Fact plan-021
HELD: 'First Reactor online by July 4, 2026' (Valar's July 2025 deck to Emery County): DOE announced criticality on 18 June 2026 (orig-010), ahead of Valar's own 30 June target (plan-004). HELD AS A PLAN, UNCHECKED: '30 EFPD in 12 months' (deck) matches Valar's June 2026 draft (orig-035); no run log is public (plan-006, plan-007). CHANGED: 'in a temporary facility' (deck): the approved papers still plan to take Ward 250 down after about a year of running (plan-003), but what was built is a 55-foot modular reactor complex on engineered foundations with more than 4,000 cubic yards of concrete poured, beside a fuel plant (plan-002), on a site Valar now calls home and is expanding (plan-003, ppl-006); '40 employees for about 12 months' (July 2025) became a projection of 275 jobs and $1.3 billion for a state tax credit (loc-004, fund-017). LATE: DOE safety approvals came about two months behind Valar's own schedule, by the only report of their dates (plan-004). NOT DELIVERED: the Philippine reactor announced in March 2025 (orig-064); the gas-fired supercritical-CO2 test heater Valar wanted done by June 2026, approved for design only (plan-018); fuel from Valar's own line: Ward 250's fuel came from a federal site in Nevada (plan-014). DROPPED: the 10,270-acre Green River gigasite, per Valar, though BLM still lists it pending (plan-017, mine-008). NOT YET DUE, NO FILING: 'Commercial Deployment by 2028' (deck), the 30 MW NVIDIA data center (plan-010), 'hundreds of reactors' in Carbon and Emery (loc-001). CONFLICTING: the date of full power (plan-009) and, on paper, the fuel's enrichment (plan-014).
- Valar Atomics + SRERC in Emery County (slide deck, marked confidential, posted on the Utah Public Notice Website) (Valar Atomics, via Utah Public Notice Website, 2025-07-08) primary company “operates for 30EFPD, in 12 months in a temporary facility”
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02, Appendix B, Table 7 (Valar Atomics, 2025-10) primary company “Initial Criticality 06/30/2026”
- Rapid construction from local contractors at Valar Atomics (USREL press release, Energy Corner) (Utah San Rafael Energy Lab and Valar Atomics, via ETV News, 2026-01-23) primary government “more than 4,000 cubic yards of concrete to date for the foundations”
- Utah Energy Research Board Meeting Minutes, February 11, 2026 (Utah Energy Research Board, via Utah Public Notice Website, 2026-02-11) primary government
- BLM National MLRS Land Use Authorizations - Rights-of-Way (query: customer name contains 'VALAR', run 2026-09-29) (U.S. Bureau of Land Management, 2026-09-15) primary government