374 facts · 512 sources · updated 2026-09-30

Claims vs Record disc-008

unresolvedsafety The accident math assumes the public stays 400 m away; the lab is 20.6 acres, and officials called the fence buffer enough

What was said

What the record shows

The gap: The worst-case analysis in Valar's draft paper assumes no member of the public is closer than 400 m, which it calls 'the nearest point of public access'; no DOE document read sets 400 m as a required boundary, and DOE's approved analysis may use a different one. The reactor's fence encloses about 2 acres of a 20.6-acre state lab, far less than the roughly 124 acres a 400 m circle covers. An access-control agreement, state control of surrounding land, or Valar's purchase of the adjacent 112 acres (which the lab director linked to 'contiguous ownership to maintain safety') may cover the difference; no record read shows any of them in place. Local officials, as reported, told residents the fence line is buffer enough.
In plain termsIn an accident, distance is protection: the farther away people are, the smaller the dose. Valar's worst-case math places the nearest member of the public 400 meters from the reactor. A circle that size covers about 124 acres, but the state lab the reactor sits on is 20.6 acres, and the reactor's fenced area about 2. So the math assumes the public is kept off land outside the lab, and no public record says who does that. Residents who asked about a buffer zone were told, as the local paper reported, that the fence is buffer enough. The land may be controlled by an agreement, or covered by the land next door that Valar is buying; the records read do not say.

Why it matters: If people can stand closer than 400 m, the paper's own numbers show the air concentration, and so the dose, rises steeply (16 times at 100 m).

What would settle it: The site description and public-access control in the approved DSA (FOIA to DOE Idaho Operations Office); GRAMA to the Utah Office of Energy Development for the USREL site plan, Valar's use agreement and any access-control agreements; the Emery County Recorder's deed for parcel 04-0019-0030.

facts safe-014, ppl-021, mine-035, gov-022, loc-035, mine-046 · checked 2026-09-29: Defence pass 2026-09-29: Defended: looked for an access-control arrangement in the NSDA, CX, Emery minutes and the lab pages; the only lead is the lab director's 'contiguous ownership' remark and the pending purchase of parcel 04-0019-0030 (disc-055). Nothing shows who controls public access out to 400 m. Status stays unresolved; summary line literally true. | Earlier verify pass: Re-read on 2026-09-29: NSDA pp. 10, 36-38 (quotes exact), CX pp. 1-2, ETV 9 Apr 2026 and 10 Oct 2025, Emery 7 Apr 2026 minutes (the minutes record a different answer to the buffer question than ETV; both are given). Geometry re-checked. Private residents who asked questions are not named. | Correction 2026-09-29 (calculation audit): claim pages corrected to 10, 11 and 39; dispersion-factor record reworded ('under 5 rem'; chi/Q not a concentration) with the 400 m check added. | Correction 2026-09-29 (wording review): verification wording updated ('summary line'). Correction 2026-10-01 (precision review): wording made more exact against the cited records.