (Scottie Kraync) (ETV News, 2026-09-14) news “as we grow here in your backyard, in your community”
- Not A Nuclear Plant Just Testing a Small Nuclear Reactor (Julie Johansen) (ETV News, 2025-07-09) news “Not A Nuclear Plant Just Testing a Small Nuclear Reactor”
What Emery residents were offered, in order: a county 'Nuclear Industries' hearing on 17 June 2025, called after news reports, where the state lab director said transparency is imperative (gov-020); a town hall on 8 July 2025 that the county hosted at Valar's request (ETV; orig-045); a state board approval in Salt Lake City on 13 August 2025 at a 35-minute first meeting (gov-013); a county commission vote on 2 September 2025 issuing the building permit itself (gov-021); DOE's categorical exclusion of 22 April 2026, posted online later with no public comment period (csite-020, gov-029); a noticed hearing on 7 April 2026 on selling the lab-side parcel (loc-007, gov-022); open houses (February and September 2026) and frequent appearances at town councils (loc-027). Separately, state bodies listed the project, or a tour of it, on noticed agendas that also had public-comment periods: the Legislature's energy committee on 18 June 2025, whose minutes record public comment on the nuclear discussion (gov-040); the Utah Energy Council's 31 March 2026 agenda (gov-041); and the Energy Research Board's 12 August 2026 agenda, for a meeting at the lab with a members' tour of the lab and Valar listed afterwards (gov-042). What the record does not show: any public hearing or comment period on the reactor's safety, emergency plan or fuel plant (safe-001, safe-016, safe-031); any county land-use (conditional use) review of the reactor, since the county had no nuclear standards (loc-024); a state permit under the 2026 waste law (gov-017); a completed third-party fire plan review (loc-018); or, as of 29 September 2026, a hearing on Orangeville's new zone for Valar's land (loc-013). The March 2026 utility minutes record Valar connecting to the sewer before approval (loc-015). By design of the federal pilot program, local governments have no approval role over the reactor itself (gov-032); what they control is land, buildings, water, sewer and zoning, and those steps were taken quickly, some with little recorded review.
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (categorical exclusion B5.26) (U.S. Department of Energy, Office of Nuclear Energy, 2026-04-22) primary government
- PUBLIC HEARING NOTICE: Proposed Property Transaction of Parcel 04-0019-0030 between Emery County and Valar Atomics (Emery County (legal notice published in ETV News), 2026-03-25) primary government “Proposed Property Transaction of Parcel 04-0019-0030 between Emery County and Valar Atomics”
- Not A Nuclear Plant Just Testing a Small Nuclear Reactor (Julie Johansen) (ETV News, 2025-07-09) news “Not A Nuclear Plant Just Testing a Small Nuclear Reactor”
- Emery County Planning Commission minutes, August 12, 2026 (Emery County Planning and Zoning Commission, 2026-08-12) primary government
- Emery County Fire Protection SSD meeting minutes, February 17, 2026 (header misprints the year as 2025) (Emery County Fire Protection Special Service District, 2026-02-17) primary government “State agencies declined to perform plan review and recommended third-party review.”
- CVSSD Regular Meeting Minutes, March 19, 2026 (approved) (Castle Valley Special Service District, 2026-03-19) primary government “Valar tied into the county sewer system without prior authorization”
- Orangeville City Planning and Zoning Commission minutes, July 16, 2026 (notice text) (Orangeville City Planning and Zoning, 2026-07-16) primary government “Everything needs to go through the attorneys from the City and Valar.”
The Utah San Rafael Energy Lab's project page (a State of Utah site, read 2026-09-29) says Ward 250 achieved 'full-power fueled criticality' on June 18, 2026, describes it as a Generation IV helium-cooled, graphite-moderated HTGR, and says the design is meant to scale to a 5 MW version. DOE's release and ANS both describe June 18 as a zero-power criticality demonstration, and Valar's own Castle Country page says full power came 'days later'. The state page's wording therefore conflicts with the federal record; it also repeats the company-style claim that the fuel is 'impossible to melt', which is a design claim, not a demonstrated result.
- Valar Atomics | Utah San Rafael Energy Lab (Utah San Rafael Energy Lab (State of Utah)) primary government “the Ward 250 successfully achieved full-power fueled criticality at the lab”
- Department of Energy Celebrates Second Advanced Reactor Achieving Criticality (U.S. Department of Energy, 2026-06-18) primary government “successfully completed a zero-power fueled criticality demonstration”