VALAR WATCH
Key findingsTheir claims, annotatedEvidenceTake action
374 facts · 512 sources · updated 2026-09-30

Claims vs Record disc-001

documented conflicttechnical Ward 250's fuel: Valar's safety agreement lists 4.95% uranium; its Los Alamos release and DOE's shipping review say HALEU

What was said

What the record shows

The gap: Valar's only public safety paper for Ward 250 lists 4.95% (ordinary) uranium. Valar's own Los Alamos release a month later calls the same fuel HALEU, and DOE's shipping review cleared HALEU of up to 19.9% U-235 for use in Ward 250. A reading favourable to the company, which Valar has not stated, is that the paper's fuel figures were preliminary design values to be corrected in a later safety analysis DOE reviewed; it is plausible: the paper calls its fuel assumptions preliminary. It does not remove the conflict: the NOVA core began its approach to criticality with HALEU TRISO fuel Valar says it provided on 12 November 2025, 30 days after the 4.95% paper was posted, and no correction to the public paper was found. Whether DOE's approved safety analysis describes HALEU is not shown by any public record.
In plain termsReactor fuel is graded by how much of the uranium is the kind that splits (U-235). Ordinary power-plant fuel has up to 5%; HALEU has 5% to just under 20%. Ward 250 burns TRISO fuel: poppy-seed-sized beads of uranium, each sealed in layers of carbon and ceramic and pressed into small pellets. Valar's only public safety paper says the uranium is 4.95%, the ordinary grade. Valar's own Los Alamos announcement a month later calls the same fuel HALEU, and DOE cleared fuel blocks for Ward 250 enriched up to 19.9%, about four times richer. A possible explanation, which Valar has not stated, is that the paper was an early draft whose fuel numbers were updated in a later safety analysis DOE reviewed; the paper does call its fuel assumptions 'preliminary.' That may be so, but the later analysis is not public and no correction to the public paper was found. The one safety document the public can read describes different fuel from the fuel DOE cleared for this reactor.

Why it matters: The fuel grade changes the reactor's physics and how much fissile uranium sits in Emery County. The public safety paper does not describe that fuel.

What would settle it: FOIA to DOE Idaho Operations Office for the fuel specification and core description in Ward 250's approved PDSA and final DSA, the Technical Safety Requirements and DOE's Safety Evaluation Report; FOIA to DOE Savannah River Operations Office and NNSA Nevada Field Office for the shipment records under the Model 9979 letter amendment; or Valar publishing the as-loaded enrichment.

facts orig-008, orig-009, orig-034, orig-040, safe-010, safe-011, dir-009, plan-014, csite-007, safe-025, orig-033 · checked 2026-09-29: Defence pass 2026-09-29: Defended from Valar's side: re-read NSDA pp. 11, 25, 52 (fuel assumptions 'preliminary'; qualification basis AGR-1/2 data; update clause tied to AGR-spec TRISO), NOVA release (approach to criticality from 12 Nov 2025; 'same fuel'; Valar provided the TRISO fuel) and the SER (shipments from NCERC in Nevada). No Valar statement explaining the 4.95% line was found on its site or in the documents read. The design-draft reading is plausible, but the conflict survives because HALEU fuel was in use 30 days after the posting and no revision of the paper was found. Summary line checked: literally true (NOVA says HALEU; NSDA says 4.95%). | Earlier verify pass: Re-read on 2026-09-29 (saved copies): NOVA release ('HALEU TRISO-fueled'; 'the same fuel, moderator, and reactivity-control scheme as Ward250'), NSDA Table 6 p. 52 and p. 11, DOE SER (19.9 wt.% maximum; 234.94 g per block; end use in Ward 250), DOE HALEU page, TLA September memo. Restructured from the seeded entry: the NSDA is now shown as a Valar claim beside the NOVA claim, and DOE's shipping review as the record, which is what the documents are. The SER is DOE's review recommending the letter amendment; the amendment letter itself was not read. | Correction 2026-09-29 (calculation audit): 'Against that reading' record no longer infers the HALEU fuel existed on 13 Oct 2025; states the 30-day interval instead. | Correction 2026-09-29 (wording review): gap no longer infers the HALEU fuel existed at posting; states the 30-day interval; 'never corrected' now 'no correction found'; verification wording updated ('summary line'). Correction 2026-09-30 (source objectivity review): reworded why it matters; reworded the plain-language text; reworded the summary line; reworded the gap.