Plans & Sites
Every site and plan, and promised vs delivered timelines.
What investors and the public were told: Contrary Research, itself an investor, published a November 2025 profile quoting an unnamed Valar investor who said Valar could produce about '$1 billion of revenue annually per 100 reactors' on a gigasite from synthetic-fuel sales, and $10 billion or more a year from a 1,000-reactor gigasite; Contrary adds that the company believes it can make synthetic fuels at prices matching or beating fossil fuels without carbon subsidies, while its own risk list calls synthetic-fuel economics and mass reactor production unproven (orig-024). Valar's homepage says its 'products create the cashflow' to drive manufacturing, and Sequoia's page says Valar 'sells power rather than reactors'. The state tax-credit file describes gigasites powering data centers, hydrogen and synthetic fuels (fund-017). What the record shows as of 29 Sept 2026: no revenue figure, customer contract or power-purchase agreement has been published by Valar or any buyer; the Series B post (Aug 2026) names investors, lenders and a 'collaboration' with NVIDIA, but no customer; the NVIDIA announcement of 1 July 2026 was, as reported by the Deseret News, a collaboration to 'explore' a 30 MW data center, with no money or timeline stated (orig-042); at the state board in July, a Valar executive said no one has yet sold power from an advanced reactor in America and that its near-term plan is premium 'behind-the-meter' customers (gov-033); Sacra, a research firm, says Valar 'needs an anchor customer'. DOE's legal basis for Ward 250 is that it does not produce commercial power (safe-030), and the Deseret News notes that the NRC must license Valar's reactor before it can generate power commercially, so Ward 250 is not a source of power sales. No hydrogen or synthetic fuel production is on record (orig-063). The public emphasis has shifted toward AI power (Series B post, NVIDIA event), though the homepage still leads with industrial power and hydrocarbon fuels (orig-063).
- Report: Valar Atomics Business Breakdown & Founding Story (Contrary Research (an investor in Valar), 2025-11-11) analysis “~$1 billion of revenue annually per 100 reactors deployed on a gigasite”
- Valar Atomics (homepage) (Valar Atomics) primary company “Our high volume, grid-independent products create the cashflow to drive manufacturing excellence and operational scale.”
- Announcing our $1B Series B Led By Sequoia (Isaiah Taylor) (Valar Atomics, 2026-08-04) primary company “a collaboration on a waterless 30 MW AI factory”
- New partnership touts nuclear-powered AI with minimal water use (Eva Terry, Deseret News) (KSL.com / Deseret News, 2026-07-06) news “announced a collaboration with Nvidia on Wednesday afternoon to explore the development”
- Valar Atomics funding, news & analysis (Sacra (research firm; partly paywalled)) analysis “Valar needs an anchor customer to validate its model in this segment.”
- GOED Public Board Materials, July 9, 2026: GOED Board Executive Summary, Valar Atomics Inc. (Board of the Governor's Office of Economic Development (Utah Public Notice Website), 2026-07-09) primary government “Incentives are site specific and subject to local incentive participation.”
- Valar Atomics (portfolio page) (Sequoia Capital) primary company “sells power rather than reactors”
Holds: DOE's July 2026 target and Valar's own October 2025 milestone table ('Initial Criticality 06/30/2026') were met when Ward 250 went critical on 18 June 2026 (orig-010); Valar's homepage promise to 'go live before America's 250th birthday on July 4th, 2026' is met for criticality. Partly: tech press in November 2025 carried the company's line that it was 'on track to demonstrate 100 kilowatts of thermal energy by July 4'; Valar says it reached full power within days, but DOE confirmed only zero-power criticality and no independent record of the power reached is public (orig-013). The same milestone table planned to submit the final safety analysis on 6 January 2026 for a 45-day review; POWER, citing Valar's posts, reports DOE approved it on 23 April 2026 (safe-006), later than planned but before criticality. Has not happened: the Philippine pilot (the February 2025 funding coverage reported a contract to pilot a test reactor and build two full-scale reactors there) had no reactor built as of the latest report read, April 2026 (fund-003, orig-064); the Emery gas-fired supercritical-CO2 heater Valar asked to finish by June 2026 has had only a design phase approved (gov-014). Too early to judge: 'commercial deployment by 2028' (July 2025 town hall, orig-045); 275 jobs and $1.3 billion invested in Emery (fund-017); fleet production of 'thousands of reactors' (Series B post). Changed: the plan described to residents as a 12-month test in a temporary facility became a permanent fuel-and-reactor base and a Carbon County campus (mine-019).
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev. 02, Appendix B: Table 7 Project Milestones (Valar Atomics (Public Documents), 2025-10) primary company “Initial Criticality 06/30/2026”
- Valar Atomics (homepage) (Valar Atomics) primary company “go live before America's 250th birthday on July 4th, 2026”
- Valar Atomics, a nuclear startup backed by Palmer Luckey and Palantir CTO, raises $130M to build thousands of advanced reactors (Daniel Levi) (Tech Startups, 2025-11-10) news “on track to demonstrate 100 kilowatts of thermal energy by July 4”
- Valar Atomics comes out of stealth with $19M and a pilot reactor site (Mike Butcher) (TechCrunch, 2025-02-20) news “build two full-scale reactors before the first integrated reactor comes online”
- Announcing our $1B Series B Led By Sequoia (Isaiah Taylor) (Valar Atomics, 2026-08-04) primary company “Thousands of reactors clustered strategically throughout the nation”
What holds (as of 29 September 2026): Valar built a 100 kWt test reactor in California and flew it to Emery County unfueled; DOE approved HALEU TRISO fuel for shipment to it from a federal site in Nevada (no public record states what fuel is loaded, disc-004); and DOE announced its zero-power criticality on 18 June 2026, ahead of the July 4 goal and of Valar's own 30 June target (plan-002, plan-004, plan-008, plan-014). A fuel lab stands beside it and is hiring for a pilot TRISO line (plan-015). What rests on the company's word: full power (plan-006; the only data is an unlabeled chart, plan-007), the electricity demonstration's output (ETV reported the reactor at 37% power, plan-010), and the fuel plant's future size (plan-015). Where Valar's own statements clash: full power on 'June 21' in the state's lease memo versus a 10 kWt output announced 22 June (plan-009); a 12-month demonstration in the approved papers versus a permanent base and 'largest' fuel maker in local talks (plan-003, plan-015); a July 4 date still in the future tense on the homepage (plan-019). Where a Valar document and a DOE document differ: the fuel is listed at 4.95% enrichment in Valar's safety agreement but as HALEU (under 20%) in DOE's shipping review (plan-014, disc-001). What is plan only: fleets and 'thousands of reactors per year' (plan-020), a Carbon County campus with no reactor count, size or date (plan-016), a 30 MW NVIDIA data center (plan-010), a turbine program (plan-018), 'one of Valar's first commercial projects' in Utah (plan-011). What has not happened: the Philippine reactor, the gas-fired test heater, fuel from Valar's own line, the Green River gigasite (plan-021). No power buyer, utility contract or military reactor contract is on the record (plan-012, plan-013). Every site on record is in plan-017; every physical movement of reactor and fuel in plan-025.
- Department of Energy Celebrates Second Advanced Reactor Achieving Criticality (U.S. Department of Energy, 2026-06-18) primary government
- Board of Trustees Meeting Materials, September 17, 2026 (SULA 2095-OBA staff memo) (Utah Trust Lands Administration, via Utah Public Notice Website, 2026-09-17) primary government
- Valar Atomics job board (public Greenhouse feed, 92 postings) (Valar Atomics (via Greenhouse), 2026-09-28) primary company
- Announcing our $1B Series B Led By Sequoia (Valar Atomics, 2026-08-04) primary company
Valar's unlisted, unfinished post dated 28 June 2026 says Ward 250 underwent 'extremely rigorous non-nuclear testing' at its headquarters in Hawthorne, California, before it reached Utah, with temperatures above 750 C and pressures over 6 MPa, thermal cycling and transients; the whole reactor system is six high-cube shipping containers. DOE's Fuel Line Pilot Program page lists the company as 'Valar Atomics Inc. (Hawthorne, California)'. On 29 September 2026 its public job board lists 71 of 92 openings in Torrance, California, including a graphite production lead for machining 'reactor components', CNC programmers, machinists, a welding lead for welds to 'nuclear-grade specifications', and eight turbomachinery roles; two posts name Hawthorne as a work base (a Torrance-listed commercial project manager to 'operate in both Hawthorne and Utah', and an Orangeville-listed people-operations director to be based in or relocate to Hawthorne), and a Utah post mentions travel to the 'Los Angeles headquarters'. The Carbon County claim notice carries a Torrance address (orig-036). In short: reactors and their parts are designed, machined and tested in the Los Angeles area; Utah is where they are fuelled and run. Non-nuclear heat tests are not limited by the nuclear safety limits in the NSDA (a 650 C limit versus 750 C goals, disc-002), so the 750 C figure is not a conflict with them.
- Ward 250 By the Numbers (unlisted, unfinished post, dated 28 June 2026) (Valar Atomics, 2026-06-28) primary company “The system experienced temps above 750c and pressures over 6MPa.”
- Energy Department Fuel Line Pilot Program (U.S. Department of Energy, Office of Nuclear Energy, 2026-02-12) primary government
- Valar Atomics job board (public Greenhouse feed, 92 postings) (Valar Atomics (via Greenhouse), 2026-09-28) primary company “Graphite is a specialized, abrasive material central to our reactor components”
- Graphite Production Lead (Torrance, California) (Valar Atomics (via Greenhouse), 2026-09-21) primary company
Built or operating: Ward 250 and its fuel lab at the San Rafael lab, Emery County (plan-002); the company's design, machining and test shops in Hawthorne/Torrance, California (plan-008). Used once: the NOVA test core at the National Criticality Experiments Research Center, Nevada, operated by Los Alamos in November 2025 (orig-008). Being acquired: the 112-acre Emery County parcel beside the lab (gov-022, loc-014). Lease approved: on 17 September 2026 the state trust-lands board approved a lease with purchase option for 480 acres of the section north of Wellington, with the other 160 acres to follow if the National Guard's lease there is moved (mine-011, plan-016); no record read shows the lease signed. Applied for: three Bureau of Land Management cases, all in the Price Field Office, all 'Pending' on 29 September 2026: UTUT106784007 'Green River Gigasite Small Modular Reactor/Data Center' (10,270.61 acres, filed 13 February 2026, which Valar told The Washington Sun it no longer pursues, mine-008), UTUT106801248 'Project Beehive Small Modular Reactor/Data Center' (case date 13 April 2026, no acreage shown), and UTUT106833224, a distribution-line case with no name (entered 23 July 2026). NPR reported on 30 September 2026, citing a Valar proposal to federal regulators that NPR reviewed, that Project Beehive would cover over 9,000 acres of BLM land near Price with data centers, some 456 small reactors of 25 megawatts of electricity each, a fuel facility and nuclear-waste storage, with the first reactors in 2028; BLM's Utah office told NPR it had received an application and was reviewing it for completeness. The proposal itself was not found in public records. No BLM rights-of-way case names Valar outside Utah, and its other public layers show no Valar claims, notices, leases or permits (mine-005, mine-030). Program: NRIC's August 2026 Launch Pad round includes Valar; POWER describes Ward 250 and the Valarin facility (gov-010). Abroad: Ward One in the Philippines, announced March 2025 and still unbuilt and without an approved site as of the last report read (orig-064). Valar says it looked at more than 20 states (ppl-006, loc-001); no site in another state was found in any public record read.
- BLM National MLRS Land Use Authorizations - Rights-of-Way (query: customer name contains 'VALAR', run 2026-09-29) (U.S. Bureau of Land Management, 2026-09-15) primary government “Green River Gigasite Small Modular Reactor/Data Center”
- Castle Country (Valar Atomics, 2026-09) primary company
- Board of Trustees Meeting slides, August 20, 2026 (SULA 2095 Other Business Arrangement) (Utah Trust Lands Administration, via Utah Public Notice Website, 2026-08-20) primary government “Selected by Valar Atomics following multi-state search”
- A startup wants to build a massive nuclear-powered data center on public land in Utah (NPR, 2026-09-30) news “some 456 small nuclear reactors”
Read on 29 September 2026, Valar's homepage says Valar is 'building hundreds of nuclear reactors on Valar Atomics gigasites' focused on hydrogen (by a sulfur-iodine cycle), data-center power, heavy industrial power and clean hydrocarbon fuels, and that it is partnering with DOE, the San Rafael lab and Utah 'to go live before America's 250th birthday on July 4th, 2026', a date now three months past, written as still ahead. Its technology page says the non-nuclear Ward Zero prototype is 'ready to go live'. The record: one test reactor has been built and operated (plan-002, plan-006); no gigasite has been approved anywhere (the Carbon lease holds land pending permits, plan-016; the Green River application was dropped, mine-008); no hydrogen or synthetic fuel has been produced (orig-063). 'Building hundreds' describes an aim, not work under way. The newer Castle Country page uses past tense for Ward 250 and says 'Ward 250 is step one'.
- The New Atomic Age | Valar Atomics (homepage) (Valar Atomics, 2026-09-29) primary company “we're building hundreds of nuclear reactors on Valar Atomics gigasites”
- The New Atomic Age | Valar Atomics (homepage) (Valar Atomics, 2026-09-29) primary company “to go live before America’s 250th birthday on July 4th, 2026”
- Technology | Valar Atomics (Valar Atomics, 2026-09-29) primary company “Its ready to go live.”
HELD: 'First Reactor online by July 4, 2026' (Valar's July 2025 deck to Emery County): DOE announced criticality on 18 June 2026 (orig-010), ahead of Valar's own 30 June target (plan-004). HELD AS A PLAN, UNCHECKED: '30 EFPD in 12 months' (deck) matches Valar's June 2026 draft (orig-035); no run log is public (plan-006, plan-007). CHANGED: 'in a temporary facility' (deck): the approved papers still plan to take Ward 250 down after about a year of running (plan-003), but what was built is a 55-foot modular reactor complex on engineered foundations with more than 4,000 cubic yards of concrete poured, beside a fuel plant (plan-002), on a site Valar now calls home and is expanding (plan-003, ppl-006); '40 employees for about 12 months' (July 2025) became a projection of 275 jobs and $1.3 billion for a state tax credit (loc-004, fund-017). LATE: DOE safety approvals came about two months behind Valar's own schedule, by the only report of their dates (plan-004). NOT DELIVERED: the Philippine reactor announced in March 2025 (orig-064); the gas-fired supercritical-CO2 test heater Valar wanted done by June 2026, approved for design only (plan-018); fuel from Valar's own line: Ward 250's fuel came from a federal site in Nevada (plan-014). DROPPED: the 10,270-acre Green River gigasite, per Valar, though BLM still lists it pending (plan-017, mine-008). NOT YET DUE, NO FILING: 'Commercial Deployment by 2028' (deck), the 30 MW NVIDIA data center (plan-010), 'hundreds of reactors' in Carbon and Emery (loc-001). CONFLICTING: the date of full power (plan-009) and, on paper, the fuel's enrichment (plan-014).
- Valar Atomics + SRERC in Emery County (slide deck, marked confidential, posted on the Utah Public Notice Website) (Valar Atomics, via Utah Public Notice Website, 2025-07-08) primary company “operates for 30EFPD, in 12 months in a temporary facility”
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02, Appendix B, Table 7 (Valar Atomics, 2025-10) primary company “Initial Criticality 06/30/2026”
- Rapid construction from local contractors at Valar Atomics (USREL press release, Energy Corner) (Utah San Rafael Energy Lab and Valar Atomics, via ETV News, 2026-01-23) primary government “more than 4,000 cubic yards of concrete to date for the foundations”
- Utah Energy Research Board Meeting Minutes, February 11, 2026 (Utah Energy Research Board, via Utah Public Notice Website, 2026-02-11) primary government
- BLM National MLRS Land Use Authorizations - Rights-of-Way (query: customer name contains 'VALAR', run 2026-09-29) (U.S. Bureau of Land Management, 2026-09-15) primary government
DOE named Valar on 30 September 2025 in 'the second round of conditional selections' for its Fuel Line Pilot Program, 'to support TRISO fuel fabrication for the Ward250 reactor deployment'; the program uses DOE authorization for fuel lines. Valar's QA program covers a 'Valarin Fuel Fabrication Facility' at the lab, based on German HOBEG methods and designed to stay below DOE Hazard Category 3 ('<HC3'; orig-038); DOE-STD-1271 bars adding nuclear material above Hazard Category 3 levels to a facility until the readiness review and startup approval are complete; a fuel line kept below that level would not reach that gate, and no record read says what review applies instead. DOE's categorical exclusion says the Ward 250 facility 'comprises the Reactor Complex and Fuel Laboratory', and Valar's QA program calls the Ward250 Fuel Laboratory a TRISO fuel manufacturing facility, but the CX's analysis does not mention fuel fabrication. Valar job postings open on 29 September 2026 seek engineers in Orangeville to 'install, troubleshoot, and optimize pilot scale uranium processing equipment' on a TRISO line (a fluidized-bed chemical vapor deposition coater; one posting asks for experience with wet chemistry or high-temperature processing), building on 'completed HAZOPs and existing safety analyses', a Nuclear Operations Manager to oversee 'both the reactor plant and the pilot TRISO fuel fabrication facility', and a material control and accounting specialist for special nuclear material 'at Valar Atomics TRISO manufacturing facilities'. DOE's selection release says each company bears all costs of building, operating and decommissioning its fuel facility. By comparison, Oklo announced in November 2025 that DOE's Idaho office had approved an NSDA for its fuel fabrication facility, the first under the fuel-line program. No NSDA, safety analysis, DOE authorization or state license for Valar's fuel line was found as of 29 September 2026. The Carbon County plan also includes fuel manufacturing (csite-007). The quality program gives no uranium inventory, enrichment or threshold for its <HC3 claim, and the safety agreement never mentions the fuel facility (it categorizes only the reactor, as Hazard Category 2), so the claim cannot be checked from Valar's public papers.
- Energy Department Selects Four Companies for Advanced Nuclear Fuel Line Pilot Projects (U.S. Department of Energy, 2025-09-30) primary government “To support TRISO fuel fabrication for the Ward250 reactor deployment”
- Ward250 San Rafael Facility Quality Assurance Program Description, No. 100474, Rev 02 (status: Approved) (Valar Atomics, 2025-10) primary company “ensures <HC3 categorization through multiple layers of inherent safety”
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (categorical exclusion B5.26) (U.S. Department of Energy, Office of Nuclear Energy (Idaho), 2026-04-22) primary government “The Ward250 facility comprises the Reactor Complex and Fuel Laboratory”
- Valar Atomics job board (92 open postings, public Greenhouse feed), read 2026-09-29 (Valar Atomics, 2026-09-29) primary company “install, troubleshoot, and optimize pilot scale uranium processing equipment”
- DOE-STD-1271-2025, Authorization Pathway for Nuclear Facilities (August 2025; DOE standard, copy posted by the Nuclear Innovation Alliance) (U.S. Department of Energy, Office of Nuclear Energy, 2025-08) primary government
- Ward250 San Rafael Facility Quality Assurance Program Description, No. 100474, Rev 02 (status: Approved) (Valar Atomics, 2025-10) primary company “The Ward250 Fuel Laboratory represents a state-of-the-art TRISO fuel manufacturing facility”
- Oklo Announces U.S. Department of Energy Approval for Nuclear Safety Design Agreement of Aurora Fuel Fabrication Facility (Oklo Inc. (Business Wire), 2025-11-11) primary company “has approved the Nuclear Safety Design Agreement (NSDA) for the Aurora Fuel Fabrication Facility”
Valar's public job board (Greenhouse, read 29 September 2026; postings updated 28 September) lists 92 openings: 71 in Torrance, California and 21 in Orangeville, Utah, and none in Carbon County, Price or Wellington. The Orangeville posts include plant operators, nuclear operations engineer and manager, instrumentation and electrical technicians, a site environmental health and safety specialist, a construction quality inspector, a development and construction finance director, and a Material Control and Accounting Specialist, whose post says the job leads the safeguards program for special nuclear material at Valar's TRISO manufacturing facilities under DOE and NRC requirements. Two fuel posts (a TRISO chemical plant process engineer, posted 16 July, and a TRISO chemical vapor deposition engineer, posted 31 July 2026) describe work to 'install, troubleshoot, and optimize pilot scale uranium processing equipment' in Orangeville; the second calls it a manufacturing 'pilot line' and says the engineer will build on 'completed HAZOPs and existing safety analyses' (a HAZOP is a structured hazard review) as 'the process transitions into production'. Set beside the record: in June 2026 Valar told Orangeville the fuel building would make it the largest US maker of this fuel once completed (loc-016); the job posts describe a pilot stage now; no DOE authorization for the fuel line was found in the public record (safe-031); and the local job figures in loc-004 cannot be matched to a payroll. Job boards change daily; these counts are as of 29 September 2026.
- Valar Atomics job board (Greenhouse public board API: 92 postings with locations and descriptions) (Valar Atomics) primary company “optimize pilot scale uranium processing equipment”
- Material Control and Accounting Specialist (Orangeville, Utah), Valar Atomics job posting (Valar Atomics, 2026-07-22) primary company
- Chemical Vapor Deposition Engineer (TRISO) (Orangeville, Utah), Valar Atomics job posting (Valar Atomics, 2026-07-31) primary company
Valar's public job board (read 29 September 2026; 92 openings, 86 first posted since June 2026) adds detail to loc-019. Torrance-listed roles (71): instrumentation and controls (19), eight 'Power Conversion' turbomachinery roles for a planned 'secondary loop Brayton cycle' (a gas turbine driven by reactor heat) with 'a purpose-built test facility program', manufacturing, machine and weld shops, graphite production, supply chain, licensing and legal. Orangeville roles (21): site operations (a Nuclear Operations Manager, a Nuclear Operations Engineer and Plant Operators who may work at 'the reactor plant or the pilot fuel fabrication facility'), fuels and materials (TRISO process and coating engineers, a nuclear material accountant), controls, QA, EH&S, HR, and a Development and Construction Finance Director whose job is cost tracking 'across active projects' and processes that 'scale across multiple construction sites'. A Project Manager, Commercial Projects (Torrance, 'operate in both Hawthorne and Utah') will 'lead development execution for one of Valar's first commercial projects' from site development to investment decision, asks applicants for experience on projects costing '$1B or more' (the post does not give this project's own cost), and will serve as a senior project representative in Utah with government and community; the post names no site. A Director of Licensing will run 'multiple concurrent licensing campaigns' across DOE and NRC pathways (safe-032). No posting mentions Carbon County, Wellington, Green River or any named future site, and none is located in Carbon County. The Power Conversion post says Valar's HTGR 'power conversion system will be built around' this turbine cycle, in the future tense; Ward 250's July electricity demonstration used a thermoelectric generator, not a turbine (ETV, 1 July; plan-010).
- Valar Atomics job board (public Greenhouse feed, 92 postings) (Valar Atomics (via Greenhouse), 2026-09-28) primary company “secondary loop Brayton cycle”
- Project Manager, Commercial Projects (Torrance, California) (Valar Atomics (via Greenhouse), 2026-05-17) primary company “lead development execution for one of Valar’s first commercial projects”
- Development and Construction Finance Director (Orangeville, Utah) (Valar Atomics (via Greenhouse), 2026-07-14) primary company “scale across multiple construction sites”
- Director of Licensing (Torrance, California) (Valar Atomics (via Greenhouse), 2026-08-11) primary company “multiple concurrent licensing campaigns”
- Director Instrumentation, Control, and Electrical - Power Conversion (Torrance, California) (Valar Atomics (via Greenhouse), 2026-06-30) primary company “paired with development generator sets and a purpose-built test facility program”
- Emery County takes center stage as Valar and Nvidia power historic breakthrough (ETV News (Kevin Butler), 2026-07-01) news “converted into electricity through a thermoelectric generator”
Utah Code 73-3-6 requires the State Engineer to publish notice of a water-right application once a week for two successive weeks in a newspaper of general circulation in the county of the source and of use (and on the state's legal-notice site), and the notices set a deadline for written protests. ETV News, delivered to every home in Carbon and Emery, carries these 'NOTICE TO WATER USERS' notices. Its search feed returned 159 of them, from June 2018 to 23 September 2026, 61 published between 11 October 2023 and 23 September 2026 (26 with Emery County applications); all were read. None names Valar Atomics or a nuclear use, and none concerns Section 16, T14S R11E (the Wellington lease) or industrial water near Orangeville for Valar. The Carbon applications are mostly irrigation and canal-company changes along the Price River; the Emery ones include coal, power-plant and ranch uses, and a 23 September 2026 notice lists a Trust Lands gravel-operation well 22 miles east of Castle Dale (protests due 20 October). This fits what Valar says so far: its current water comes through Orangeville's system with shares turned in to the city (loc-017), and no record read shows a state application for that; the 1,000 additional shares are 'in the discussion phase'. It also means no public protest window has yet opened on any Valar water use. The Trust Lands memo says the Wellington site must buy existing rights and move them by a publicly advertised change application (mine-015, mine-017). ETV's search may not return every notice, and the Emery County Progress, which may also carry them, did not answer (sources_not_read); the state's legal-notice website was not searched.
- Utah Code 73-3-6: Publication of notice of application (amended 2024) (Utah State Legislature, 2024-05-01) primary government “once a week for a period of two successive weeks in a newspaper”
- ETV News public notices: 'NOTICE TO WATER USERS' from the Utah State Engineer (search feed pages 1-15: 159 notices, June 2018 to 23 Sept 2026; 61 since 11 Oct 2023) (Utah Division of Water Rights (legal notices published in ETV News)) primary government
- NOTICE TO WATER USERS (Emery County applications; protests due Oct. 20, 2026) (Utah Division of Water Rights (legal notice published in ETV News), 2026-09-23) primary government
Under 'Fuel Feedstock Delivery & Handling', the memorandum says high-assay low-enriched uranium (HALEU), 'low-enriched uranium plus' (LEU+) or low-enriched uranium (LEU) may be delivered to the site in certified special-nuclear-material containers under NRC, DOT and DOE rules, and that the feedstock 'would then be manufactured into TRISO fuel pellets' for the reactors on site. The staff slides list 'Manufacture TRISO fuel' as a project purpose. The memo does not say which enrichment Valar would use, how much uranium would be kept on site, or which agency would license the fuel plant. Valar's own documents already disagree on whether Ward 250's fuel is 4.95% LEU or HALEU (disc-001, orig-040); the Carbon memo leaves all three grades open.
- 09.17.2026 TLA Board Packet (Item 10A: SULA 2095-OBA Board of Trustees Memorandum, Carbon County letter, lease map) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-09-17) primary government “That uranium feedstock would then be manufactured into TRISO fuel pellets”
- TLA Board of Trustees meeting presentation, August 20, 2026 (Item 9A slides: SULA 2095 OBA) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-08-20) primary government “Manufacture TRISO fuel”
- What is High-Assay Low-Enriched Uranium (HALEU)? (U.S. Department of Energy, Office of Nuclear Energy, 2024-12-03) primary government “HALEU is enriched between 5% and 20% in U-235”
- TRISO Particles: The Most Robust Nuclear Fuel on Earth (U.S. Department of Energy, Office of Nuclear Energy, 2019-07-09) primary government “They can be fabricated into cylindrical pellets or billiard ball-sized spheres”
The Wellington section is held for the Public Schools Trust (csite-002). Trust Lands says 'nearly all' the revenue it earns is deposited in the Permanent School Fund, and that each year the fund's gains, interest and dividends are distributed to every public school in Utah by enrollment through the School LAND Trust program. So the $400,000 bonus and rent from Valar (mine-011; ETV reported about $35 million over 50 years) go into that statewide fund, not to Carbon County schools as such; a Carbon school gets its enrollment share like any other. Property taxes on any buildings would go to local taxing entities, including the Carbon County School District, subject to any incentive (none found for Carbon, csite-029). The school beneficiaries' advocate supported the lease (csite-028). Other school and college ties found: Valar was among the donors the Emery High National Honor Society thanked for its 17 August back-to-school event (ETV, 19 Aug 2026); a Southern Utah University engineering student interned at Valar's Orangeville site (SUU release, September 2026); Valar presented to USU Eastern's Eastern Leaders Academy (March 2026, loc-022). No agreement between Valar and the Emery County School District appears in its board's agendas and minutes posted on the state notice site from April to September 2026 (read; the 8 April minutes mention Valar only as one of the local businesses at a school's career day), and the Carbon School District board's page there listed no notices when read on 29 September 2026.
- From Trust Lands to Your School (Utah Trust Lands Administration) primary government “Nearly all of the revenue Trust Lands generates is deposited into the Permanent School Fund.”
- Valar Atomics secures land agreement for Carbon County project (Stephanie Olsen) (ETV News, 2026-09-18) news
- Community comes together for Emery High NHS Back-to-School event (ETV News, 2026-08-19) news “including Valar Atomics”
- SUU mechanical engineering student transforms classroom knowledge into real-world impact at Valar Atomics (SUU press release) (ETV News, 2026-09-19) primary government
- Emery County School District Board of Education notices (agendas and minutes, April to September 2026) (Utah Public Notice Website) primary government
- Carbon County School District Board of Education (public body page; no notices listed) (Utah Public Notice Website) primary government
- Emery County School District Board of Education minutes, April 8, 2026 (Emery County School District, 2026-04-08) primary government “Career Day highlighting local businesses (TSJ construction, Valor Atomics, and helicopter pilot)”
The state's lease record (staff memo and slides for the Trust Lands board, August and September 2026) describes the purpose of the Wellington-area lease as 'an integrated nuclear energy, advanced manufacturing, critical mineral refining, and data center computing campus': developing, manufacturing and operating helium-cooled high-temperature reactors to generate electrical power, TRISO fuel manufacturing, component manufacturing, concrete batch plants, training facilities, hydrogen and synthetic fuels, data centers, water desalination and steel. The memo says development is planned 'across multiple phases progressing from manufacturing construction to reactor fleet deployment' and that the campus 'will take many years to build'; rent is a low 'Development Phase' rate for years 1 to 5 (mine-011). The slides say Valar wants to lease the land 'while they complete site permitting'. Nowhere in the memo or slides is there a number of reactors, a power output, a construction date or a job count. The only scale figures on record come from speech: ETV reported the CEO hoping for hundreds of reactors in Carbon and Emery (10 September; loc-001). Carbon County site facts (location, easements, notice, permits, water) are in carbon_site.json (csite-001 to csite-032) and mining.json (mine-010 to mine-017); the RW 453 claim notice is fld-002.
- Board of Trustees Meeting Materials, September 17, 2026 (SULA 2095-OBA staff memo) (Utah Trust Lands Administration, via Utah Public Notice Website, 2026-09-17) primary government “progressing from manufacturing construction to reactor fleet deployment”
- Board of Trustees Meeting slides, August 20, 2026 (SULA 2095 Other Business Arrangement) (Utah Trust Lands Administration, via Utah Public Notice Website, 2026-08-20) primary government “Valar Atomics desires to lease the property while they complete site permitting”
ETV News (14 Sept 2026) reported Valar's public open house at its Orangeville site on Thursday, 10 September 2026, for Carbon and Emery residents: small-group tours of the Ward 250 building, food and entertainment. As ETV reported it, head of projects Max Ukropina said Valar has hired dozens of community members and wants to hire more; founder and CEO Isaiah Taylor said Valar chose Emery and Carbon counties after considering more than 22 states, and that Valar hopes to build hundreds of reactors in Carbon and Emery counties (ETV's paraphrase, not a quote); he was quoted hoping residents will come to work for Valar 'as we grow here in your backyard'. State Sen. David Hinkins spoke of industry easing residents' property taxes. The report does not mention the Wellington trust-land lease the Trust Lands board approved seven days later (mine-011; ETV, 18 Sept), any Carbon County site, a fuel factory or a timeline. When Valar's Harry Hansen (spelled Hanson in that report) announced the open house to the Carbon County Commission on 2 September, he called it a chance to 'come check out what’s going on here in Orangeville' and said Valar planned a town hall specifically for Carbon County residents in late September or early October, date not yet set (ETV, 4 Sept). Whether the Carbon site came up in the small-group tours is not in any record read.
- Community gets closer look at Valar Atomics during open house (Scottie Kraync) (ETV News, 2026-09-14) news “as we grow here in your backyard, in your community”
- Commission honors Spectrum Paint owner and announces Valar Atomics open house (Stephanie Olsen) (ETV News, 2026-09-04) news “come check out what’s going on here in Orangeville”
- Valar Atomics secures land agreement for Carbon County project (Stephanie Olsen) (ETV News, 2026-09-18) news “located about six miles north of Wellington and six miles east of Price”
Valar's Castle Country page says Ward 250 flew to Utah on three C-17s 'in partnership with the Department of Energy and the Department of War' (Operation Windlord, 15 February 2026; orig-030, orig-027). No Defense Department contract with Valar is on the federal spending record (gov-027), and who paid for the flights is reported, not documented (fund-013). The Defense Innovation Unit's list of companies eligible for its Advanced Nuclear Power for Installations program (10 April 2025) names eight firms (Antares, BWXT, General Atomics, Kairos, Oklo, Radiant, Westinghouse, X-energy), not Valar. The Army's Janus program (26 August 2026) picked five vendors for five bases, up to $2.2 billion combined (Antares, BWXT, General Atomics, Radiant, Westinghouse), not Valar. Valar's job board lists military technical experience as a qualification or preference in several posts, and one post asks for the ability to obtain any required DOE or NRC access or clearance (plan-011), but no military customer, contract or site for a Valar reactor was found as of 29 September 2026.
- Army reaches agreement with private industry for nuclear micro-reactors (U.S. Army, 2026-08-26) primary government “the Janus Program has selected five nuclear energy vendors, and five initial locations”
- DOD selects eligible companies for the Advanced Nuclear Power for Installations Program (Defense Innovation Unit, 2025-04-10) primary government “Selected companies for the ANPI program include:”
- Castle Country (Valar Atomics, 2026-09) primary company “in partnership with the Department of Energy and the Department of War”
DOE's environmental determination for Ward 250 (signed 22 April 2026) describes the Ward250 facility as a 'Reactor Complex and Fuel Laboratory' inside a security fence of about 2 acres, within the state-run Utah San Rafael Energy Research Center, a 20.6-acre site near Orangeville; the reactor complex is about 55 feet high and made of modular buildings on engineered foundations tied only to existing lab utilities. A joint update from the state lab and Valar, run in ETV News on 23 January 2026, said local contractors had moved and crushed about 40,000 cubic yards of material and poured over 4,000 cubic yards of concrete for foundations of the Ward 250 test reactor and a fuel fabrication facility. ETV (24 August 2026), reporting a business-chamber tour on 19 August, said the reactor was now enclosed in cement bricks that hide it from view, and described an operations center and exhaust equipment designed to detect radioactive particles and shut the exhaust off. Valar's open job posts (29 September 2026) staff both 'the reactor plant' and a 'pilot TRISO fuel fabrication facility' in Orangeville. Other things at or beside the lab are recorded elsewhere: Valar's proposed 10 MW gas-fired test heater, approved only for design (gov-014); other nuclear companies courting the lab (gov-031); the 112-acre county parcel next door that Valar is buying (gov-022, loc-014); and the unauthorized sewer tie-in (loc-015).
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (U.S. Department of Energy, Office of Nuclear Energy, 2026-04-22) primary government “comprises the Reactor Complex and Fuel Laboratory enclosed within a security-fenced area”
- Rapid construction from local contractors at Valar Atomics (USREL press release, Energy Corner) (Utah San Rafael Energy Lab and Valar Atomics, via ETV News, 2026-01-23) primary government “The site will house Valar’s fuel fabrication facility and the WARD 250 test reactor.”
- Emery County Business Chamber gets an up-close look at Valar Atomics progress (ETV News (Stephanie Olsen), 2026-08-24) news
- Valar Atomics job board (public Greenhouse feed, 92 postings) (Valar Atomics (via Greenhouse), 2026-09-28) primary company “Operators may be assigned to either the reactor plant or the pilot fuel fabrication facility”
The Utah Trust Lands Administration posted a notice that it had received an application, from an applicant it did not name, for Section 16, Township 14 South, Range 11 East, SLB&M, about 640 acres near Wellington in Carbon County, and invited competing bids to lease, buy or exchange it by August 7, 2026. The board's August 20, 2026 agenda lists a discussion item on a Special Use Lease Agreement (SULA 2095 OBA) for 640 acres in Carbon County with Valar Atomics. This was the first primary record found of Valar seeking a site outside the Emery County test lab. Later records settle what this fact first left open: the board memo gives Section 16 as the lease (csite-002), and the board approved the arrangement on September 17, 2026 (mine-011, csite-001). The notice named neither Valar nor a nuclear use (csite-005, mine-012).
- Board of Trustees Meeting Agenda Thursday, August 20, 2026, at 9:00 a.m. (Utah Trust Lands Administration (Utah Public Notice Website), 2026-08-20) primary government “located in Carbon County, Utah (640 +/- acres) with Valar Atomics”
- Public Notice - Business Opportunity - Carbon County (Utah Trust Lands Administration) primary government “has received an application on the following property near Wellington in Carbon County”
Carbon County Commission minutes, 19 August 2026, item 9 (the item right after the 'Valor Atomics presentation'): commissioners approved, contingent on Emery County's approval, on Commissioner Haddock's motion seconded by Commissioner Jensen (the motion carried), a joint $60,000 consulting agreement with John Cox of Utah Public Affairs Consulting 'to identify and secure economic development opportunities' across coal, natural gas, nuclear and advanced manufacturing, split $30,000 each with Emery County; Carbon's half comes from unused economic-development consulting funds; the commission approved it contingent on Emery's approval. Emery County's 1 September minutes approve 2027 rural county grant projects that include $30,000 (printed '$30,00') for a 'potential Economic Development Consultant' (the grant money comes from the state's rural county grants); one commissioner said he would rather Emery had its own consultant, not one shared with Carbon; on 15 September the commission 'agreed to move ahead with a possible partnership' with Carbon to hire the consultant (ETV). No record read shows the signed agreement, the contract text, or whether the consultant has any tie to Valar or other nuclear developers. On the same 19 August item 8, the minutes record Valar saying it 'relocated to the region from California two years ago'; Valar's job board still lists 71 of its 92 openings in Torrance, California (loc-019), and its Carbon claim notice gives a Torrance address (orig-036).
- Aug 19, 2026 Commission Meeting Minutes (Carbon County Board of Commissioners; scanned, read as page images) (Carbon County Commission, 2026-08-19) primary government “They relocated to the region from California two years ago”
- Carbon County Commission Meeting, August 19, 2026 (notice and agenda; items 8 and 9) (Carbon County Commission, 2026-08-19) primary government
- Emery County Commission Meeting Minutes, September 1, 2026 (CM09012026), item on 2027 Rural County Grant projects (Emery County Commission, 2026-09-01) primary government
- Emery County delays solar decision, pauses new conditional use permits (ETV News, 2026-09-21) news
ETV News (24 Aug 2026) reported the Emery County Business Chamber's 'Lunch and Learn' tour of Valar's site on 19 August 2026. The report says the reactor is now enclosed in cement block walls; that the site has exhaust equipment designed to detect radioactive particles and shut off the exhaust if there is any potential for outside contamination; and that the helium-cooled design lets the reactor shut down within seconds, 'completely removing the risk of a meltdown'. That last sentence is the paper's narration of what the group learned on the company's tour and is not attributed to a named speaker, so it cannot be treated as Valar's exact words. The report also says Valar discussed 'potential plans' to produce reactors for industrial businesses so heavy power users can move off the grid, citing the Price firm Intermountain Electronics 'strictly as an example'. Set beside the record: Valar's own Nuclear Safety Design Agreement (October 2025 draft) analyses a bounding 'maximum hypothetical accident' that assumes TRISO fuel particle failures beyond demonstrated limits and a release of radioactive material, and estimates the resulting dose at the site boundary (safe-013, loc-035); the Union of Concerned Scientists calls TRISO 'far from meltdown-proof' (safe-025). No public monitoring data for the exhaust system has been published (safe-024). Supplying reactors to private businesses would be commercial use, which the DOE research pathway Ward 250 runs under does not cover; that would need separate licensing (safe-030).
- Emery County Business Chamber gets an up-close look at Valar Atomics' progress (Stephanie Olsen) (ETV News, 2026-08-24) news “completely removing the risk of a meltdown”
- Ward250 Nuclear Safety Design Agreement (Document 100403, Revision 02, marked draft, October 2025) (Valar Atomics, 2025-10) primary company “TRISO fuel particle failures exceeding demonstrated limits”
At Emery County's 7 April 2026 hearing on the land sale, residents raised truck traffic along Highway 29, and the state lab director told the hearing that the land was zoned as an industrial park for exactly this kind of expansion (ETV, 9 April). Earlier, on 19 February 2026, an Orangeville councilman asked for opinions on whether the city wants Valar to haul its 'nuclear parts' through town or to ask that they go around on the highway (minutes). On 7 July 2026 Emery County approved a memorandum of understanding with Orangeville for three speed-limit signs, contingent on partnerships and funding (ETV, 8 July), and on 13 August the Orangeville council approved its MOU with the county and the Utah Highway Patrol (minutes), city officials saying the signs had become more urgent with increased traffic from mining and Valar (ETV, 20 Aug). The council also noted coal trucks from the Fossil Rock mine, now in production, on Coal Haul Road, the road that serves the lab. No traffic study for Valar's site or the planned expansion was found in any record read.
- Emery Commission public hearing receives comments on the sale of property to Valar Atomics (ETV News, 2026-04-09) news
- Growth, industry and community issues highlight Orangeville council meeting (Kevin Butler) (ETV News, 2026-08-20) news
- Emery County Commission honors Ellertson, approves rodeo team donations (ETV News, 2026-07-08) news
- February 19, 2026 City Council Meeting Minutes (Orangeville; notice text) (Orangeville City, 2026-02-19) primary government “wants Valor to haul their nuclear parts through town”
- August 13, 2026 City Council Minutes (Orangeville) (Orangeville City, 2026-08-13) primary government “MOU with Emery County and UHP for Speed Limit Signs”
(1) The Series B post says that 'just a week later' than the June 18 criticality, Ward 250 generated electricity to power an NVIDIA Blackwell. Valar's own Castle Country page and Deseret News date that event July 1, 2026, thirteen days after criticality (orig-013, orig-042), and TechCrunch, attributing it to the company, wrote that it happened in June. A small point, but the company's own pages disagree. (2) The post says its power will be generated in reactors with no burden on the water supply. The Trust Lands memo says the helium-cooled reactors need no cooling water (mine-017), which supports the reactor part; separately Valar is seeking up to 1,000 water shares in Emery County for future development (mine-042) and would have to buy water rights for its Carbon County campus (mine-017). The claim holds for reactor cooling; the wider campus needs water. (3) The post says Valar will not rely on outside suppliers for fuel and will make it in labs beside its reactors. So far, DOE's shipping review cleared HALEU fuel for Ward 250 to be shipped from Los Alamos's criticality center in Nevada (safe-010); DOE's fuel-line selection of Valar is conditional (orig-032); and no DOE authorization of the Valarin fuel line is public (safe-031). A plan, not the current practice. (4) 'Ward 250's operability has been proven': DOE confirmed criticality (orig-010); the power reached and the run history are not public (orig-013, safe-007).
- Announcing our $1B Series B Led By Sequoia (Isaiah Taylor) (Valar Atomics, 2026-08-04) primary company “Just a week later, Ward 250 set another record”
- Castle Country | Valar Atomics (Valar Atomics) primary company “on July 1 it generated electricity, live in front of an audience”
- Sequoia's Shaun Maguire leads $1B round for nuclear startup Valar Atomics (TechCrunch, 2026-08-03) news “In June, it demonstrated its Ward 250 reactor successfully powering an Nvidia Blackwell system”
- Announcing our $1B Series B Led By Sequoia (Isaiah Taylor) (Valar Atomics, 2026-08-04) primary company “generated in reactors with no burden on our water supply”
- Announcing our $1B Series B Led By Sequoia (Isaiah Taylor) (Valar Atomics, 2026-08-04) primary company “Valar will not rely on outside suppliers for the fuel needed to deploy and operate.”
- Safety Evaluation Report, Letter Amendment of Certificate of Compliance No. 9979 for the Model 9979 Package, Docket 26-35-9979 (U.S. Department of Energy, Packaging Certification Program, 2026-05-20) primary government “fuel compacts from the National Criticality Experiments Research Center in Nevada”
Valar's Series B post (4 August 2026) says the money lets it move from demonstrating one integrated reactor to 'producing fleets of them en masse', with each reactor shortening the next until Valar produces 'tens, then hundreds, then thousands of reactors per year' in factories 'filled wall to wall' with small modular reactors, and that it will make its own fuel beside its reactors. It names no next reactor design or size, no factory site, no customer and no date. The concrete signs of the next step are elsewhere: a manager for 'one of Valar's first commercial projects' in Utah on the job board (plan-011), a turbine program (plan-018), the Carbon lease (plan-016), a state tax-credit application projecting $1.3 billion of investment and 275 jobs in Emery County (fund-017), and a promise to Emery County in July 2025 of 'Commercial Deployment by 2028' (orig-045). DOE's July 2026 fact sheet, in its paragraph on Antares's Mark-0, says that demonstration set a baseline for 'subsequent reactors' to produce electricity 'in 2027 and the following years'; it gives no electricity date for Valar. Any reactor that sells power would need an NRC license under DOE's own terms (safe-030, csite-010); no NRC application or pre-application from Valar has been found (an open question in government.json; safe-032).
- Announcing our $1B Series B Led By Sequoia (Valar Atomics, 2026-08-04) primary company “tens, then hundreds, then thousands of reactors per year”
- FACT SHEET: The Golden Era of American Nuclear Energy Has Arrived (U.S. Department of Energy, 2026-07-25) primary government “to produce electricity in 2027 and the following years”
- Valar Atomics + SRERC in Emery County (slide deck, marked confidential, posted on the Utah Public Notice Website) (Valar Atomics, via Utah Public Notice Website, 2025-07-08) primary company “Commercial Deployment by 2028”
The memorandum of understanding signed on 27 July 2026 by Energy Secretary Chris Wright and Gov. Spencer Cox to establish a Nuclear Lifecycle Innovation Campus (NLIC) in Utah (posted by OED; read from its page images) names, as the 'Historical Foundation' of the partnership, 'the successful permitting, development, and testing of Valar Atomics' Ward 250' test reactor at the San Rafael lab. It calls for a later Host Agreement that 'shall address the acceptance and management of out-of-state used nuclear fuel, spent nuclear fuel, high-level radioactive waste, and greater than class C radioactive waste'; says permanent disposal facilities at the campus would be NRC-licensed, with the state never the licensee; has DOE provide regulatory oversight under 10 CFR 830 for non-NRC activities; says decisions on public disclosure under FOIA or GRAMA 'will be made following consultation between the Parties'; and lets either side end it if no Host Agreement is signed by 30 September 2026. It also commits both sides to 'robust community engagement and transparency' (3.1), runs for 30 years, and extends federal nuclear-accident indemnity (AEA section 170d) to the state, campus tenants and contractors. The MOU names no site; the governor's March 2026 release named Tooele County as the candidate host (gov-015 sources), and no record read places the campus in Carbon or Emery County. Set beside the record: the only permitting on file for Ward 250 is DOE's (safe-001, safe-007); no state permit for it was found (gov-017).
- Memorandum of Understanding Between the Department of Energy and the State of Utah Concerning the Establishment of a Nuclear Lifecycle Innovation Campus in the State of Utah (signed July 27, 2026) (U.S. Department of Energy and State of Utah (posted by Utah Office of Energy Development), 2026-07-27) primary government “the successful permitting, development, and testing of Valar Atomics’ Ward 250”
- Utah and Tooele County explore response to U.S. Department of Energy opportunity for Nuclear Lifecycle Innovation Campus (Office of the Governor of Utah, 2026-03-27) primary government
Orangeville City records: on 11 December 2025 the mayor told the council he would like to see Valar annexed into the city (minutes; he had first raised annexation in September 2025). On 17 March 2026 a special service district asked Emery County that Valar's parcel be annexed into Orangeville (gov-022), and on 19 May the county sent annexation notices (gov-022); on 21 May the Castle Valley Special Service District board reviewed pending annexations including property near Orangeville 'that may be developed by Valor', noting recent state law changes that allow a streamlined annexation by landowner petition (minutes). The city's 11 June minutes record staff 'working on annexation requirements' and the mayor meeting Valar about annexation. On 9 July council minutes record staff 'working on Nuclear Energy Ordinance', and that the city had sent a draft of 'the nuclear energy industry ordinance' being coded to allow Valar to be annexed; the annexation process was to begin at the August meeting with a Valar representative present. The Planning and Zoning Commission's 16 July minutes record an agenda item 'Ordinance I-2 Advanced Energy and Manufacturing District', with Valar's Jess Housekeeper present as its representative: 'There needs to be a plan for an ordinance for this company and future companies', he 'explained the wants and needs for this company', a public meeting would need to be posted by 30 July in draft form, and 'Everything needs to go through the attorneys from the City and Valar.' The commission's later agendas (11 August, 8 September, 17 September work meeting) do not list the I-2 ordinance, and no public hearing on it was found in the council's or the planning commission's notices through the 8 October 2026 council notice (a hearing on a cemetery fee). On 13 August the mayor said annexation could begin once the sale is final (loc-014). The planning commission's 8 September agenda and the council's 10 September agenda list an 'Updated Annexation Policy', the council's item 'to reflect legislative changes'. At the county, commissioners said on 21 July that annexation would put the land under Orangeville's authority for services and future land-use decisions (ETV, 28 July).
- September 11, 2025 City Council Minutes (Orangeville; notice text) (Orangeville City, 2025-09-11) primary government
- December 11, 2025 City Council Minutes (Orangeville) (Orangeville City, 2025-12-11) primary government “he would like to see them annexed into the city”
- June 11, 2026 City Council Minutes (Orangeville) (Orangeville City, 2026-06-11) primary government “Mayor will be meeting with Valor regarding annexation”
- July 9, 2026 City Council Meeting Minutes (Orangeville) (Orangeville City, 2026-07-09) primary government “we have sent a draft of the nuclear energy industry ordinance”
- Orangeville City Planning and Zoning Commission minutes, July 16, 2026 (notice text) (Orangeville City Planning and Zoning, 2026-07-16) primary government “Everything needs to go through the attorneys from the City and Valar.”
- Orangeville Planning and Zoning Commission agenda, August 11, 2026 (Orangeville City Planning and Zoning, 2026-08-11) primary government
- Orangeville Planning and Zoning Commission agenda, September 8, 2026 (Orangeville City Planning and Zoning, 2026-09-08) primary government
- Orangeville Planning and Zoning Commission work meeting agenda, September 17, 2026 (Orangeville City Planning and Zoning, 2026-09-17) primary government
- Orangeville City Council agenda, September 10, 2026 (Orangeville City, 2026-09-10) primary government
- August 13, 2026 City Council Minutes (Orangeville) (Orangeville City, 2026-08-13) primary government “Once sale is finalized Annexation process can begin”
- Orangeville City Council notices through the 8 October 2026 public hearing notice (Utah Public Notice Website) primary government
- Emery County Commissioners Debate Solar, Data Centers and EMS Funding (Kevin Butler) (ETV News, 2026-07-28) news
- CVSSD Regular Meeting Minutes, May 21, 2026 (approved; scanned, read as page images) (Castle Valley Special Service District, 2026-05-21) primary government “property near Orangeville that may be developed by Valor”
- Orangeville Planning and Zoning Commission notices, May to September 2026 (Utah Public Notice Website) primary government
The Board of the Governor's Office of Economic Development approved, by unanimous consent on 9 July 2026, a REDTIF post-performance refundable tax credit for Valar Atomics Inc. of up to $106,737,499: 50% of new state tax revenue for 10 years, with projected capital investment of $1,299,110,000, 275 jobs at an average wage of $137,567, in Emery County. The credit is paid only after new revenue is receipted, is 'site specific and subject to local incentive participation', and needs a local incentive approved by the GOED Incentives Committee. The notice and agenda, posted 7 July, described the item only as a company in 'the energy and advanced manufacturing industry' (the same agenda named the three companies up for economic development zones); the board materials naming Valar were attached to the notice at 1:00 p.m. on 9 July, after the meeting, which was scheduled for 10 a.m. to noon. Utah's records law lets agencies protect records that would reveal incentive negotiations if disclosure would cause the company economic harm (63G-2-305(35)), and the July 9 minutes carry that label. Per the minutes, Valar's representatives spoke of a 'waterless data center in Orangeville' and plans 'to install additional commercial units in the area', and an Emery County commissioner spoke in support. No state incentive record for the Carbon County campus was found.
- 0. GOED Public Board Materials - 7.9.26 (Valar Atomics Inc. executive summary) (Board of the Governor's Office of Economic Development (Utah Public Notice Website), 2026-07-09) primary government “Incentives are site specific and subject to local incentive participation.”
- 2. GOED Board Meeting Minutes - 7.9.26 (posted with the Sept 10, 2026 meeting) (Board of the Governor's Office of Economic Development (Utah Public Notice Website), 2026-09-10) primary government “plan to install additional commercial units in the area”
- GOED Board Meeting, July 9, 2026 (notice) (Utah Public Notice Website, 2026-07-07) primary government “one company operates in the energy and advanced manufacturing industry”
- 1. GOED Board - Public Agenda - 7.9.26 (attached to the July 9 notice 2026-07-07 3:18 PM) (Board of the Governor's Office of Economic Development (Utah Public Notice Website), 2026-07-07) primary government “one company operates in the energy and advanced manufacturing industry”
- Utah Code 63G-2-305: Protected records (effective 7/1/2026), subsection (35) (Utah State Legislature, 2026-07-01) primary government “records that would reveal negotiations regarding assistance or incentives offered by”
Re-reading the GOED board's 9 July 2026 materials and minutes (csite-024 has the incentive terms): the executive summary describes a $1,299,110,000 Emery County project with 275 jobs averaging $137,567, and says the up-to-$106,737,499 REDTIF credit (half of new state tax revenue for 10 years, paid only after the revenue comes in) is 'site specific and subject to local incentive participation', with a local incentive proposal needing GOED Incentives Committee approval. Per the minutes, Valar's Harry Hansen cited the NVIDIA chip demonstration and 'a waterless data center in Orangeville'; Valar's Cory Gardner said Valar plans 'to install additional commercial units in the area', that the fastest path to turning reactors on is selling power 'behind the meter' to avoid interconnection queues, that its near-term strategy is 'behind-the-meter customers willing to pay a premium', and that no one has yet sold power from an advanced reactor in America. The minutes list Emery County Commissioner Jordan Leonard among the visitors under 'Valar Atomics' (they do not say why) and record him speaking in support. Set beside the record: three months earlier, at the county's 7 April hearing, the answer recorded to 'what incentives has the county given you?' was 'None', with a commissioner adding Valar had 'not even asked' for a tax incentive (gov-022); no local incentive for Valar appears on the Emery County Commission's or its Community Reinvestment Agency's agendas through September 2026 (Utah Public Notice Website scan, 29 Sept 2026); and DOE's legal basis for authorizing Ward 250 without the NRC is that pilot reactors do not produce commercial electric power (safe-030, gov-007), so sold power from 'commercial units' would need NRC licensing (csite-010).
- GOED Public Board Materials, July 9, 2026 (Valar Atomics Inc. executive summary) (Governor's Office of Economic Opportunity (Utah Public Notice Website), 2026-07-09) primary government “Incentives are site specific and subject to local incentive participation.”
- GOED Board Meeting Minutes, July 9, 2026 (posted with the Sept 10, 2026 meeting) (Governor's Office of Economic Opportunity (Utah Public Notice Website), 2026-09-10) primary government “they plan to install additional commercial units in the area”
- Emery County Commission Meeting Minutes, April 7, 2026 (Emery County Commission (Utah Public Notice Website), 2026-04-07) primary government “they have not even asked for any tax incentive”
What local records show about Valar's water: 11 December 2025, Orangeville approved a future 8-inch water line for Valar's new building, Valar saying it 'acquired the necessary water shares', on condition that fees are paid and the correct shares turned in (minutes). 19 February 2026, the utility district approved a $20,000 connection contingent on all shares being submitted to Orangeville (loc-015). 9 July 2026, Orangeville minutes: the 1,000 water shares under discussion are 'still in the discussion phase' and not for the data center; Valar told the county on 21 July the extra shares would support future development on the land it is buying (mine-042). For scale, the mayor told the council in November 2025 that the city itself held 998.4 Class A and 94 Class B shares of Cottonwood Creek irrigation water and was still 89 shares short. On 16 July 2026 the utility district reported 'critically low reservoir levels' and Orangeville's secondary water at 233 acre-feet for the year. Which company's shares Valar holds or seeks, and how much water 1,000 shares represents, is not stated in any record read. Utah Division of Water Rights records, where a change of use would be filed and advertised, could not be searched: its search pages sit under a path its robots.txt closes to all automated readers (sources_not_read).
- December 11, 2025 City Council Minutes (Orangeville) (Orangeville City, 2025-12-11) primary government “they have acquired the necessary water shares”
- July 9, 2026 City Council Meeting Minutes (Orangeville) (Orangeville City, 2026-07-09) primary government “The 1000 water shares is not part of the data center”
- November 13, 2025 City Council Minutes (Orangeville; notice text) (Orangeville City, 2025-11-13) primary government “right now the city has 998.4 Class A shares and 94 Class B shares”
- CVSSD Regular Meeting Minutes, July 16, 2026 (approved; scanned, read as page images) (Castle Valley Special Service District, 2026-07-16) primary government “critically low reservoir levels raise concerns”
- CVSSD Regular Meeting Minutes, February 19, 2026 (approved) (Castle Valley Special Service District, 2026-02-19) primary government
- Orangeville City Council approves resolutions, discusses EMS and Valar (Kevin Butler) (ETV News, 2026-07-16) news
- Emery County Commissioners Debate Solar, Data Centers and EMS Funding (Kevin Butler) (ETV News, 2026-07-28) news
- Utah Code 73-3-6: Publication of notice of application (amended 2024) (Utah State Legislature, 2024-05-01) primary government “once a week for a period of two successive weeks in a newspaper”
- NOTICE TO WATER USERS (Emery County applications; protests due Oct. 20, 2026) (Utah Division of Water Rights (legal notice published in ETV News), 2026-09-23) primary government “Protests must be filed with the Division of Water Rights”
At the 1 July 2026 event at the Orangeville site (orig-042), ETV reported that Valar's Max Ukropina and NVIDIA representatives 'discussed a collaboration to explore' nuclear-powered AI factories, including a proposed 30-megawatt facility in Emery County, and that the reactor was raised to 37% power to supply electricity to a server hosting a website. KSL/Deseret (6 July) wrote that the companies are 'exploring the deployment' of a 30 MW data center fully powered by their reactor. Valar's Series B post (4 August) calls it 'a collaboration on a waterless 30 MW AI factory'. No contract, memorandum or NVIDIA release was found: a search of nvidia.com returned nothing on Valar, and no filing names a Valar-NVIDIA agreement. In July Valar told the state economic board of 'a waterless data center in Orangeville' (gov-033); in June its public-affairs representative told Orangeville the reactor's energy has no set purchaser (loc-016). Scale: 30 MW is 300 times Ward 250's 100 kW heat rating, and more than that in electricity, since only part of the heat becomes electricity. No reactor Valar has built or had authorized could supply it; it would take a fleet or much larger reactors, which for sold power would need NRC licensing (csite-010, safe-030). If ETV's 37% is of the 100 kW rating, the demonstration ran at roughly 37 kW of heat, and ETV says the electricity came from a thermoelectric generator, which turns only part of the heat into electricity; KSL/Deseret's line that the reactor 'is now generating 100 kilowatts of electricity' (orig-042) fits neither figure.
- Emery County takes center stage as Valar and Nvidia power historic breakthrough (ETV News (Kevin Butler), 2026-07-01) news “discussed a collaboration to explore nuclear-powered AI factories”
- New partnership touts nuclear-powered AI with minimal water use (KSL.com (Eva Terry, Deseret News), 2026-07-06) news “exploring the deployment of a 30 megawatt data center”
- Announcing our $1B Series B Led By Sequoia (Valar Atomics, 2026-08-04) primary company “a collaboration on a waterless 30 MW AI factory”
No power purchase agreement, utility contract or named customer for Valar was found as of 29 September 2026. What the record shows instead: in June 2026 Valar's public-affairs representative told Orangeville the reactor's energy has no set destination or purchaser (loc-016); in July Valar told the state economic board its fastest path is selling to 'behind-the-meter customers willing to pay a premium', skipping grid interconnection (gov-033); in August it told a local business chamber it might build reactors for heavy industrial users, naming a local manufacturer 'strictly as an example' (ETV, 24 August); NVIDIA's role is an announced study (plan-010); and on 17 September, just before the Carbon lease vote, Valar's Harry Hansen told the Trust Lands board that Valar was at the point where site control 'becomes the next conversation when it comes to off-takers', after which it could talk about bringing in buyers for the power (auto-generated meeting transcript). Abroad, Bilyonaryo reported on 2 July 2026 that Meralco, the Philippines' largest electricity distributor, would hold talks with Valar 'in the coming days', according to its chief operating officer, who added that Meralco is open to other small-reactor technologies and that any investment must rest on proven designs. No agreement from those talks was found. No U.S. utility (Rocky Mountain Power/PacifiCorp or others) was found naming Valar in a search of the web; the Utah Public Service Commission's docket site answered with a bot check and could not be searched. Selling Ward 250's power is outside DOE's research-only basis for authorizing it (safe-030).
- MVP opens talks with US firm Valar Atomics on next-gen nuclear reactor (Bilyonaryo (staff), 2026-07-02) news “will hold talks with Valar representatives in the coming days”
- Emery County Business Chamber gets an up-close look at Valar Atomics progress (ETV News (Stephanie Olsen), 2026-08-24) news “strictly as an example”
- Orangeville City Council Regular Meeting Minutes, June 11, 2026 (Orangeville City, via Utah Public Notice Website, 2026-06-11) primary government “the energy does not currently have a set destination or purchaser”
- 09.17.2026 TLA Board of Trustees Meeting Audio (auto-generated transcript) (Utah Trust Lands Administration, via Utah Public Notice Website, 2026-09-17) primary government “Valor's at the point where site control becomes the next conversation”
EO 14301 places advanced reactors under DOE rather than NRC jurisdiction when DOE exercises sufficient control and they do 'not ... produce commercial electric power'. Valar says Ward 250 generated electricity on 1 July 2026, 'directly powering an NVIDIA chip' (orig-013; Deseret News reported the event, orig-042), and Valar and NVIDIA said they were exploring a 30 MW data center powered by Valar reactors (orig-042). No record read shows Ward 250 selling electricity. The Nuclear Innovation Alliance notes that the Atomic Energy Act lets DOE retain 'for its own account' the commercial application of an initial demonstration reactor, that section 44 governs the sale of electricity incidental to test and demonstration reactors, and that sales of electricity to third parties 'raise unresolved regulatory questions' for DOE and the NRC. DOE-STD-1271 says the DOE pathway is meant to accommodate 'leveraging into an NRC license'. On the record read, the July 1 demonstration stays inside the non-commercial line; any commercial use of Valar reactors would need NRC licensing (csite-010).
- Executive Order 14301, Reforming Nuclear Reactor Testing at the Department of Energy, 90 FR 22591 (Executive Office of the President (Federal Register), 2025-05-29) primary government “and not to produce commercial electric power”
- Castle Country | Valar Atomics (Valar Atomics) primary company “directly powering an NVIDIA chip”
- A Review of Recent DOE Updates to Its Reactor Authorization Process (Nuclear Innovation Alliance) analysis “such sales raise unresolved regulatory questions for the DOE and NRC”
- DOE-STD-1271-2025, Authorization Pathway for Nuclear Facilities (August 2025; DOE standard, copy posted by the Nuclear Innovation Alliance) (U.S. Department of Energy, Office of Nuclear Energy, 2025-08) primary government “intended to accommodate efficient and effective leveraging into an NRC license”
Deseret News (Eva Terry, July 1, 2026) reported an event at Valar's Orangeville site with Taylor, an NVIDIA energy-policy director, Utah energy office director Emy Lesofski and State Sen. David Hinkins, where the companies said they are exploring a 30 megawatt data center fully powered by Valar's reactors. The article says Ward 250 was 'now generating 100 kilowatts of electricity'; that wording cannot match the 100 kW thermal limit in Valar's safety agreement (orig-034): a reactor limited to 100 kW of heat cannot deliver 100 kW of electricity, because turning heat into electricity always loses part of it. The figure is most likely the thermal rating reported as electric. The article quoted no independent expert or critic.
- New partnership touts nuclear-powered AI with minimal water use (Deseret News, 2026-07-01) news “it is now generating 100 kilowatts of electricity”
Orangeville City Council minutes, 11 June 2026, public comment: Valar's Harry Hansen, who said he has a background with the state energy office, answered council questions. Asked how many local workers were hired, he said he would get an accurate number. Asked whether Valar's second building is another reactor, he said it is not: Valar will manufacture its own fuel there, the fuel is 'extremely safe', and 'Once completed they will be the largest manufacturer of this fuel in the United States'. Asked whether the energy would go to data centers, he said data centers 'could be purchasers' but the energy has no set destination or purchaser yet. Set beside the record: the fuel building matches the lab's January 2026 release and Valar's QA plan for a 'Valarin' TRISO fuel facility (loc-003, orig-038); no DOE safety authorization for the fuel line has been made public (safe-031); the 'largest' claim is about the future and cannot be tested now; selling Ward 250's energy would fall outside DOE's research-only basis for authorizing it (safe-030).
- June 11, 2026 City Council Minutes (Orangeville) (Orangeville City, 2026-06-11) primary government “Once completed they will be the largest manufacturer of this fuel”
State records show the San Rafael lab hosting or courting several nuclear developers besides Valar: NuCube (MOU with OED, 6 May 2025 per OED's slides; named with Valar to legislators in June 2025, gov-019), which POWER reports was instead selected with Idaho State University in April 2026 for DOE's Launch Pad USA, to site its test reactor on ISU's Pocatello campus; Natura Resources, which holds an NRC construction permit for a molten-salt reactor in Texas and whose project at the lab (medical isotopes, a planned test reactor) the Energy Research Board approved the same day as Valar's (13 Aug 2025, gov-013), and which OED told legislators is leasing 'the majority of the space' at the lab (Oct 2025); and Nuclea Energy, a Canadian company, whose MOU to explore siting a 3.5 MW electric test reactor the board approved on 11 February 2026 and OED signed on 2 June 2026, with OED offering to 'support licensing conversations' with DOE and the NRC and to help explore deployment 'beyond test reactors'. Valar itself proposed a 10 MW gas-fired heater for power-cycle tests (gov-014), is buying the 112-acre parcel next door for fuel fabrication and manufacturing (gov-022), and plans a TRISO fuel line (safe-031). The lab told its board in February 2026 it was adding perimeter fencing and ID checks 'to meet DOE standards'. No public safety analysis or environmental review for these other projects was found in the records read, as of 2026-09-29.
- Memorandum of Understanding between OED and Nuclea Energy USA Inc. (OED26142), signed June 2, 2026 (Utah Office of Energy Development, 2026-06-02) primary government “OED is willing to support licensing conversations with both the Department of Energy”
- Utah Energy Research Board Meeting Minutes, February 11, 2026 (Utah Energy Research Board, 2026-05-13) primary government “to explore siting a 3.5 MW electric test reactor at the lab”
- Board Meeting Minutes, Utah Energy Research Board, August 13th, 2025 (Utah Energy Research Board, 2025-11-13) primary government
- Office of Energy Development Update, PUET Interim Committee, October 15, 2025 (Utah Office of Energy Development, 2025-10-15) primary government
- From Pilot to Launch: DOE Names First Four Nuclear Energy Launch Pad Developers (Sonal C. Patel) (POWER, 2026-04-28) news
Nuclear siting in Emery County is not only Valar. Near Green River, Blue Castle Holdings leased water rights totalling 53,600 acre-feet from the Kane County (29,600) and San Juan County (24,000) water conservancy districts for a proposed nuclear power plant; the Utah Court of Appeals affirmed approval of the change applications in July 2016 against a challenge by HEAL Utah and others, noting the project still needed an environmental review and an NRC early site permit application (2016 UT App 153). On 27 May 2026 Fulcrum Point Holdings (a Hi Tech Solutions affiliate) announced a joint venture with Blue Castle (KSL; Holtec's release is dated 28 May and Utah Business carried the Fulcrum release on 29 May) to take the project through federal licensing with Holtec SMR-300 reactors, which can use air cooling; Emery Commissioner Jordan Leonard and the governor's energy adviser are quoted in support. Neither release gives an NRC filing date; the Fulcrum release's company description puts the multi-unit Blue Castle project at up to 2,200 megawatts, while KSL noted the announcement did not specify the Green River capacity. KSL (27-28 May) reported HEAL Utah's concerns about water use, the Colorado River and waste. At the 30 June 2026 Carbon/Emery economic development committee, a Hi Tech Solutions director said the site had been studied, land and access secured, and the project was in the application process (ETV). The Emery Commission voted in September 2025 to support Green River as a site for a state nuclear project (gov-021). Separately, Valar filed a 10,270-acre 'Green River Gigasite' reactor and data-center application with BLM in February 2026, which it later told a reporter it had dropped while BLM still lists it pending (mine-006, mine-008). No record read connects the Blue Castle project to Valar. The NRC's site refused our reader, so no NRC filing for either could be checked.
- HEAL Utah v. Kane County Water Conservancy District, 2016 UT App 153 (No. 20140429-CA) (Utah Court of Appeals, 2016-07-21) primary government
- Holtec International's SMR-300 Chosen to Power the Green River Advanced Nuclear Project in Utah (Holtec International, 2026-05-28) primary company
- Fulcrum Point Holdings, a Hi Tech Solutions affiliate, announce joint venture with Blue Castle to advance nuclear project in Green River, Utah (press release) (Fulcrum Point Holdings (via Utah Business), 2026-05-29) primary company
- Green River nuclear energy plans revived, add to Utah's potential nuclear portfolio (Tim Vandenack) (KSL.com, 2026-05-27) news
- Carbon/Emery economic development committee discusses nuclear energy, business grants, and coal exports (Kevin Butler) (ETV News, 2026-07-06) news
ETV News (28 May 2026) reported that at the 26 May Carbon/Emery economic development group, a USU Eastern deputy vice president said the Price campus is hiring two or three faculty to launch an engineering curriculum, starting with fundamentals in fall 2026, aiming to enroll students by fall 2027. At the 30 June meeting, the new USU Eastern engineering program was noted as favorable for a nuclear plant and its employees (ETV, 6 July). A USU Eastern release printed by ETV (26 March 2026) says Valar spoke at the Eastern Leaders Academy's economic development day. A USU Eastern professor's housing study counted Valar's workforce (loc-010), and USU Eastern hosted an Economic Development Summit in October 2025 (ETV, 6 Oct 2025). No USU Eastern training agreement, nuclear technician program or funding tie with Valar was found in the records read; Valar's Orangeville job posts ask for years of experience and several say 'willing to relocate to Orangeville' (job board, 29 Sept; loc-019), and a Valar radiation-protection staffer told the Trust Lands board he would hire and train local radiation technicians (ppl-009).
- USU Eastern Engineering, Ridge Road Growth, PacifiCorp IRP Presented to Carbon/Emery EDC (Kevin Butler) (ETV News, 2026-05-28) news
- Carbon/Emery economic development committee discusses nuclear energy, business grants, and coal exports (Kevin Butler) (ETV News, 2026-07-06) news
- Economic growth & development in focus at Eastern Leaders Academy (USU Eastern press release) (ETV News, 2026-03-26) primary government
- The importance of the Economic Development Committee stressed by many (ETV News, 2025-10-06) news “the Economic Development Summit at USU Eastern in October”
- Valar Atomics job board (Greenhouse public board API; Orangeville postings) (Valar Atomics) primary company “Willing to relocate to Orangeville, UT area for operations.”
The only fuel supply for Valar on the record is DOE's: a Safety Evaluation Report approved 20 May 2026 lets Savannah River's shipping package carry 'limited shipments' of HALEU TRISO fuel compacts from the National Criticality Experiments Research Center in Nevada to the Ward 250 site, at most 24 packages, one Valar-designed graphite fuel block each, expiring 30 June 2027 or when shipments end (safe-010, safe-011, safe-012). The report describes each block as 170 TRISO compacts holding 234.94 grams of uranium-235 at under 20% enrichment. Valar's own safety agreement (NSDA, October 2025, Table 6) lists the fuel enrichment as '4.95% U-235' on the basis of 'LEU limits'; the two documents describe different fuel, and no document read explains the difference (disc-001). No public record read gives the dates the fuel actually moved (plan-025). Neither that report nor Valar's NOVA release nor World Nuclear News's NOVA report (21 November 2025) names who fabricated the TRISO particles or compacts, or who owns the high-assay uranium; Valar is not in DOE's three announced HALEU allocation rounds (gov-008). Valar's Series B post says it 'will not rely on outside suppliers' and will make fuel in labs beside its reactors (orig-070), and its Carbon plan has uranium shipped in as HALEU, LEU+ or LEU (csite-007). But making TRISO still needs enriched uranium from an enrichment plant; Valar has no enrichment capacity, and a web search in the earlier pass found no supply contract with any U.S. enricher (Centrus, Urenco, Orano, General Matter). For comparison, World Nuclear News reported on 18 September 2026 that the fuel for Antares's criticality test, another DOE pilot reactor, was supplied by BWX Technologies, and that Antares had signed a multi-year HALEU supply contract with Centrus (the article gives no signing date). Valar is one of 84 signers of DOE's Defense Production Act fuel-cycle pact (gov-001), which is a framework, not a supply contract.
- Safety Evaluation Report, Letter Amendment of Certificate of Compliance No. 9979, Revision 20 (Valar Atomics fuel elements) (U.S. Department of Energy, Packaging Certification Program, 2026-05-20) primary government “from the National Criticality Experiments Research Center in Nevada to the Valar Atomics”
- Valar Atomics project achieves early criticality milestone (World Nuclear News, 2025-11-21) news “NOVA uses the same fuel, moderator and reactivity-control scheme as Ward250”
- Announcing our $1B Series B Led By Sequoia (Valar Atomics, 2026-08-04) primary company “Valar will not rely on outside suppliers for the fuel needed to deploy and operate.”
- Antares, Centrus sign multi-year HALEU contract (World Nuclear News, 2026-09-18) news “The fuel for the criticality demonstration was provided by BWX Technologies, Inc.”
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (October 2025), Appendix A, Table 6: Key design parameters (Valar Atomics, 2025-10) primary company “4.95% U-235”
From the Emery County Commission's minutes. 20 Jan 2026: the commission began 'the disposition process' for parcel 04-0019-0030 ('the property next to the Research Center') 'solely for the purpose of economic development'. 17 Feb: a letter of support for Valar passed; the MOU for Valar's site-suitability testing on the parcel was 'Tabled' (the agenda listing is in orig-046). 17 March: the county's property ordinance required 30 days' notice to neighbors, posting three weeks before sale, and 'sealed bids'; the commission added a section letting it sell under state statute 17-78-103 (notice, public comment and fair value by two appraisals, no bidding) when a parcel is not posted within 30 days; the county attorney said he had not reviewed the new wording and Commissioner Worwood voted no for that reason; the same meeting then approved selling the parcel to Valar under 17-78-103, subject to a hearing and two appraisals, and let Valar use it as a staging area if the county were released from liability. 7 April hearing: Valar said it wants the land for 'Fuel fabrication and manufacturing' and possible temporary employee housing; the state lab director said the state also wanted to buy it, for 'contiguous ownership to maintain safety', and asked whether a bid process could be requested; Commissioner Worwood answered that the county followed state requirements and called the sale 'an intermediate step' while Valar looks for 'a larger piece of property with water'; asked about incentives, the answer recorded was 'None'. 19 May: the commission (2-0) approved the purchase and sale agreement at $394,500, the average of two appraisals, sent annexation notices for the parcel and the lab parcel into Orangeville, and passed a resolution removing the parcel from the Inland Port project area (gov-023). 7 July: a 30-day due-diligence extension, already signed by one commissioner, was ratified; he said the land 'has been sold' to Valar. Other items in these minutes: on 17 March a local special service district asked that Valar annex the parcel into Orangeville, and the sheriff reported a recent meeting with Valar on safety. No recorded deed was read (open question).
- Emery County Commission Meeting Minutes, January 20, 2026 (Emery County Commission (Utah Public Notice Website), 2026-01-20) primary government “solely for the purpose of Economic Development”
- Emery County Commission Meeting Minutes, February 17, 2026 (Emery County Commission (Utah Public Notice Website), 2026-02-17) primary government
- Emery County Commission Meeting Minutes, March 17, 2026 (Emery County Commission (Utah Public Notice Website), 2026-03-17) primary government “as of this meeting has not reviewed the section wording”
- Emery County Commission Meeting Minutes, April 7, 2026 (public hearing on sale of parcel 04-0019-0030) (Emery County Commission (Utah Public Notice Website), 2026-04-07) primary government “the State is interested in contiguous ownership to maintain safety”
- Emery County Commission Meeting Minutes, May 19, 2026 (Emery County Commission (Utah Public Notice Website), 2026-05-19) primary government “The asking price would be $394,500.00.”
- Emery County Commission Meeting Minutes, July 7, 2026 (Emery County Commission (Utah Public Notice Website), 2026-07-07) primary government “has been sold by the county to Valar”
- Utah Code 17-78-103, Acquisition, management, and disposal of property (effective 5/6/2026) (Utah State Legislature, 2026-05-06) primary government
Valar's Nuclear Safety Design Agreement (October 2025) describes a lifecycle of about 18 months from authorization through decommissioning: a pre-operational phase, 12 months of nuclear operations in test campaigns, then defueling and decommissioning that returns the site to unrestricted use. DOE's environmental determination (22 April 2026) describes a 24-month research program: about 12 months of reactor operation, 6 months of in-vessel cooldown and 6 months of decommissioning, after which the single core of spent fuel goes in dry casks to an unnamed 'DOE-approved facility' (safe-023). DOE's agreement with Valar runs from October 2025 to 4 July 2027 (orig-055). If operations are counted from criticality in June 2026, the 12 months end around June 2027, and DOE's schedule puts the end of decommissioning around mid-2028; no record read gives the actual planned end date. Set beside this, Valar now describes the Utah site as permanent: its head of projects told the state trust-lands board the lab is 'no longer just a test facility' (ppl-006), it is buying the neighboring 112-acre parcel (gov-022), it was approved for a state tax credit that requires it to stay 10 years (fund-017), and its Castle Country page says 'we're ready to build more'. At the 1 July 2026 event Taylor said the fuel inside Ward 250 would let it keep running for 165 years (KSL/Deseret, 6 July); that describes the fuel's capacity at very low power, not the approved plan, which is about 12 months of operation with no refueling (DOE). The two are not necessarily in conflict (the test reactor can be removed while the company stays), but no public document says what replaces Ward 250 or whether Ward 250 will actually be torn down on the stated schedule.
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (October 2025), page 8 (Valar Atomics, 2025-10) primary company “a structured lifecycle spanning approximately 18 months from authorization through decommissioning”
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (U.S. Department of Energy, Office of Nuclear Energy, 2026-04-22) primary government “consisting of approximately 12 months of reactor operation followed by 6 months”
- Castle Country (Valar Atomics, 2026-09) primary company “We think of this as home, and we're ready to build more.”
- New partnership touts nuclear-powered AI with minimal water use (KSL.com (Eva Terry, Deseret News), 2026-07-06) news “The fuel inside the Ward250 will let it continue running for 165 years”
At the same 7 April 2026 Emery County hearing, a resident asked about safety buffer zones; Valar's representative answered that every design has to be reviewed and approved by the Department of Energy. Asked about 'turmoil' between the state and the NRC, Valar's Max Ukropina said past laws had been burdensome and that President Trump had loosened some regulations. Set beside the record: for Ward 250 the answer holds, since DOE alone authorizes it (safe-001, gov-005). For what Valar has described next it is incomplete: three months later Valar told the state's incentive board it plans 'additional commercial units in the area' and behind-the-meter power sales (gov-033); the executive order behind the DOE route covers reactors that do not produce commercial electric power (gov-005); and DOE's own releases, and Hogan Lovells' summary of the law, place later commercial licensing with the NRC (gov-007, gov-032, csite-010). DOE's Launch Pad USA pathway can authorize non-federal sites, but no record read shows Valar using it for another site (gov-010).
- Emery County Commission Meeting Minutes, April 7, 2026 (public hearing on sale of parcel 04-0019-0030) (Emery County Commission (Utah Public Notice Website), 2026-04-07) primary government “every design has to be reviewed and approved by the Department of Energy”
- GOED Board Meeting Minutes, July 9, 2026 (Governor's Office of Economic Opportunity (Utah Public Notice Website), 2026-09-10) primary government “they plan to install additional commercial units in the area”
- Executive Order 14301 (90 FR 22591) (Federal Register (GPO govinfo), 2025-05-29) primary government “that do not produce commercial electric power”
ETV's report (9 April 2026) of Emery County's 7 April hearing on selling the 112-acre parcel beside the lab says Valar's representatives explained they needed more land to expand their factory and ready the reactor, and, asked what they planned to build, replied that plans were not firm yet but they were considering expansion and 'maybe even housing'. Later in the same meeting the commission approved a real-estate use agreement letting Valar use 10 acres south of the lab as a laydown and staging area during construction, with a waiver of liability. The county's own minutes add that Valar named 'fuel fabrication and manufacturing' for the parcel and that a commissioner called the sale an 'intermediate step' while Valar looked for a larger property with water (gov-022, gov-038); the sale price was $394,500 and closing was not confirmed as of mid-August (loc-014); Orangeville is drafting an advanced-energy zoning district and annexation for the land (loc-013); Valar is seeking up to 1,000 more water shares for future development there (loc-017). The Wellington lease map was drawn two days after this hearing (mine-048).
- Emery Commission public hearing receives comments on the sale of property to Valar Atomics (ETV News, 2026-04-09) news “plans are not firm yet but are considering expansion and maybe even housing”
Castle Dale City Council minutes of 12 March 2026 record Valar's director of Utah operations, Jess Housekeeper, saying 'The reactor requires minimal water—about 10 acre-feet for industrial use' and that it mainly uses helium cooling. The minutes give no time period for the 10 acre-feet. If it is a yearly figure, 10 acre-feet is about 3.26 million gallons, or roughly 8,900 gallons a day on average. DOE's categorical exclusion for Ward 250, signed six weeks later (22 April 2026), describes water use only as 'less than 1000 gallons/day for domestic use', says no process water is discharged and that sanitary waste goes through the lab's infrastructure, and does not mention any industrial water use. The utility district's minutes say Valar asked for restroom sewer service only, with no process water (loc-015). The figures may describe different things (the reactor alone versus the whole site with its fuel laboratory, consumption versus a water-right allotment, or a yearly versus a one-time amount); no record read reconciles them. Separately, Valar says it holds the shares for its current needs and seeks up to 1,000 more for future development (loc-017).
- Castle Dale City Council Meeting Minutes, March 12, 2026 (approved; scanned, read as page images) (Castle Dale City, 2026-03-12) primary government “The reactor requires minimal water—about 10 acre-feet for industrial use”
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (categorical exclusion B5.26) (U.S. Department of Energy, Office of Nuclear Energy, 2026-04-22) primary government “Water consumption is less than 1000 gallons/day for domestic use.”
- CVSSD Regular Meeting Minutes, March 19, 2026 (approved) (Castle Valley Special Service District, 2026-03-19) primary government “standard sanitary sewer service only for restrooms, with no process water proposed”
ETV News (24 Feb 2026) reported a USU Eastern professor's presentation to the Emery County Business Chamber's housing committee on growth in Carbon and Emery counties: about 1,100 temporary units (motel rooms and RV spaces), roughly 100 homes for sale in Carbon and 20 in Emery, median price above $400,000; Valar's nuclear test project planning to employ about 40 technicians and contractors who would compete for short-term rentals; and 300-400 miners expected at Fossil Rock looking for long-term housing. The same professor updated the Carbon/Emery economic development committee on his 'Housing Analysis for Carbon and Emery Counties' on 27 January 2026, prompting discussion of population growth from Valar and Fossil Rock (ETV, 30 Jan; that meeting heard of 170 homes for sale in Carbon and 18 in Emery). At Emery's 7 April hearing Valar named possible housing among uses for the land it was buying (ETV; gov-022). The larger job numbers Valar gave the state in July 2026 (275, loc-004) and the Carbon campus plan are not reflected in any housing study read. Orangeville's council adopted a 180-day moratorium on new short-term rental applications on 8 January 2026, a councilman saying 'with the nuclear hiring staff' the housing effect was unknown (minutes), and at a May 2026 public hearing on rental rules a councilman said more housing will be needed to support the mines and Valar (minutes).
- Housing Committee hears about coming population growth and housing crisis (ETV News, 2026-02-24) news “planning to employ about 40 technicians and contractors”
- January 8, 2026 City Council Meeting Minutes (Orangeville) (Orangeville City, 2026-01-08) primary government “with the nuclear hiring staff”
- May 14, 2026 Public Hearing Minutes (Orangeville) (Orangeville City, 2026-05-14) primary government “more housing needed to support the mines, Valor Atomics, etc.”
- Economic Development Committee discuss housing and well permitting (Julie Johansen) (ETV News, 2026-01-30) news “Housing Analysis for Carbon and Emery Counties”
On 19 February 2026 the state's Resource Development Coordinating Committee (RDCC) posted four applications for Trust Lands right-of-entry (site-study) permits as projects 87096 to 87099, numbered 7672, 7674, 7675 and 7676. Comments were due 3 March and the stated start was 6 March. Each notice says that Trust Lands 'has received a Right-of-Entry (ROE) permit application' for cultural-resource surveys, geotechnical investigations and similar studies 'to evaluate the feasibility of a potential industrial and manufacturing development', and that 'No permanent development is proposed under the Right-of-Entry authorization.' Trust Lands' permit maps, dated 18 February 2026, give the areas: 7672, 1,812.94 acres near Green River (T20S R15E and T21S R15-16E, Emery County); 7674, 5,381.59 acres south and west of Price (T14-15S R9-10E, Carbon County); 7675, 634.32 acres, nearly all of Section 16, T14S R11E, north of Wellington (Carbon County; the map leaves out a small southeast corner); 7676, 487.83 acres in Sections 2 and 16, T16S R13E (Emery County). That is 8,316.68 acres in all. The notices record that local governments were contacted on 19 February. The only state comments were Division of Wildlife Resources recommendations of 3 March 2026: three of the areas are crucial year-long pronghorn habitat; white-tailed prairie dogs, burrowing owls and kit foxes could occur; and hawks are known to nest near two of the areas. No applicant is named in the four notices, the four maps or the comment letters, and no record read shows the permits were issued: the register lists all four as 'State Comment Published'.
- RDCC project register: projects 87096-87099 (Right-of-Entry Permits #7672, #7674, #7675, #7676) and 87203 (SULA 2095) (Utah Resource Development Coordinating Committee (Public Lands Policy Coordinating Office), 2026-02-19) primary government “to evaluate the feasibility of a potential industrial and manufacturing development”
- Right of Entry No. 7672 - Geotechnical Survey (permit map, file ROE_7672_SULA_1622_02182026.pdf) (Utah Trust Lands Administration (via the RDCC project register), 2026-02-18) primary government “Right of Entry No. 7672 - 1,812.94 Acres”
- Right of Entry No. 7674 - Geotechnical Survey (permit map) (Utah Trust Lands Administration (via the RDCC project register), 2026-02-18) primary government “Right of Entry No. 7674 - 5,381.59 Acres”
- Right of Entry No. 7675 - Geotechnical Survey (permit map) (Utah Trust Lands Administration (via the RDCC project register), 2026-02-18) primary government “Right of Entry No. 7675 - 634.32 Acres”
- Right of Entry No. 7676 - Geotechnical Survey (permit map) (Utah Trust Lands Administration (via the RDCC project register), 2026-02-18) primary government “Right of Entry No. 7676 - 487.83 Acres”
- Public Lands Policy Coordinating Office letter on Right-of-Entry Permit #7674 (Division of Wildlife Resources comments) (Utah Public Lands Policy Coordinating Office, 2026-03-03) primary government “within crucial year-long pronghorn habitat”
Right-of-entry permit application 7672 (1,812.94 acres; Trust Lands permit map, 18 February 2026) lies within Sections 32 and 36 of T20S R15E, Sections 10 and 11 of T21S R15E and Section 6 of T21S R16E, near Green River in Emery County. The permit map file is named for, and draws beside it, Special Use Lease Agreement No. 1622 (2,441.03 acres); no record read names that lease's holder. Overlaid on BLM's case map for Valar's pending 'Green River Gigasite' right-of-way application (UTUT106784007), Section 32 of T20S R15E lies wholly inside the application's outer boundary and is the only hole in the case map (about 637 acres): state land the application surrounds. The case map also covers about 467 acres of Section 6, T21S R16E (the part that is not state land); the permit application's state land there lies outside it. Sections 36, 10 and 11 lie outside it; they border it, but no part falls inside it. No record read names the applicant for 7672 or shows the permit was issued. BLM still lists Valar's application as pending; Valar told a reporter it has decided not to pursue the site (mine-008).
- Right of Entry No. 7672 - Geotechnical Survey (permit map, file ROE_7672_SULA_1622_02182026.pdf) (Utah Trust Lands Administration (via the RDCC project register), 2026-02-18) primary government “Right of Entry No. 7672 - 1,812.94 Acres”
- BLM Natl MLRS Rights of Way: case UTUT106784007, 'Green River Gigasite Small Modular Reactor/Data Center' (case map) (Bureau of Land Management (MLRS)) primary filing “Green River Gigasite Small Modular Reactor/Data Center”
- BLM PLSS CadNSDI first division (sections) for the listed townships (Bureau of Land Management (Cadastral National Spatial Data Infrastructure)) primary government
- RDCC project register: projects 87096-87099 (Right-of-Entry Permits #7672, #7674, #7675, #7676) and 87203 (SULA 2095) (Utah Resource Development Coordinating Committee (Public Lands Policy Coordinating Office), 2026-02-19) primary government “to evaluate the feasibility of a potential industrial and manufacturing development”
- Trump Is Considering More Data Centers on Public Lands Than Previously Known (The Washington Sun (Mara Hoplamazian and Jade Lozada), 2026-09-18) news “After considering the site, the company has decided to no longer pursue the project”
The Emery County Commission's February 17, 2026 meeting notice lists two Valar items: approving or denying a county letter of support to Valar Atomics, and approving or denying an MOU letting Valar perform site suitability testing on parcel 04-0019-0030. This indicates Valar was already studying a site in Emery County beyond the state lab by early 2026. Valar's Castle Country page says the commission backed the project unanimously. The outcome of the MOU item and the parcel's location are not given in the notice; see local.json.
- Emery County Commission Meeting (notice, February 17, 2026) (Utah Public Notice Website (Emery County Commission), 2026-02-17) primary government “allowing them to perform site suitability testing on parcel 04-0019-0030”
Minutes of the Utah Energy Research Board's 11 February 2026 meeting (held at the lab in Orangeville and online; agenda item 'Valar Supercritical CO2 Demonstration'): lab director Jaron Wallace presented a Valar proposal to build a 10 MW thermal natural-gas-powered heater to test supercritical CO2 power generation and other technologies; Valar would fund the whole $20 million project, which 'will eventually become the property of the lab', and asked for completion by June 2026. Members questioned the June timeline and asked for risk management and contract exit clauses; the board voted to enter an agreement for 'Phase 1', the first $400,000 of design, engineering and execution planning, and to re-evaluate before construction (Phase 2). The same meeting heard that Valar was 'on track for a July 4th operational deadline', that the lab was growing from five to eight employees, and that new perimeter fencing and ID checks were being added 'to meet DOE standards'. The board's 13 May 2026 minutes record no Phase 2 vote, and its 12 August 2026 agenda lists no item on the project. This project is not mentioned in any Valar document or state release read, and no air-quality permit for a 10 MW gas heater was found (DAQ's lists could not be searched, carbon_site.json).
- Utah Energy Research Board Meeting Minutes, February 11, 2026 (Utah Energy Research Board (Utah Public Notice Website), 2026-05-13) primary government “Valor Atomics will fund the entire $20 million project”
- Amended Utah Energy Research Board Meeting Wednesday, February 11, 2026 (notice and agenda) (Utah Public Notice Website, 2026-02-03) primary government “DISCUSSION/MOTION: Valar Supercritical CO2 Demonstration - Dr. Jaron Wallace”
- Utah Energy Research Board Meeting Minutes, May 13, 2026 (Utah Energy Research Board (Utah Public Notice Website), 2026-05-13) primary government
- Utah Energy Research Board Amended Agenda, August 12, 2026 (Utah Energy Research Board (Utah Public Notice Website), 2026-08-12) primary government
Ward 250 is not built to supply the grid: its July 2026 electricity demonstration used a thermoelectric generator and ran one server (ETV; plan-010). The next step Valar has shown is a heat-to-electricity program. On 11 February 2026 the Utah Energy Research Board heard a Valar proposal, presented by the lab director, to build a 10 MW (thermal) natural-gas-powered heater at the lab to test supercritical-CO2 power generation; Valar would fund the whole $20 million, the equipment would become lab property, and Valar asked for completion by June 2026. The board approved only a $400,000 'Phase 1' of design and planning, to re-evaluate before construction (gov-014). No Phase 2 approval, air permit or completion was found. Valar's job board (29 September 2026) has eight turbomachinery roles in Torrance for a 'secondary loop Brayton cycle' on helium, supercritical CO2 or air, with 'a purpose-built test facility program' (plan-011); the posts do not say where that facility will be. DOE's environmental review of Ward 250 says 'No combustion processes occur' at the reactor; a gas-fired heater at the same lab would be a separate project with its own review, and none was found.
- Utah Energy Research Board Meeting Minutes, February 11, 2026 (Utah Energy Research Board, via Utah Public Notice Website, 2026-02-11) primary government “Valor requested an aggressive completion date of June 2026.”
- Director Instrumentation, Control, and Electrical - Power Conversion (Torrance, California) (Valar Atomics (via Greenhouse), 2026-06-30) primary company “secondary loop Brayton cycle”
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (U.S. Department of Energy, Office of Nuclear Energy, 2026-04-22) primary government “No combustion processes occur.”
- Emery County takes center stage as Valar and Nvidia power historic breakthrough (ETV News (Kevin Butler), 2026-07-01) news “converted into electricity through a thermoelectric generator”
DOE's Office of Nuclear Energy lists Valar Atomics among HALEU Consortium members on a page last modified 30 December 2025. The page says 'Membership is free and is open to U.S. entities' involved in any stage of the nuclear fuel cycle that want to partner with DOE on HALEU availability, and that they apply by email. Membership is not a HALEU allocation. Valar is not named in any of DOE's three announced allocation rounds (gov-008). No record read names the supplier of Ward 250's fuel; dir-028 sets out why it is most likely the CNPS stock. (Updates gov-008.)
- HALEU Consortium Members (U.S. Department of Energy, Office of Nuclear Energy, 2025-12-30) primary government “Membership is free and is open to U.S. entities”
Contrary Research's profile of Valar (marked 'Updated November 11, 2025'; the page discloses that Contrary is an investor in Valar, orig-021) compares Valar with Oklo. It says that, like other companies using HALEU fuels, Oklo's largest risk is fuel availability, 'something Valar’s LEU-TRISO dodges'. That description matches the 4.95% LEU figure in Valar's safety agreement, dated October 2025 (dir-009). It does not match the NOVA release a week later ('HALEU TRISO', orig-040), LANL's account that NOVA used 19.9% CNPS fuel (dir-026, dir-027), or DOE's May 2026 shipping review (HALEU, up to 19.9 wt.%, safe-010). This is an investor's description, not a statement by Valar. (Updates disc-001.)
- Report: Valar Atomics Business Breakdown & Founding Story (Contrary Research, 2025-11-11) analysis “something Valar’s LEU-TRISO dodges”
Valar's QA Program Description (October 2025; status 'Approved', and Valar's post says DOE approved it) covers not just the Ward 250 reactor but a 'Valarin Fuel Fabrication Facility' at the Utah San Rafael Energy Research Center; together they are called the Valar Atomics San Rafael (VASR) Facility. It says the fuel lab will make TRISO particles in graphite compacts using German HOBEG technology with modern improvements. This matches Valar's stated aim to make its own fuel beside its reactors (orig-014) and its fuel-line pilot selection (orig-032). Whether the fuel lab has been built or authorized is not stated in the sources read; see plans_ops.json.
- Ward250 San Rafael Facility Quality Assurance Program Description (Document 100474, Rev. 02) (Valar Atomics, 2025-10) primary filing “leveraging proven German HOBEG technology with modern process improvements”
Valar's Quality Assurance Program Description (October 2025, status 'Approved'; the only published Valar document read that covers the fuel plant) treats the Ward250 reactor and the 'Valarin Fuel Fabrication Facility' as one 'VASR Facility' and scales its quality rules to the facility's 'limited operational duration of approximately 12 months' and 'low hazard category', with full implementation required before fuel receipt. It says the fuel lab will make TRISO particles in graphite compacts using German HOBEG methods and is designed to stay below DOE Hazard Category 3 (orig-038, safe-031). Set beside this: on 11 June 2026 Valar's representative told Orangeville the second building will make Valar 'the largest manufacturer of this fuel in the United States' once completed; July 2026 job posts describe 'pilot scale uranium processing equipment' and a process that 'transitions into production' (loc-019); DOE's program page still lists Valar's fuel-line selection (30 September 2025) as conditional, with no later status; POWER (25 August 2026), listing Valar among 13 projects added to DOE's Nuclear Energy Launch Pad, says Valar is developing a 'co-located Valarin facility' for TRISO particles and compacts, and notes that project scopes were not disclosed. No NSDA, safety analysis, DOE authorization or state license for the fuel plant has been published (safe-031), and no public document says how much uranium it may hold or produce. A quality program sized for a 12-month demonstration is a different thing from a production plant; the record does not show which rules would apply to production. The quality program gives no uranium inventory, enrichment or threshold for its <HC3 claim, and the safety agreement never mentions the fuel facility (it categorizes only the reactor, as Hazard Category 2), so the claim cannot be checked from Valar's public papers.
- Ward250 San Rafael Facility Quality Assurance Program Description, No. 100474, Rev 02 (October 2025) (Valar Atomics, 2025-10) primary company “limited operational duration of approximately 12 months”
- Orangeville City Council Regular Meeting Minutes, June 11, 2026 (Orangeville City, via Utah Public Notice Website, 2026-06-11) primary government “Once completed they will be the largest manufacturer of this fuel”
- TRISO Chemical Plant Process Engineer (Orangeville, Utah) (Valar Atomics (via Greenhouse), 2026-07-16) primary company
- Energy Department Fuel Line Pilot Program (U.S. Department of Energy, Office of Nuclear Energy, 2026-02-12) primary government
- NRIC Adds 13 Projects to Nuclear Energy Launch Pad (POWER Magazine (Sonal C. Patel), 2026-08-25) news “co-located Valarin facility to fabricate TRISO fuel particles and graphite compacts”
- Valar Atomics job board (public Greenhouse feed, 92 postings): Chemical Vapor Deposition Engineer (TRISO), Orangeville (Valar Atomics (via Greenhouse), 2026-07-31) primary company “as the process transitions into production”
Table 7 of Valar's Nuclear Safety Design Agreement (October 2025, page 53) set these targets: NSDA submittal 22 Sept 2025 (status 'In Review'), preliminary safety analysis (PDSA) 1 Nov 2025, final safety analysis (DSA) 6 Jan 2026, each with a 45-day DOE review; construction complete 13 April 2026; phased readiness review; initial criticality 30 June 2026. The record: DOE's PDSA approval is known only from POWER's report linking to Valar's own posts, as February 2026, and final DSA approval as 23 April 2026 (safe-006); set against the table's submittal dates plus the 45-day reviews (about mid-December 2025 and about 20 February 2026), each came roughly two months later; the reactor was flown in unfueled on 15 February 2026 (orig-030); DOE's environmental determination was signed 22 April 2026 and speaks of construction in the past tense; DOE approved the fuel-shipping package on 20 May 2026 (safe-010); Valar told the state lab board in May that DOE's readiness team had reviewed it (gov-037); DOE announced criticality on 18 June 2026 (orig-010), 12 days before the table's 30 June target (plan-005 on the exact date). The promise that mattered most publicly, criticality before 4 July 2026, holds (fund-020). None of the DOE approvals themselves (PDSA, DSA, safety requirements, readiness report, startup approval) has been published (safe-007).
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02, Appendix B, Table 7: Project Milestones (Valar Atomics, 2025-10) primary company “Initial Criticality 06/30/2026”
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (U.S. Department of Energy, Office of Nuclear Energy, 2026-04-22) primary government “Construction was confined to the existing USREL site with minimally invasive excavation.”
- Department of Energy Celebrates Second Advanced Reactor Achieving Criticality (U.S. Department of Energy, 2026-06-18) primary government
Two ETV News items from 2025, eleven months or more before the Wellington lease vote, show that a Valar project in Carbon County was in the local paper in general terms. On 17 September 2025 ETV printed the state Office of Energy Development's groundbreaking release (orig-067); its 'About Valar Atomics' paragraph says Valar 'is building America’s first nuclear gigasites', which it defines as clusters of thousands of high-temperature reactors. On 10 October 2025 an ETV article on the San Rafael lab, quoting lab director Jaron Wallace, reported that after about three years, once Valar completes its reactor and proves it can be run safely, 'their current plan is to build a manufacturing hub in Carbon County', which could bring hundreds of jobs to Carbon and Emery; it also said Valar was looking at powering data centers. The article does not say who told ETV about the Carbon plan, names no site, and says nothing about trust land or reactors in Carbon County. In sum, a Carbon County project by Valar was public in general terms from October 2025; the Wellington location, the trust-land lease and the plan for a reactor, fuel and industrial campus there were not found in any local record before the state vote (loc-011, loc-012, loc-032). The lease was approved about eleven months after the article, sooner than the 'after three years' it described.
- Valar Atomics breaks ground on test reactor at the Utah San Rafael Energy Lab (ETV News reprint of a Utah Office of Energy Development release) (ETV News, 2025-09-17) news “Valar Atomics is building America’s first nuclear gigasites”
- What’s actually happening at the Utah San Rafael Energy Lab? (Susanna Watts) (ETV News, 2025-10-10) news “their current plan is to build a manufacturing hub in Carbon County”
DOE's September 30, 2025 release is the primary record. In the second round of conditional selections for its Fuel Line Pilot Program, DOE selected Oklo, Terrestrial Energy, TRISO-X and Valar Atomics Inc (Hawthorne, CA), Valar's project being to support TRISO fuel fabrication for the Ward 250 deployment and possibly other high-temperature gas reactors. Each company pays all costs of building, running and decommissioning its fuel facility and must arrange its own nuclear feedstock; companies may apply for HALEU through DOE's HALEU Availability Program. DOE had earlier selected Standard Nuclear to build TRISO fuel facilities. World Nuclear News and Mother Jones ('one of four companies', 'last September') report the same selection, and Valar's NOVA release and Series B post list it. Set beside the record: DOE's May 2026 shipping review authorized HALEU TRISO fuel compacts to be shipped to Ward 250 from Los Alamos's criticality center in Nevada, where the NOVA test ran (safe-010); the NOVA release says Valar 'provided' the TRISO fuel, but no record read says who manufactured it; Valar's QA plan describes a 'Valarin' fuel lab at the Utah site (orig-038), for which no DOE authorization is public (safe-031); and the Series B post says Valar will make its own fuel beside its reactors (orig-070).
- Energy Department Selects Four Companies for Advanced Nuclear Fuel Line Pilot Projects (U.S. Department of Energy, 2025-09-30) primary government “To support TRISO fuel fabrication for the Ward250 reactor deployment”
- Los Alamos National Laboratory and Valar Atomics Announce Project NOVA Criticality Milestone in Nevada (Valar Atomics / LANL, 2025-11-18) primary company “Valar Atomics provided the reactor core, TRISO fuel, and system configuration.”
- US microreactor transported by air (World Nuclear News, 2026-02-18) news “a pilot programme to build advanced nuclear fuel lines”
- Mother Jones (Kiera Butler), 26 Feb 2026 (Mother Jones, 2026-02-26) news “the DOE named Valar as one of four companies”
- Safety Evaluation Report, Letter Amendment of Certificate of Compliance No. 9979 for the Model 9979 Package, Docket 26-35-9979 (U.S. Department of Energy, Packaging Certification Program, 2026-05-20) primary government “limited shipments of high-assay low-enriched uranium (HALEU) tri-structural isotropic (TRISO) fuel”
ETV News (Julie Johansen, July 9, 2025) reported the Emery County Commission's July 8, 2025 town hall in Castle Dale, requested by Valar after an MOU was signed and before its contract with the state lab was final. As reported, Valar said the company was about two years old, had a non-fueled test reactor near Los Angeles, aimed for July 4, 2026 (the nation's 250th birthday, hence 'Ward 250') with commercial development by 2028, expected about 40 employees for roughly 12 months of testing with local contractors for construction, and chose Utah because Carbon and Emery counties are the state's energy hub. A Valar slide deck posted on the state-run Utah Public Notice Website (file created July 8, 2025, server date 9 July 2025; 11 of its 12 pages are marked 'CONFIDENTIAL. DO NOT DISTRIBUTE.', yet the file is publicly posted; the public body and notice it is attached to were not identified) says the same: under 250 kW, 30 effective full-power days over 12 months in a temporary facility, commercial deployment by 2028.
- Not A Nuclear Plant Just Testing a Small Nuclear Reactor (ETV News (Emery Telcom), 2025-07-09) news “the nation’s 250 birthday, thus the name Valar Atomics Ward 250”
- Valar Atomics + SRERC in Emery County (Valar Atomics (posted on Utah Public Notice Website), 2025-07-08) primary government “Commercial Deployment by 2028”
DOE's 18 June 2025 release opening the Reactor Pilot Program (Request for Application issued that day; first applications due 21 July 2025, then rolling) says the program 'is specifically designed to foster research and development of nuclear reactors and not demonstrate reactors for commercial suitability', while also calling DOE authorization 'a fast-tracked approach to enable future commercial licensing activities' (DOE's program page says the program aims 'to fast-track commercial licensing'), that applicants bear all costs of designing, building, operating and decommissioning each test reactor, and that selection would weigh technological readiness, site evaluations, financial viability and a detailed plan to reach criticality. DOE's 16 July 2025 Fuel Line Pilot release likewise says fuel lines 'will serve for research, development, and demonstration purposes', with each company paying for its facility and 'the procurement of all nuclear material feedstock'. Set beside Valar's statements to Utah bodies: at the July 2025 town hall it spoke of commercial development by 2028 (orig-045); before the state's economic board in July 2026 its representatives spoke of plans 'to install additional commercial units in the area' (csite-024); and the Carbon County lease is for a nuclear 'campus' with fuel manufacturing (csite-007). Commercial units would fall outside the DOE pilot pathway and need NRC licensing (safe-030, csite-010); Hogan Lovells' summary of the application rules says the administration intends DOE-authorized reactors to be fast-tracked for future NRC licensing (gov-032). The Request for Application itself (FedConnect) was not read.
- Energy Department Announces New Pathway to Test Advanced Reactors (U.S. Department of Energy, 2025-06-18) primary government “not demonstrate reactors for commercial suitability”
- Energy Department Announces Pilot Program to Build Advanced U.S. Nuclear Fuel Lines and End Foreign Dependence (U.S. Department of Energy, 2025-07-16) primary government “the procurement of all nuclear material feedstock”
- U.S. Department of Energy Reactor Pilot Program (U.S. Department of Energy, Office of Nuclear Energy) primary government “fast-track commercial licensing”
The same April 2025 post says Utah, Texas and other states had expressed interest in hosting the test reactor, but that because the NRC had not exempted small test reactors, Valar was building and testing it in the Philippines instead. Four months later (August 2025) DOE's pilot selection gave Valar a U.S. path, and its first reactor to be built, Ward 250, went to Utah instead (orig-006); Ward One stayed a Philippine plan. The November 2025 NOVA release still lists the Philippine partnership, and ANS reported that month that Ward One was slated to be built there by a Philippine-incorporated Valar subsidiary. Set beside the record: as of April 2026, Philippine reporting says the reactor had not been built and the project was still seeking approval to use a site on University of the Philippines land (orig-064).
- Valar Atomics is Suing the NRC (Valar Atomics, 2025-04-07) primary company “we are building and testing this reactor in the Philippines instead”
- Los Alamos National Laboratory and Valar Atomics Announce Project NOVA Criticality Milestone in Nevada (Valar Atomics (joint announcement with LANL), 2025-11-18) primary company “partnered with the Philippines Nuclear Research Institute”
- New financing round benefits Valar (American Nuclear Society, Nuclear Newswire, 2025-11-13) news “slated to be built in the Philippines”
March 2025 (GMA News and Daily Tribune, March 24; Power Philippines): speaking as president of Valar Atomics Research Institute, Kip Mock said Valar would build a 100 kW micro high-temperature gas reactor with the Philippine Nuclear Research Institute (PNRI) as a proof of concept, not connected to the grid and not generating electricity, at a cost in the 'tens of millions' of dollars; licensing with PNRI's regulatory arm had begun; he would not give a timeline or location. A US firm, EoS Organization, gave a 192-million-peso grant to the Philippine Nuclear Science Foundation in support of the reactor, and Mindanao State University-Iligan Institute of Technology joined as a partner. TechCrunch (February 2025) reported the PNRI contract covered a test-scale reactor and two full-scale reactors. Greenpeace Philippines condemned the deal (March 27, 2025). ANS (November 2025) described Valar Atomics Research Institute as a Philippine-incorporated subsidiary. The Philippine Collegian, the University of the Philippines student paper (April 2026), reports PNRI Director Carlo Arcilla said the project had Department of Science and Technology approval, aimed to finish within two to three years, and was seeking approval from the University of the Philippines to build within PNRI, which sits on UP Diliman land, and that the scientists' group AGHAM opposed it. Set beside Valar's April 2025 statement that it was building and testing this reactor in the Philippines (orig-018): a year later no reactor had been built there. Valar's claim of the world's first binding Coordinated Research Project with PNRI (orig-066) could not be checked: PNRI's website refuses our reader.
- US nuke firm partners with PNRI to build 'research reactor' in PH (GMA News Online, 2025-03-24) news “simply a proof-of-concept”
- Valar Atomics develops Phl's first nuke reactor (Maria Bernadette Romero) (Daily Tribune, 2025-03-24) news “developing a micro high-temperature gas reactor in the Philippines”
- Valar Atomics to build experimental nuclear reactor in the Philippines (Power Philippines, 2025-03-24) news “will not be connected to the grid or generate electricity”
- Greenpeace denounces PNRI-Valar Atomics nuclear deal: 'Filipinos are not guinea pigs' (Greenpeace Philippines, 2025-03-27) analysis “The company has no track record”
- New financing round benefits Valar (American Nuclear Society, Nuclear Newswire, 2025-11-13) news “a subsidiary of Valar incorporated in the country”
- Scientists, Students Oppose Construction of US-Linked Nuclear Reactor on UP Land (Philippine Collegian (published on its Substack), 2026-04-25) news “within the next two to three years”
- Valar Atomics comes out of stealth with $19M and a pilot reactor site (Mike Butcher) (TechCrunch, 2025-02-20) news “build two full-scale reactors before the first integrated reactor comes online”
- Valar Atomics is Suing the NRC (Isaiah Taylor) (Valar Atomics, 2025-04-07) primary company “we are building and testing this reactor in the Philippines instead”
Valar's mission page lists Max Ukropina as Head of Projects. In the NOVA release (Nov 2025) he said President Trump asked industry and the labs 'to make nuclear great again'. At the Trust Lands board on 20 August 2026 (auto-transcript and approved minutes) he said Valar talked to more than 20 states; that in 2024 he came to Utah and met the Office of Energy Development, the Governor's economic office, SERDA and Carbon County (the auto-transcript renders these as 'Office of Development, the Goyo, Serta, and Carbon County'), when the plan was to make fuels from coal-plant flue gas; that the Emery lab is 'no longer just a test facility' but Valar's whole Utah operation including a fuel facility; that Valar is buying 110 acres from Emery County (mine-018); and that Valar had been careful to avoid 'overpromising' to rural communities. Set beside the record: in July 2025 Valar told Emery County about a 12-month test in a temporary facility (orig-045, mine-019), and the first public record naming Valar for the Carbon site is from August 2026 (csite-018), although by his account the company had been talking with Carbon County since 2024 (csite-028). His earlier career was not established from any readable source (his profile pages need a login).
- Mission | Valar Atomics (Valar Atomics) primary company “Max Ukropina Head of Projects”
- Los Alamos National Laboratory and Valar Atomics Announce Project NOVA Criticality Milestone in Nevada (Valar Atomics, 2025-11-18) primary company “President Trump asked industry and the labs to make nuclear great again.”
- 2026-08-20 TLA Board of Trustees Meeting Audio Transcript (auto-generated) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-08-24) primary government “It's no longer just a test facility.”
- 08.20.2026 FINAL TLA Minutes (Utah Trust Lands Administration (Utah Public Notice Website), 2026-09) primary government
In the order Carbon and Emery audiences heard it, from local reports and releases: 8 July 2025, Valar's Castle Dale town hall, reported by ETV the next day under the headline 'Not A Nuclear Plant Just Testing a Small Nuclear Reactor': a test of about 12 months with about 40 staff (orig-045). 17 September 2025, the state's groundbreaking release printed in ETV ends with Valar's own description: it 'is building America’s first nuclear gigasites', clusters of thousands of reactors (orig-067, loc-034). 10 October 2025, ETV reported that after about three years Valar's 'current plan' was a manufacturing hub in Carbon County, no site named (loc-034). 23 January 2026, a lab release printed in ETV: the site will house Valar's fuel fabrication facility as well as Ward 250. 24 February 2026, Valar's open-house release: Ward 250 is a research reactor for engineering validation and 'it is not a commercial power plant'. 7 April 2026, Emery hearing on the land sale: plans for the extra land 'not firm yet', maybe housing (ETV); fuel fabrication and manufacturing (minutes, gov-022). 9 July 2026, to the state incentive board in Salt Lake City: 'additional commercial units in the area' (gov-033); 9 and 21 July, up to 1,000 water shares for future development (mine-042). 12 August 2026: plans to eventually manufacture reactors and fuel, with mass production as the long-term goal (ETV). 19 August: 'potential plans' to produce reactors for industrial users so they can move off the grid (ETV, loc-006). 10 September: hopes to build hundreds of reactors in Carbon and Emery (loc-001). 17 September: state lease for a Carbon reactor, fuel and industrial campus approved (mine-011). None of these statements contradicts the company's published 'gigasite' aim (orig-001), and that aim was printed in the local paper in September 2025; the 2025 'just testing' framing described the first reactor only. The gap is in timing and specifics: the size of the plan reached local audiences in pieces, a Carbon County plan was reported in general terms in October 2025, and no local statement read named the Wellington site before the vote (loc-012).
- Not A Nuclear Plant Just Testing a Small Nuclear Reactor (Julie Johansen; reports the 8 July 2025 town hall) (ETV News, 2025-07-09) news “Not A Nuclear Plant Just Testing a Small Nuclear Reactor”
- Rapid construction from local contractors at Valar Atomics (USREL press release) (ETV News, 2026-01-23) primary government “will house Valar’s fuel fabrication facility”
- Valar Atomics welcomes community for reactor facility open house (Valar Atomics press release) (ETV News, 2026-02-24) primary company “it is not a commercial power plant”
- Emery Commission public hearing receives comments on the sale of property to Valar Atomics (ETV News, 2026-04-09) news
- Leaders look to coal, nuclear and new industry for growth at local energy summit (Kevin Butler) (ETV News, 2026-08-14) news “This is our home. We wanna stay here”
- Emery County Business Chamber gets an up-close look at Valar Atomics' progress (Stephanie Olsen) (ETV News, 2026-08-24) news “completely removing the risk of a meltdown”
- Community gets closer look at Valar Atomics during open house (Scottie Kraync) (ETV News, 2026-09-14) news “as we grow here in your backyard, in your community”
- Emery County Commissioners Debate Solar, Data Centers and EMS Funding (Kevin Butler) (ETV News, 2026-07-28) news
- Valar Atomics breaks ground on test reactor at the Utah San Rafael Energy Lab (Utah Office of Energy Development press release) (ETV News, 2025-09-17) primary government “Valar Atomics is building America’s first nuclear gigasites”
- What’s actually happening at the Utah San Rafael Energy Lab? (Susanna Watts) (ETV News, 2025-10-10) news “their current plan is to build a manufacturing hub in Carbon County”
Job figures on the record, in order: at the 8 July 2025 town hall, about 40 employees for roughly 12 months of testing, with local contractors for construction (ETV, 9 July 2025; orig-045); at the Carbon/Emery economic development group's September 2025 meeting, Emery Commissioner Dennis Worwood said Valar planned to hire 20-40 more local employees (ETV, 6 Oct 2025); on 10 October 2025 ETV reported the research at the lab had 'only brought in a few dozen jobs', mostly engineers from outside the area, and that a later Carbon County manufacturing hub could bring hundreds (loc-034); on 11 December 2025 Valar's Jess Housekeeper told Orangeville's council Valar was looking for 30-40 workers over the next six months (minutes); in February 2026 a USU Eastern housing study presented to a local housing committee counted Valar as planning to employ about 40 technicians and contractors (ETV, 24 Feb 2026); on 15 April 2026 Housekeeper told Ferron's council that Valar employed 120 people in Emery County, 'a lot' of them not living in Utah, with 15-20 full-time employees at the site plus construction workers and electricians (minutes); on 9 July 2026 the state's economic development board approved a tax credit on Valar's projection of 275 jobs at an average wage of $137,567 in Emery County with $1.3 billion of investment (csite-024); on 13 August 2026 Valar's Harry Hansen told the Orangeville council Valar had recently hired 40 new employees from the Castle Country area (ETV, 20 Aug); on 19 August Valar told the Carbon County Commission it had hired local residents from closed coal operations (minutes); on 10 September Max Ukropina said Valar has hired dozens of community members (ETV, 14 Sept). Emery Commissioner Jordan Leonard said in August that local hiring by Valar had drawn workers from other local jobs, opening places for returning families (ETV, 14 Aug). No figure for jobs at the Carbon County campus appears in the Trust Lands records summarized in carbon_site.json. The figures are not in conflict on their face: they count different things (site staff, contractors, everyone working for Valar in Emery) at different stages, and the April figure shows that many of the people then working for Valar in Emery did not live in Utah. The 275-job figure is a projection tied to a state tax credit that is paid only after the new tax revenue comes in (csite-024); no public count of Valar's Utah payroll exists to check the local figures against.
- The importance of the Economic Development Committee stressed by many (ETV News, 2025-10-06) news “plans to hire 20-40 more local employees”
- Housing Committee hears about coming population growth and housing crisis (ETV News, 2026-02-24) news “planning to employ about 40 technicians and contractors”
- Growth, industry and community issues highlight Orangeville council meeting (Kevin Butler) (ETV News, 2026-08-20) news
- Community gets closer look at Valar Atomics during open house (Scottie Kraync) (ETV News, 2026-09-14) news “as we grow here in your backyard, in your community”
- Leaders look to coal, nuclear and new industry for growth at local energy summit (Kevin Butler) (ETV News, 2026-08-14) news “some workers have left other positions in the community”
- Not A Nuclear Plant Just Testing a Small Nuclear Reactor (Julie Johansen; reports the 8 July 2025 town hall) (ETV News, 2025-07-09) news “hire about 40 employees for about 12 months in the actual testing”
- What’s actually happening at the Utah San Rafael Energy Lab? (Susanna Watts) (ETV News, 2025-10-10) news “only brought in a few dozen jobs”
- December 11, 2025 City Council Minutes (Orangeville) (Orangeville City, 2025-12-11) primary government “looking for 30-40 workers over the next 6 months”
- Ferron City Council Minutes, April 15, 2026 (scanned, read as page images) (Ferron City, 2026-04-15) primary government “We actively employ 120 people. A lot of those are NOT living in Utah.”
- Aug 19, 2026 Commission Meeting Minutes (Carbon County Board of Commissioners; scanned, read as page images) (Carbon County Commission, 2026-08-19) primary government “actively hired local residents from closed coal assets”
2024-2025: the California filing gives the business as nuclear heat for fuel synthesis (orig-052); the December 2024 homepage leads with hydrogen and synthetic fuel from captured CO2 (orig-062); TechCrunch (February 2025) reported the aim of cheap hydrogen and synthetic fuels at up to 900 C; Valar's head of projects told the Trust Lands board that its 2024 Utah plan was to make fuels from coal-plant flue gas (mine-018, ppl-006); its December 2025 lobbying registration still describes 'clean hydrocarbon fuel production'. 2026: the July 1 event powered one NVIDIA chip and announced a 30 MW data-center study (orig-042); its BLM applications are titled 'Small Modular Reactor/Data Center' (mine-006); the Series B post leads with AI infrastructure; the Carbon County plan lists reactors, fuel manufacturing, hydrogen and synthetic fuels, data centers and steel (csite-001, csite-007). No record read shows Valar producing any hydrogen or synthetic fuel, and its homepage still offers hydrogen through a sulfur-iodine cycle, a process that an investor-published profile says has never been deployed commercially (orig-024). Plans can change honestly; the record shows the headline product moving from fuels toward AI power while the fuel claims stay on the site.
- Valar Atomics Inc. Hawthorne, CA - filing information (third-party republication of California Secretary of State data) (bizprofile.net, 2026-03-25) analysis “Nuclear Heat for Fuel Synthesis and other applications”
- The New Atomic Age | Valar Atomics (live homepage) (Valar Atomics) primary company “When paired with our sulfur-iodine cycle process, our reactors produce cheap and abundant hydrogen.”
- LD-1 Lobbying Registration: Atlas Crossing LLC for Valar Atomics Inc. (effective 12/8/2025) (Clerk of the House / Secretary of the Senate (lda.gov), 2026-01-07) primary filing “Scaling nuclear energy for heavy industrial power and clean hydrocarbon fuel production.”
- Announcing our $1B Series B Led By Sequoia (Isaiah Taylor) (Valar Atomics, 2026-08-04) primary company “the first and only time that an advanced reactor has directly powered AI infrastructure”
- Valar Atomics comes out of stealth with $19M and a pilot reactor site (Mike Butcher) (TechCrunch, 2025-02-20) news “you can produce hydrogen very cheaply, and you unlock all sorts of things”